CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Arun District Council
Planning Policy Committee, Wednesday 26 November 2025 at 6.00pm

Arun Brownfield Land Register

Noted Planning 2 papers

AI summaryPlanning Policy Committee noted the 2025 Brownfield Land Register, now listing 31 sites, and agreed to keep it under review for any future Part 2 sites eligible for permission in principle.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted31 sites listed on 2025 Part 1 register
MoneyNot stated
What happens nextKeep register under reviewReview for Part 2 sites and permission in principle
Who it affectsBrownfield landowners and developersSites eligible for permission in principle

What was decided

The Committee noted the 2025 Brownfield Land Register (Part 1), which now contains 31 sites, up from 24. Report 4.3

The Committee agreed to keep the register under review for preparation of a Part 2 register and permission in principle, should any suitable sites be identified. Report 4.5

Why

The Council has a duty to review the register at least once a year, removing sites that no longer meet the criteria and adding new ones that do. Report 4.4

Sites on the register that are deliverable within 5 years can be counted towards the 5-year housing land supply, so an up-to-date register supports the Authority Monitoring Report. Report 4.6, P7

What happens next

The Council will continue reviewing existing and newly proposed sites and will consider whether any should be added to Part 2 of the register. Report 4.5

If suitable sites are identified for Part 2, the Council will carry out the required consultation and publicity under the 2017 Regulations. Report 4.2

Options considered

  • Rejected: Add a site to Part 2 of the register (granting permission in principle). The Council has not identified sites suitable for permission in principle for 2025 Report 4.3

Implications

  • Legal: Inclusion on the register and any future Part 2 listing must follow the Town and Country Planning (Brownfield Land Register) Regulations 2017 (as amended), including consultation and publicity. Report 4.2
  • Legal: Part 2 sites are limited to up to 9 homes, less than 1,000 sqm of commercial floorspace, and less than 1 hectare, and cannot be major development, require Environmental Impact Assessment, affect European Habitats, or already have planning permission. Report 4.2
  • Other: An up-to-date register complements the 5-year housing land supply and supports the Authority Monitoring Report and HELAA. Report 4.6

Who and where

  • Owners and developers of brownfield land in the district Report 4.2, 4.3
  • Planning applicants seeking permission in principle on small brownfield sites Report 4.2
  • The Council's housing land supply and monitoring function Report 4.6

Timeline

  • 2025: 2025 Brownfield Land Register published, containing 31 sites Report 4.3
  • At least once a year: The Council must review the register Report 4.4

Plain English for the jargon

  • Brownfield Land Register: A list of previously developed land that local planning authorities consider suitable for residential or other development.
  • Part 1: The standard register of brownfield sites; no permission in principle is granted by inclusion.
  • Part 2: Sites granted permission in principle, subject to qualifying criteria and consultation.
  • Permission in Principle (PiP): A streamlined planning consent confirming the principle of development on a site, subject to size and use limits.
  • DEL: A marker on the register showing a site is deliverable and can count towards the 5-year housing land supply.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item379

Resolved

RESOLVED to: i. Note the 2025 Brownfield Land Register (Part 1); and ii. Keep the Brownfield Land Register under review regarding preparation of a (Part 2) register and ‘permission in principle’ (including the carrying out of consultation and publicity requirements), should any suitable sites be identified, in accordance with the Town and Country Planning (Brownfield Land Register) Regulations 2017 (as amended).
Word for word from the decision Arun published for this meeting. Source: democracy.arun.gov.uk

Follow this further

Built from Arun's papers

What the report saysPro

Report to Planning Policy Committee

Arun District Council

Brownfield Land Register (Part 1)

November 2025 Contents

Section Title Page

1.0Introduction 3

2.0Brownfield Land Register Requirements 4

3.0Arun District Council Brownfield Land Register 6

4.0Next Steps 17

2 1.0 Introduction

1.1The Government is seeking to maximise the numbers of new homes built on brownfield (also known as ‘previously developed’) land and make the most efficient use of land. The Town & Country Planning (Brownfield Land Register) Regulations 2017 (hereafter referred to as ‘the Regulations’) introduced a duty for local planning authorities (LPAs) to prepare, maintain and publish a register of brownfield land within their areas and where appropriate, introduced ‘Permission in Principle’ (PiP) as a new route to obtaining planning permission for these sites.

1.2The aim of the Brownfield Land Register is to ensure standardised information and data about brownfield land that is suitable and available for residential development, is made accessible nationally and is kept up to date. The Government envisages that this will improve the quality and consistency of data held by LPAs, which will help to provide certainty for developers and communities, encouraging investment in local areas.

1.3Brownfield Land Registers also offer the potential for granting PiP on suitable sites through allocation in a Part 2 register. Where sites are granted a PiP, it must then be followed by an application for Technical Details Consent (TDC) to agree the details of the scheme before obtaining full planning permission.

1.4The sites on the Brownfield Land Register for Arun District Council have been included in accordance with the Regulations. Further information on the requirements is set out later in this document. It should be noted that Brownfield Land Registers include all brownfield sites that are suitable for residential development irrespective of their planning status. However, inclusion in Part 1 of the register does not automatically mean that a site will gain planning permission for residential use.

1.5The Brownfield Land Register complements intentions set out in the National Planning Policy Framework (NPPF 2024) which encourage effective use of land in meeting the need for homes and other uses, including making as much use as possible of previously developed or ‘brownfield’ land.

1.6In addition, the strategy and policies of the adopted Arun Local Plan 2011-2031 seek to minimise impacts on the countryside and environment and encourage, where possible, development to make best use of available brownfield land and buildings, provided it is not of high environmental value.

3 2.0 Brownfield Land Register Requirements

Definition of previously developed land

2.1‘Annex 2 Glossary’ of the NPPF sets out the definition of “previously developed land” as:

“Land which has been lawfully developed and is or was occupied by a permanent structure and any fixed surface infrastructure associated with it, including the curtilage of the developed land (although it should not be assumed that the whole of the curtilage should be developed). It also includes land comprising large areas of fixed surface infrastructure such as large areas of hardstanding which have been lawfully developed. Previously developed land excludes: land that is or was last occupied by agricultural or forestry buildings; land that has been developed for minerals extraction or waste disposal by landfill, where provision for restoration has been made through development management procedures; land in built-up areas such as residential gardens, parks, recreation grounds and allotments; and land that was previously developed but where the remains of the permanent structure or fixed surface structure have blended into the landscape.”

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
08.1 Brownfield-Land-Register-Document_2025Report 227 KB DownloadRead as text
PDF
Arun Brownfield Land RegisterReport 121 KB Download

At this meeting

Whole meeting

Who was there

10 of 27 attended
JG
Julie GrievesOfficer, expected
MP
Mark PengellyOfficer, in attendance
VH
Victoria HobdayOfficer, expected
JB
Jon BestOfficer, in attendance
RS
Richard ShermanOfficer, expected
DE
David EastonOfficer, expected
AB
Antony BadenOfficer, expected
NC
Neil CrowtherOfficer, in attendance
KR
Karl RobertsOfficer, expected
MW
Martyn WhiteOfficer, in attendance
DB
Daniel BainbridgeOfficer, expected
GY
Councillor Gill YeatesChair, present

All 27 on the meeting page

On this subject at Arun

Search all
  1. Arun Brownfield Land RegisterThis decision
  2. Arun Brownfield Land Register (BLR)Noted

More from Arun Planning Policy Committee

All decisions
MeetingDecisionOutcome
26 Mar 2026 Arun Community Infrastructure Levy - Infrastructure Investment Plan (2024-2026)RESOLVED to approve 1. Moving the Palmer Road Angmering sports hub project from the IIP Baseline longlist to the IIP ... Approved Open
26 Mar 2026 Arun Biodiversity Action PlanRESOLVED to agree to 1. Endorse the (BAP) and approve the document for publication. 2. Delegate authority to the Grou... Agreed Open
2 Feb 2026 Committee Revenue Budget 2026/27RESOLVED to Agree the 2026/27 Revenue Budget as set out in Appendix A and recommends to the Policy and Resources Comm... Agreed Open
2 Feb 2026 Consultation on Draft Conservation Area Character AppraisalsRESOLVED i) The draft conservation area character appraisals for Aldingbourne, Norton, Shripney, and Angmering (three... Agreed Open
12 Jun 2025 Start TimesRESOLVED That the start time of all remaining meetings of the Committee for 2025/26 would be 6pm. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies