Arun Community Infrastructure Levy - Infrastructure Investment Plan (2024-2026)
ApprovedPlanning1 paper
AI summaryArun Planning Policy Committee approved moving the Palmer Road Angmering Sports Hub to the Infrastructure Investment Plan Priority shortlist and authorised £1 million of Community Infrastructure Levy funding for the project.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSports hub moves to priority list
Money£1 millionCIL funding authorised
What happens nextProject starts April 2026Pre construction in 2026/27
Who it affectsAngmering residents and usersFootball and wider community
What was decided
The committee approved moving the Palmer Road Angmering Sports Hub from the Infrastructure Investment Plan Baseline longlist to the Priority shortlist. Report 2.1, P3
The committee authorised £1 million of Community Infrastructure Levy funding for the Palmer Road Angmering Sports Hub project. Report 2.1, P3, 4.11
Why
The project programme is due to begin in April 2026, meaning funding is required earlier than anticipated in the Infrastructure Investment Plan. Report 3.1, 3.2
Planning permission for the sports hub has been granted and Full Council approved a £10m capital budget on 16 July 2025, showing council commitment to the scheme. Report 4.9
Significant development in Angmering has generated substantial CIL contributions which, under CIL regulations, should support the local community by mitigating development impacts. Report 4.8
What happens next
The pre construction contract is scheduled to commence in the 2026/27 financial year, which includes the detailed design stage. Report 4.6
After the £1m contribution, over £330,000 will remain in the Arun District Council CIL account, and this is expected to increase significantly in the coming year. Report 4.12
Any future spend on this project will be considered alongside other potential projects through the agreed CIL assessment processes. Report 4.12
The money
£1 million Approved CIL contribution towards the Palmer Road Angmering Sports Hub project Report 4.11, P3
£1m CIL funding drawdown requested, with £1.33m currently held in the council's CIL portion Report 9.1
£10m Total estimated scheme cost, capital budget approved by Full Council on 16 July 2025 Report 4.9
£3m Available through section 106 developer contributions, of which £2m received to date Report 4.9
over £330,000 Will remain in the ADC CIL account after the £1m contribution Report 4.12
Options considered
Rejected: Do nothing. Failure to part fund from the ADC CIL account would jeopardise delivery of a project the council has already committed to Report 7.1, P28
Implications
Financial: After the £1m contribution, over £330,000 remains in the ADC CIL account and is expected to increase in the coming year. Report 4.12, 9.1
Legal: There are no governance or legal implications arising from this update. Report 10.1
Equalities: The proposal will have a positive impact on community health and wellbeing through supporting infrastructure delivery. Report 14.1
Climate: There are no direct adverse implications for climate change or environment arising from this report. Report 15.1
Risk: Implementing the recommendation will help ensure this important project is delivered. Report 8.1
Staffing: There are no implications arising for Human Resources. Report 11.1
Who and where
Angmering residents and the wider district Report 4.8
Local football players and sports facility users Report 4.3
Timeline
May 2019: Football Foundation Local Football Facilities Plan identified Palmer Road as a priority project Report 4.3
16 July 2025: Full Council approved £10m capital budget, subject to an affordability review and agreed by the section 151 officer Report 4.9
April 2026: Project programme due to begin Report 3.1
2026/27 financial year: Pre construction contract scheduled to commence, including the detailed design stage Report 4.6
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge on development used to fund local infrastructure
IIP: Infrastructure Investment Plan, the council's three year programme of prioritised infrastructure projects eligible for CIL funding
section 106: Planning obligations under Section 106 of the Town and Country Planning Act, requiring developers to contribute to local infrastructure
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item690
Resolved
RESOLVED to approve 1. Moving the Palmer Road Angmering sports hub project from the IIP Baseline longlist to the IIP Priority shortlist. 2. The authorisation of £1 million CIL funding required for the Palmer Road Angmering Sports Hub project.
Word for word from the decision Arun published for this meeting.Source: democracy.arun.gov.uk
1.1This report provides an update on the delivery of the Palmer Road Angmering Sports Hub which is currently identified on the Infrastructure Investment Plan longlist. This report seeks Committee approval for moving the project to the IIP shortlist and for the CIL funding required to support the project’s delivery. The report confirms the level of funding now being requested from the ADC CIL pot, which, due to its scale, requires Committee endorsement.
Recommendations
2.1The Planning Policy Committee resolves to approve:
• Moving the Palmer Road Angmering sports hub project from the IIP Baseline longlist to the IIP Priority shortlist • The authorisation of £1 million CIL funding required for the Palmer Road Angmering Sports Hub project.
Executive summary
3.1This report sets out the CIL funding requirements for the Palmer Road Angmering Sports Hub. The project programme is due to begin in April 2026, meaning funding is required earlier than anticipated in the IIP.
3.2The change in project delivery timeline necessitates an update to the IIP, moving the Palmer Road Angmering Sports Hub project from the Baseline longlist to the Priority shortlist.
3.3A CIL contribution of £1 million is required to contribute towards the delivery of the project, with the potential for additional funding to be considered later in the year, subject to CIL funding availability.
4. DETAIL
IIP Priority Shortlist 4.1 ADC became a CIL Charging Authority in April 2020. The CIL Governance process sets out how CIL receipts will be prioritised and allocated towards infrastructure projects. This process includes Arun District Council undertaking informal consultations with infrastructure providers and Town/Parish Councils through inviting project bids and supporting evidence, to help identify a three year programme of infrastructure projects eligible for funding and prioritisation. This programme is called the Infrastructure Investment Plan.
4.2There are currently five infrastructure projects on the IIP Priority shortlist (2025/2027), two of which are now completed. The shortlist is attached as background document 1.
• Relocation or redevelopment of Littlehampton Fire Station 16/IDP/ES
• Littlehampton Waste Recycling Centre 12a/IDP/WM
• Route 8: Active Travel Route (safe cycling) from Arundel to Littlehampton via Ford Station 18/ADC/TI
• Complete - Lion’s Den Play Park in Littlehampton 10/ADC/GI
• Complete - Ferring Village play area improvements 79/ADC/GI
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Committee Revenue Budget 2026/27RESOLVED to Agree the 2026/27 Revenue Budget as set out in Appendix A and recommends to the Policy and Resources Comm...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.