RESOLVED That Cabinet: a) Notes and approves the amended timescales for the period of formal consultation for the implementation of the first Selective Licensing Scheme of private landlords; b) Notes that the consultation will focus on two priority areas, Phase 1 Stanton Hill and Phase 2 Sutton Central areas of the District.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
HEADING: SELECTIVE LICENSING CONSULTATION PORTFOLIO HOUSING AND ASSET MANAGEMENT HOLDER: KEY DECISION: NO SUBJECT TO CALL-IN: NO
1. PURPOSE OF REPORT To update members of the changes in relation to the consultation period of the proposed Selective Licensing Scheme as previously agreed at Cabinet in November 2015, and the proposed designated areas.
2. RECOMMENDATION(S)
(1) To note and approve the amended timescales for the period of formal consultation for the implementation of the first Selective Licensing Scheme of private landlords, and (2) To note the consultation will focus on two priority areas, Phase 1 Stanton Hill, and Phase 2 Sutton Central areas of the District.
3. REASONS FOR RECOMMENDATION(S) The Cabinet report presented in November 2015 proposed a six month period of consultation in relation to the proposed implementation of a selective licensing scheme across four areas of the district, set out in Phases 1 to 4. As a result of more detailed analysis it is now proposed that the selective licensing scheme and any application to the Secretary of State is initially focussed on the two priority areas, Phase 1 Stanton Hill and Phase 2 Sutton Central. This is because there is not yet sufficient information or evidence in the Phase 3 & 4 areas for effective consultation to take place, and the information is not yet robust enough for the designation of these areas to be either confirmed by the Secretary of State or fall within the Secretary of State’s general approval.
The consultation will therefore be over a 12 week period which is considered to be sufficient time for residents to respond in these two priority areas, and not the full six month period as previously planned for the four areas consultation.
4. ALTERNATIVE OPTIONS CONSIDERED (with reasons why not adopted) No alternative options have been considered as Members have already formally given approval for the public consultation to proceed, therefore the consultation will commence in accordance with that approval, the only difference being the smaller priority areas and reduced timescale.
5. BACKGROUND At the Cabinet Meeting held on 5th November 2015, Members agreed to a 6 month period of public consultation for the implementation of a Selective Licensing Scheme of private landlords for the Stanton Hill (Phase 1), Sutton Town Centre (Phase 2), and Sutton North (Phase 3) and Sutton East (Phase 4) areas of the District, as detailed in the Private Sector Renewal Strategy. This was due to commence in Spring 2016. However, as a result of further clarification and more detailed robust project management it has been determined that the Phase 3 & 4 areas are not sufficiently defined and there is not yet sufficient evidence to enable effective consultation to take place. The information is not currently robust enough yet for the designation of these areas to be either confirmed or fall within the general approval.
It is proposed the consultation will focus on the Phase 1 & 2 priority areas only, i.e. Stanton Hill and Sutton Central (approx. 1,214 properties). Appendix 1 lists the actual locations within the boundary areas and Appendix 2 shows a geographical map with boundaries of the two areas.
The November 2015 Cabinet Report proposed the maximum six months for consultation but due to the proposed reduction in focus of this initial selective licensing project, and the size of areas, the consultation timescale has been reduced accordingly reduced to 12 weeks. This still allows more than the minimum legal requirement of 10 weeks for consultation to fall within the general approval. Twelve weeks will allow adequate time for consideration and response by residents and stakeholders and all responses will be conscientiously taken into account when finalising proposals.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.