Resolved
RESOLVED that a) the proposed site-specific green space improvement projects, as outlined in the report, be approved; b) progress on the Green Space Improvement Programme, as presented, be received and noted.
Cabinet approved this item on Tuesday 1 December 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that a) the proposed site-specific green space improvement projects, as outlined in the report, be approved; b) progress on the Green Space Improvement Programme, as presented, be received and noted.
To note and agree the proposed site-specific green space improvement projects for the funding approved at Council on 22 October 2020 and to note progress on the Green Space Improvement Programme.
Recommendation(s)
1. To agree the proposed site-specific green space improvement projects.
2. To note progress on the Green Space Improvement Programme.
Reasons for Recommendation(s)
The improvements have been identified following a review of the play area annual inspection reports and site walkovers with the Leader and ward members.
The sites are all neighbourhood sites which have not received investment for several years and require improvement. Improvements will include additional pieces of play equipment, bins and signage, footpath works and tree planting.
These sites are a valuable community resource, particularly during the pandemic when people have been making greater use of their local green spaces. These improvements will provide significant investment into green spaces this financial year, complementing the existing commitment of over £1.5m spend by the end of March next year. Alternative Options Considered
Not to agree the proposed allocation of improvements – not recommended, each of the improvements have been identified in consultation with the Leader and / or ward members. A number of sites require intervention this financial year to ensure that the quality of the District’s green space provision remains high.
Detailed Information
Green Space Improvement Programme An ambitious programme of investment will see over £1.5m invested into green spaces this financial year. A number of projects are due to start on site in December this year, or early in the New Year 2021, which include: completion of the stone-carved mining statues and additional car parking at Brierley Forest Park; installation of the new play areas at Sorrel Drive and Skegby Road Recreation Ground; improvements at West Park; and the brook restoration and landscape works at Titchfield Park in Hucknall.
As well as this, a wide variety of Projects across the District have been completed so far this year and these include: restoration of the viaduct and dredging work at Kings Mill Reservoir and refurbishment of the Mill Waters Café; the new outdoor gym facility at Jacksdale Recreation Ground, footpath improvements and increased capacity for the main car park in the village; refurbishment of the play area at Nabbs Lane Park, Hucknall; resurfacing of Rights of Way on the western pit tip site in Kirkby; installation of play and fitness equipment at Annesley Recreation Ground; and the refurbishment of the play area at Titchfield Park, Kirkby which is due for completion by early December.
Additional improvement works The improvement works and cost estimates for each project are detailed below. Final project costs will be allocated from the allocation of £366k (£193k Capital Receipts and £173k S106 funding) which has been made available to meet the cost of these investments.
1.0Healdswood Recreation Ground Cost Estimate 1.1 Toddler play area. –Remove redundant play panels and replace with new alternative.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Green Spaces Capital Investment ProgrammeReport | 195 KB | DownloadRead as text |
Follow Cabinet at Ashfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2026 | Local Government Reorganisation (Verbal Update and Q/A Session)RESOLVED that a) the information provided and the ongoing work being undertaken to support the transition programme, ... | Noted | Open |
| 27 Jul 2026 | Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be... | Noted | Open |
| 27 Jul 2026 | Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas... | Noted | Open |
| 27 Jul 2026 | Update - Charitable Trust Issues at Lord Francis Park (Kirkby-in-Ashfield), Hucknall Leisure Centre and Titchfield Park (Hucknall)RESOLVED that a) the current position relating to Charitable Trust Issues at Lord Francis Park (Kirkby-In-Ashfield), ... | Noted | Open |
| 27 Jul 2026 | Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.