a) That Cabinet notes the outturn position of the 2016/17 Capital Programme; b) That Cabinet notes the slippage on the 2016/17 Capital Programme and allows this to be carried forward to 2017/18 Capital Programme; c) That this change be recommended to Council for approval.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
The Capital Outturn details Capital Expenditure incurred in 2016/17, how this expenditure has been funded and provides explanations for major budget variances.
The overall Capital Expenditure was £13.037m and under spent to budget by £1.962m. The main reason for the under spend related to General Fund and Housing Revenue Account (HRA) projects which had not commenced or progressed as planned during the year. This underspend is referred to as ‘slippage’.
As a result of the above slippage and the use of £0.007m of Capital Receipts received in the year which were not included in the funding budget, the Council has utilised less borrowing (£0.254m) and less of its grant funding and other funding (£1.715m).
Recommendation(s) Members are requested:
(i) Note the outturn position of the 2016/17 Capital Programme. (ii) Note the slippage on the 2016/17 Capital Programme and allow this to be carried forward to 2017/18 Capital Programme and recommended to Council.
Reasons For Recommendation(s)
To report to those charged with Governance the financial position for the end of 2016/17 and comply with the Council’s Financial Regulations.
Alternative Options Considered (With Reasons Why Not Adopted)
None Detailed Information
1. Introduction
Cabinet approved the Capital Programme for 2016/17 to 2019/20 on 20 th February 2017. This is a report back to Cabinet on the financial out-turn of the capital expenditure against that Capital Programme.
2. Outturn 2016/17
The outturn position for 2016/17can be summarised as follows:
Capital Actual Variance Scheme programme Expenditure £000's £000's £000's Housing Revenue Account Management Fee 638 641 3 Catch up and Major Repairs 5,801 5,527 (274) Service Improvements 256 162 (94) Contingent Major Repairs 84 68 (16) Exceptional Extensive Works 1,036 1,014 (22) Disabled adaptations - Treated as Revenue Expenditure From Capital Under Statute (REFCUS) 445 414 (31) Empty Homes 108 82 (26) Darlison Court (New Builds) 366 370 4 Warwick Close 430 430 0 Other Housing Revenue Account Schemes (less than £100k each) 253 109 (144) Total Housing Revenue Account 9,417 8,817 (600)
General Fund Ada Lovelace Business Centre Development 288 198 (90) Idlewells Market Hall Asbestos Removal and Refurbishment - Allocation still subject to option appraisal 575 691 116 Titchfield Park and Hucknall Cemetery: implementation of park masterplan 118 89 (29) Kirkby Regeneration and Civic Centre 145 143 (2) Green Deal Communities Project 222 225 3 Acacia Avenue Rec - General Improvements 150 21 (129) Improvement Grants 1996 Act Disabled Facility Grant 641 684 43 Better Care Grants 169 7 (162) Office Accommodation Works 472 373 (99) Vehicle Tracking Scheme 135 0 (135) Garden Waste Bins 462 342 (120) Purchase of Vehicles 706 570 (136) Other General Fund Schemes (less than £100k each) 1,499 877 (622) Total General Fund 5,582 4,220 (1,362)
Total Expenditure 14,999 13,037 (1,962)
Funding Major Repairs Reserve 8,114 6,625 (1,489) Borrowing 1,341 1,088 (253) Government Grants and Other Contributions 3,925 2,897 (1,028) Revenue Contributions 241 1,042 801 Capital Receipts 1,378 1,385 7 Total Funding 14,999 13,037 (1,962) The outturn shows an under spend of £1.962m compared to the approved programme.
A summary of the main variances are as follows:-
Housing Revenue Account (HRA) Catch Up and Major Repairs – A significant reason for this underspend is the rejection by some customers in the Council Dwellings for the works to be completed, Service Improvements – There have been delays in receipt of Design Drawings; these works will be completed in 2017/18.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.