a) the report be received and noted and the further development of the Ashfield Place Leadership programme, as outlined in the report, be approved; b) the allocation of £34,000 Section 106 monies to Sutton Town Centre improvements, as previously agreed at the Cabinet meeting on 14th June 2018, be noted; c) the grant offer from WREN of £50,000, to progress the Lime Tree Recreation Ground Scheme in Hucknall, be noted. REASON FOR DECISIONS The Council’s Corporate Plan has made a commitment to the Place and Economic theme to: - · Enhance the identity and brand for Ashfield; · Raise the profile of Ashfield as a place where people would wish to visit.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
The new Administration has identified and prioritised the economy and community pride and aspiration as key areas for improvement. To update Cabinet on the delivery of the key projects, programmes and initiatives within the Place Leadership agenda, as set out in the Corporate Plan (2016-2019) and approve the allocation of Section 106 monies for Sutton Town Centre improvements.
Recommendation(s) 1) Cabinet is recommended to endorse the contents of this report and the further development of the Ashfield Place Leadership programme.
2) Cabinet notes the allocation of £34,000 to Sutton Town Centre agreed at Cabinet on 14th June 2018 for improvements to street furniture
3) Cabinet notes a grant offer from WREN of £50,000 for the Lime Tree Recreation Ground scheme.
Reasons for Recommendation(s) The Council’s Corporate Plan has made a commitment to the Place and Economic theme to:
Enhance the identity and brand for Ashfield; so it is cherished by those who live or work here, desirable to those who visit, and attractive to those who bring jobs and investment; Raise the profile of Ashfield as a place where people want to visit and spend their time enjoying themselves. In order to build on the work to date, this report is to update Cabinet on the delivery of the key projects and initiatives within the Place enhancement programme. The funding allocated will support:
Allocation of Section 106 monies will allow for upgrading/ replacement of street furniture within Sutton town centre which will improve the appearance of the town.
Successful grant allocation from WREN will allow for the Lime Tree Recreation Ground scheme to be progressed. A new play area will be installed which will complement works carried out last year to provide footpath links, a kick about area and improved maintenance.
Alternative options considered
Do nothing: Not recommended for a number of reasons. The insight work carried out to date in conjunction with stakeholders has allowed the Council to increase understanding of the District by creating the ‘Ashfield Story’ and future requirements. The ‘Ashfield Story’ will be central to the successful delivery of the Place Leadership Programme objectives set out within the Corporate Plan (2016-2019). Street furniture within Sutton town centre is in poor condition and in need of refurbishment/ upgrading. This work also provides us with an opportunity to agree and then specify a consistent Ashfield “palette” or a “look” for town centre street furniture to further enhance the sense of Place.
Detailed Information
Programme delivery
The Council expressed an aspiration towards “Place Enhancement” in the Corporate Plan (2016-2019), making Ashfield a location and destination of choice for business and visitors and a desirable place to live for all residents.
One of the key projects in the Place Enhancement programme is to capture and develop Ashfield’s unique character to those that live, work and visit by developing a Place Plan.
In October 2016 Cabinet approved the appointment of expert advisors, an independent marketing company “Thinking Place”, to advise the Council on how to deliver the Place objective.
A wide range of stakeholders and partners have been involved, helping to better understand the ‘Ashfield Story’; identifying what makes the area distinctive, so that we can create a compelling offer, encouraging inward investment and building community pride.
The initial stage in the development of the Place agenda identified the District’s strengths and assets. This was done through consultation with key stakeholders, including community and business leaders, to formulate a plan of action.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.