a) That Cabinet notes the budget monitoring to November 2017 for the General Fund and Housing Revenue Account (HRA) and approves the reductions in the budget by £183k for the General Fund and £790k for the HRA; b) That Cabinet approves the movements from earmarked reserves to fund specific projects as set out in the report, noting that these movements will have no impact on the position of the General Fund; c) That Cabinet approves the budget changes as set out in the report and recommends them to Council in accordance with Financial Regulations.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
This report sets out the details of income and expenditure incurred to November 2017 by the General Fund and Housing Revenue Account (HRA), compares it to the approved budgets and explains the significant variances.
The report includes a forecast outturn position based on known information at this time.
The report also recommends revisions to the 2017/18 General Fund and HRA budgets as detailed below.
Recommendation(s) Members are requested:
(i) To note the budget monitoring to November 2017 for General Fund and HRA and approve the reductions in the budget by £183k for General Fund and £790k for HRA. (ii) To approve the movements from earmarked reserves to fund specific projects as outlined below. This has no impact on the position of the General Fund. (iii) To approve the budget changes as listed and recommend to Council in accordance with Financial Regulations.
Reasons for Recommendation(s)
To report to those charged with Governance the financial position to November 2017 and comply with the Council’s Financial Regulations. Alternative Options Considered (With Reasons Why Not Adopted)
There have been no alternative options identified.
Detailed Information
Budget Monitoring to November 2017
a. General Fund to November 2017
The table below shows the overall summary for the General Fund by Directorate, excluding capital financing costs and internal recharges. This also includes a forecast outturn position showing where estimated areas will be over or under spent at the year end.
Actuals Budget Variance Forecast Outturn (£000) (£000) (£000) (£000) Chief Executive Officer 450 349 (101) (84) Legal and Governance 927 990 63 278 Resources and Business Transformation 4,005 4,429 424 179 Place and Communities 7,390 7,432 42 (395) Housing and Assets 1,482 1,589 107 (15) Total 14,254 14,789 535 (36)
Net Expenditure to November 2017, excluding Capital and Internal Recharges, at £14.254m is £535k under spent. The key variances of note are detailed below:
Direct Employee Expenditure
Direct pay at £11.32m is £13k under budget. This comprises of an under spend of £354k for direct pay, against an over spend of £341k for agency costs.
Transfer Payments
Transfer payments are the costs incurred from payment of rent allowances and rent rebates and the corresponding income received from Central Government, which reimburses a large proportion of these costs.
The overall net cost of transfer payments at £1.351m is £92k under budget. This comprises of the net cost of Housing Benefit Subsidy which is £36k under budget and Discretionary Housing Payments (DHP) which are £56k under budget. It is forecast that the DHP payments will be £50k less than budget, however this does not appear in the overall forecast outturn because any underspend will have to be repaid to the Department of Work and Pensions (DWP). The Council has been exploring ways to increase the uptake of this service.
The forecast outturn for Housing Benefit subsidy is expected be under budget by £174k. There has been a favourable outcome from the Audit for the Housing Benefit Subsidy Claim for 2016/17. A full loss of subsidy due to Local Authority Error of £174k had been budgeted for but early indications show that this is not likely now. This will not be confirmed by DWP until later in January 2018.
Utilities Utilities are under budget by £56k in total, Electricity £24k, Gas £19k and Water Rates £12k. Current Position – Services The table below shows the General Fund position to November 2017 by Service Area, excluding internal recharges and capital. This also includes the proposed budget changes discussed later in the report and the effect is captured in the forecast outturn. Significant variances are discussed below.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.