RESOLVED That Cabinet authorises the Director of Resources and Business Transformation to commence a procurement process and to appoint a supplier to provide an upgraded telephony system.
Cabinet decided this item on Thursday 19 October 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That Cabinet authorises the Director of Resources and Business Transformation to commence a procurement process and to appoint a supplier to provide an upgraded telephony system.
To request approval to replace and upgrade the telephony hardware and software to a fully supported version, through a procurement process to find a supplier partner to undertake the migration from the current platform and implement new features that will aid Agile Working.
Recommendation(s)
1. To authorise the Director Resources and Business Transformation to commence a procurement process and to appoint a supplier to provide an upgraded telephony system.
Reasons For Recommendation(s)
The current contract for telephony support with Virgin Media has ended. A temporary maintenance contract has been taken out with a third party.
The upgraded telephony system will include features that will help the Council move towards a more agile working style by enabling end users to have a Council phone number while away from the Council Offices via an app installed on a mobile device such as a smart phone or tablet or even home PC.
Dependent on the costs, which the procurement process will identify, consideration will also be given to having a hosted telephony system which delivers additional operational benefits.
Alternative Options Considered (With Reasons Why Not Adopted)
None – the telephony system is end of life and must be upgraded or changed. Detailed Information
The current telephony hardware has reached end of life and needs to be replaced. The current telephony software, Cisco CUCM, has also reached end of life and needs to be upgraded. This does not include the Cisco handsets which remain fully functional.
As the migration of the current system to a supported platform c/w configuration and upgrade to the latest version of the software is a highly specialist function a procurement exercise is required to find a partner to perform these tasks.
ICT have been provided with a number of indicative costs, the one that appears to offer the best value for money and fit with the existing phone system is:
Software and hardware upgrades £22,000 Installation works £46,000 Sub Total £68,000 Annual Cisco Software Assurance £9,600* (£3,200 pro rata 2017/18) Annual Support £9,000* (£2,250 pro rata 2017/18) Total £86,600
*There is currently a budget for annual support costs of £18,700, which will fund the new contract costs. There have been additional costs incurred in 2017/18 for additional support requirements which will result in a greater charge of around £5,000 above budget, however, some of this may be reimbursed on commencement of the new contract but the value is not yet known. The costs of implementation will be contained within existing budgets at present as a result of savings made across the authority, but this will be monitored closely and may become a budget pressure later in the year.
Following the procurement process the actual costs may be higher or lower than the indicative costs stated.
The current telephony system software is no longer supported by Cisco. The hardware has reached its end of life, therefore a procurement exercise needs to be undertaken to find a supplier who can ensure the software is correctly licensed and supported, undertake the migration, upgrade and testing of the telephony platform to a fully supported version and provide ongoing support.
A procurement exercise via a Government Framework will commence at the end of October 2017 with the aim of beginning the migration work in November/December 2017.
The benefits to the Council and service delivery through the investment in an upgraded telephony system include:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Telephony UpgradeReport | 118 KB | DownloadRead as text |
Follow Cabinet at Ashfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2026 | Local Government Reorganisation (Verbal Update and Q/A Session)RESOLVED that a) the information provided and the ongoing work being undertaken to support the transition programme, ... | Noted | Open |
| 27 Jul 2026 | Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be... | Noted | Open |
| 27 Jul 2026 | Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas... | Noted | Open |
| 27 Jul 2026 | Update - Charitable Trust Issues at Lord Francis Park (Kirkby-in-Ashfield), Hucknall Leisure Centre and Titchfield Park (Hucknall)RESOLVED that a) the current position relating to Charitable Trust Issues at Lord Francis Park (Kirkby-In-Ashfield), ... | Noted | Open |
| 27 Jul 2026 | Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.