RESOLVED That Cabinet agrees: a) That Ashfield District Council allocates £143,946 from the Section 106 allocation received for Lindley’s Lane as match funding towards the project; b) That the Council’s Capital Programme for 2016/17 be updated to include this project totalling “287,892 with funding being provided by the Section 106 allocation above and £143,946 from the Local Enterprise Partnership’s Local Growth Fund; c) That approval is given to utilise the EMPA SCAPE Framework and a direct award is made under that framework to appoint a contractor. d) That Legal Services are granted authority to complete the necessary documentation required in order to complete the appointment of the contractor.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
This report seeks approval to implement the Ada Lovelace Business Centre project, which will create 1658 sq ft of lettable office accommodation (7 units) that will be available to let to small businesses. The total cost of the refurbishment works has been estimated to be £287,892 and the project has the potential to be funded using a mixture of internal and external funding, on a pound for pound basis.
This report seeks formal approval to accept external funding of £143,946 from the Local Enterprise Partnership (LEP) through their Local Growth Fund programme as well as to allocate £143,946 from Ashfield District Council’s Section 106 allocation for Lindley’s Lane, Kirkby, which combined will cover the costs of the conversion of Ada Lovelace House. The funding of £143,946 from the LEP was formally approved for the project at their Infrastructure and Investment Board on 7th September 2016.
In addition the report seeks Cabinet approval to use the East Midlands Property Alliance (EMPA) SCAPE Framework for the purposes of appointing a contractor to undertake the works, as well as to grant authority to Legal to complete the necessary documentation to complete the appointment.
2. RECOMMENDATION(S)
This report seeks approval for the following four recommendations:
1. That Ashfield District Council allocate £143,946 from the Section 106 allocation received for Lindley Lane as match funding towards the project.
2. That the Council’s Capital Programme for 2016/17 be updated to include this project totalling £287,892 with funding being provided by the Section 106 allocation above and £143,946 from the Local Enterprise Partnership’s Local Growth Fund.
3. That approval is given to utilise the EMPA SCAPE Framework and a direct award is made under that framework to appoint a contractor.
4. That Legal are granted authority to complete the necessary documentation required in order to complete the appointment of the contractor.
Key Decision – This item first appeared on the Forward Plan published on 3rd August 2016 and meets the definition of a Key Decision as the total value of the project exceeds £250,000.
3. REASONS FOR RECOMMENDATION(S)
By accepting these recommendations, the Council will bring back into use, through refurbishment works, this currently vacant Ashfield District Council owned property. The grant income of £143,946 from the Local Enterprise Partnership has helped to reduce by 50%, the requirement of Ashfield District Council funds to bring this building back into use. This will stop the building from becoming a potential liability to the Council, as may otherwise happen if it is left empty over the long term.
The use of the EMPA SCAPE Framework for the purposes of appointing a contractor to undertake these works is recommended due to the value for money which it offers as well as the savings in the cost of procurement.
The works to be undertaken have the added advantage of helping to increase the vibrancy of the town centre and increase wider investor confidence in the town; whilst at the same time will provide an impetus for other sites in the town to come forward for development.
4. ALTERNATIVE OPTIONS CONSIDERED (with reasons why not adopted)
The alternative option considered was the do nothing option and leave the building as vacant premises thereby removing the requirement for any funding from either Ashfield District Council or any other source. This option was not pursued for the following reasons:
1. The vacant building would remain an ongoing liability to the District Council if left vacant in the long term.
2. There is significant need for town centre improvements within Kirkby, particularly at this key gateway site and a key part of undertaking this work is to enhance the offer of the town centre, particularly around the quality of the commercial offer.
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.