Resolved
RESOLVED – That 1. The contents of the report be noted. 2. The suggested amendment to KPI’s CP36, CP41 and CP42 be approved. 3. The suggested addition of KPI CP43 be approved.
Policy and Resources Committee noted this item on Tuesday 9 July 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That 1. The contents of the report be noted. 2. The suggested amendment to KPI’s CP36, CP41 and CP42 be approved. 3. The suggested addition of KPI CP43 be approved.
1.1This report is to update the Committee on the Q4 and end of year Performance Outturn for the Key Performance Indicators (KPIs) which make up the Corporate Plan, for the period 1 April 2023 to 31 March 2024.
2.1It is recommended that the Committee notes the contents of this report. 2.2. It is recommended that the Committee considers the suggested amendment to KPI’s CP36, CP41 and CP42 (para 4.12). 2.3. It is recommended that the Committee considers the suggested addition of KPI CP43 (para 4.13).
3.1This report sets out the performance of the Key Performance indicators at Quarter 4 and end of year for the period 1 April 2023 to 31 March 2024. 4. DETAIL
4.1The Council Vision 2022-2026 was approved at Full Councill in March 2022. To support the Vision, we need a comprehensive and meaningful set of performance measures which allow us to identify how well we are delivering across a full range of services. Two kinds of indicators were agreed at the Policy and Finance Committee on 17 March 2022. The first of these are annual indicators and will primarily update the progress against strategic milestones. In addition to this ‘key performance indicators’ (KPIs) will be reported to committees every quarter. These KPIs are known as our Corporate Plan.
4.2A short report and appendix will go to each of the other Committees in the cycle of meetings after each quarter has ended. This appendix will only contain the indicators which are relevant to each Committee.
4.3A full report showing quarterly performance against all indicators (which are measured at that quarter) will go to the relevant Policy and Finance Committee meeting at the end of the cycle of the other Committee meetings. Members of the other Committees will be able to give comments or ask questions of officers about the KPI indicators that are relevant to their committee and these can be referred to the Policy and Finance Committee for consideration if deemed necessary.
4.4The Committee meetings that will receive Q4 KPI reports are as follows:
Committee meeting Meeting date Indicators to receive report on Planning Committee 5 June 2024 10 (CP26, CP27, CP28, CP29, CP30, CP31, CP32, CP33, CP34, CP35) Planning Policy Committee 6 June 2024 1 (CP36) Economy Committee 13 June 2024 2 (CP41, CP42) Housing & Wellbeing 18 June 2024 8 (CP11, CP15, CP16, CP17, Committee CP18, CP19, CP20, CP21) Environment Committee 20 June 2024 10 (CP12, CP13, CP37, CP38, CP39, CP40, CP22, CP23, CP24, CP25) Corporate Support 27 June 2024 10 (CP1, CP2, CP3, CP4, CP5, Committee CP6, CP7, CP8, CP9, CP10) Licensing Committee 28 June 2024 1 (CP14) Policy & Finance 9 July 2024 All 42 indicators Committee
4.5Thresholds are used to establish which category of performance each indicator is within.
Achieved target 100% or above target figure Didn’t achieve target but within 15% range 85%-99.9% below target figure Didn’t achieve target by more than 15% 85% or less target figure
4.6There are 42 Key Performance indicators and 41 indicators are measured at Q4. 4.7. Appendix A gives full commentary for each indicator. This appendix shows the figures for Q1, Q2 and Q3 and the figures and commentary for Q4 and the end of the year. The status has been determined by the end of year figure.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Q4 KPI reportAppendix A | 455 KB | Download |
PDF |
Key Performance Indicators 2022-2026: Quarter 4 End of Year Performance Report for the Period 1 April 2023 to 31 March 2024Report | 182 KB | DownloadRead as text |
Follow Policy and Resources Committee at Arun and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Start TimesRESOLVED That its start times for meetings for this new Municipal Year be 6.00 pm. | Decided | Open |
| 2 Jul 2026 | Adoption of the Resolution FrameworkRESOLVED - To (1) Approve the adoption of the Resolution Framework as the Council’s primary approach for managing con... | Approved | Open |
| 2 Jul 2026 | Budget 2027/27 - ProcessRESOLVED To approve the budget process for 2027/28 as outlined in the report. | Approved | Open |
| 12 Mar 2026 | Pay Policy Statement 2026RESOLVED That the contents of the /27 as set out in Appendix 1 be noted. The Committee then RECOMMEND TO FULL COUNCIL... | Noted | Open |
| 12 Mar 2026 | Q3 Performance Report for the Key Performance Indicators (KPIs) which form part of the Council's Vision 2022-2026RESOLVED – That it (1) Approves that we no longer collect information for KPI CP36, the number of new homes completed... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.