Ada Lovelace Business Centre Development

Agreed Executive 2 papers

Cabinet agreed this item on Thursday 22 September 2016. Below is the council's own wording, with the papers it was decided on.

ItemCA.28

Resolved

RESOLVED That Cabinet agrees: a) That Ashfield District Council allocates £143,946 from the Section 106 allocation received for Lindley’s Lane as match funding towards the project; b) That the Council’s Capital Programme for 2016/17 be updated to include this project totalling “287,892 with funding being provided by the Section 106 allocation above and £143,946 from the Local Enterprise Partnership’s Local Growth Fund; c) That approval is given to utilise the EMPA SCAPE Framework and a direct award is made under that framework to appoint a contractor. d) That Legal Services are granted authority to complete the necessary documentation required in order to complete the appointment of the contractor.
Word for word from the decision Ashfield published for this meeting. Source: democracy.ashfield.gov.uk

Follow this further

Built from Ashfield's papers

What the report saysPro

Report to Cabinet

Purpose of report

This report seeks approval to implement the Ada Lovelace Business Centre project, which will create 1658 sq ft of lettable office accommodation (7 units) that will be available to let to small businesses. The total cost of the refurbishment works has been estimated to be £287,892 and the project has the potential to be funded using a mixture of internal and external funding, on a pound for pound basis.

This report seeks formal approval to accept external funding of £143,946 from the Local Enterprise Partnership (LEP) through their Local Growth Fund programme as well as to allocate £143,946 from Ashfield District Council’s Section 106 allocation for Lindley’s Lane, Kirkby, which combined will cover the costs of the conversion of Ada Lovelace House. The funding of £143,946 from the LEP was formally approved for the project at their Infrastructure and Investment Board on 7th September 2016.

In addition the report seeks Cabinet approval to use the East Midlands Property Alliance (EMPA) SCAPE Framework for the purposes of appointing a contractor to undertake the works, as well as to grant authority to Legal to complete the necessary documentation to complete the appointment.

2. RECOMMENDATION(S)

This report seeks approval for the following four recommendations:

1. That Ashfield District Council allocate £143,946 from the Section 106 allocation received for Lindley Lane as match funding towards the project.

2. That the Council’s Capital Programme for 2016/17 be updated to include this project totalling £287,892 with funding being provided by the Section 106 allocation above and £143,946 from the Local Enterprise Partnership’s Local Growth Fund.

3. That approval is given to utilise the EMPA SCAPE Framework and a direct award is made under that framework to appoint a contractor.

4. That Legal are granted authority to complete the necessary documentation required in order to complete the appointment of the contractor.

Key Decision – This item first appeared on the Forward Plan published on 3rd August 2016 and meets the definition of a Key Decision as the total value of the project exceeds £250,000.

3. REASONS FOR RECOMMENDATION(S)

By accepting these recommendations, the Council will bring back into use, through refurbishment works, this currently vacant Ashfield District Council owned property. The grant income of £143,946 from the Local Enterprise Partnership has helped to reduce by 50%, the requirement of Ashfield District Council funds to bring this building back into use. This will stop the building from becoming a potential liability to the Council, as may otherwise happen if it is left empty over the long term.

The use of the EMPA SCAPE Framework for the purposes of appointing a contractor to undertake these works is recommended due to the value for money which it offers as well as the savings in the cost of procurement.

The works to be undertaken have the added advantage of helping to increase the vibrancy of the town centre and increase wider investor confidence in the town; whilst at the same time will provide an impetus for other sites in the town to come forward for development.

4. ALTERNATIVE OPTIONS CONSIDERED (with reasons why not adopted)

The alternative option considered was the do nothing option and leave the building as vacant premises thereby removing the requirement for any funding from either Ashfield District Council or any other source. This option was not pursued for the following reasons:

1. The vacant building would remain an ongoing liability to the District Council if left vacant in the long term.

2. There is significant need for town centre improvements within Kirkby, particularly at this key gateway site and a key part of undertaking this work is to enhance the offer of the town centre, particularly around the quality of the commercial offer.

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Ada Lovelace Business Centre DevelopmentReport 93 KB DownloadRead as text
PDF
Layout Plan: Appendix 1Appendix 338 KB Download

At this meeting

Whole meeting

Who was there

10 of 16 attended
JA
Councillor Jim AspinallCommittee Member, present
CB
Craig BonarOfficer, in attendance
TB
Councillor Tim BrownCommittee Member, present
CB
Councillor Cheryl ButlerChair, present
DD
Councillor Don DavisCommittee Member, present
RD
Ruth DennisOfficer, in attendance
DG
David GreenwoodOfficer, in attendance
JJ
Councillor Jackie JamesCommittee Member, present
RM
Councillor Rachel MaddenGuest, present
AM
Alan MaherOfficer, in attendance
RM
Robert MitchellOfficer, in attendance
KM
Councillor Keir MorrisonCommittee Member, present

All 16 on the meeting page

More from Ashfield Cabinet

All decisions
MeetingDecisionOutcome
27 Jul 2026 Local Government Reorganisation (Verbal Update and Q/A Session)RESOLVED that a) the information provided and the ongoing work being undertaken to support the transition programme, ... Noted Open
27 Jul 2026 Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be... Noted Open
27 Jul 2026 Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas... Noted Open
27 Jul 2026 Update - Charitable Trust Issues at Lord Francis Park (Kirkby-in-Ashfield), Hucknall Leisure Centre and Titchfield Park (Hucknall)RESOLVED that a) the current position relating to Charitable Trust Issues at Lord Francis Park (Kirkby-In-Ashfield), ... Noted Open
27 Jul 2026 Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies