RESOLVED a) that subject to planning consent and Homes England funding: b) the use of the unused section of the Council-owned Wesley Street Allotment site for bungalows let on an affordable rent basis, be approved; c) delegated authority be granted to the Director of Housing and Assets, in conjunction with the Director of Legal and Governance and the Corporate Finance Manager (and Section 151 Officer), to agree the appropriation of the Wesley Street site from the General Fund to the Housing Revenue Account based upon best consideration of the land value and the parameters of the social housing viability model, in line with details as set out in the report; d) the use of both Housing Revenue Account reserves and Commuted Sums to fund the construction of 12 new affordable homes, be approved; e) delegated authority be again granted to the Director of Housing and Assets, in conjunction with the Corporate Finance Manager (and Section 151 Officer), to negotiate and formalise final scheme costs, specification and delivery. Reason: The development would help to achieve the Council’s Corporate Plan objective of delivering much needed additional good quality affordable housing in the District and bring into use, in an extremely positive way, an under used site.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To advise Members about the opportunity to develop affordable bungalows on a Council owned undeveloped plot of land at Wesley Street, Annesley, and seek approval of said development.
Recommendation(s)
Subject to planning consent and Homes England funding:
1. To approve the use of the unused section of the Council-owned Wesley Street Allotment site for bungalows let on an affordable rent basis.
2. To grant delegated authority to the Director of Housing and Assets, in conjunction with the Director of Legal and Governance, and the Chief Finance Officer, to agree the appropriation of the Wesley Street site from the General Fund to the Housing Revenue Account based upon best consideration of the land value and the parameters of the social housing viability model and in line with details set out in the report.
3. To approve the use of both Housing Revenue Account reserves and Commuted Sums to fund the construction of 12 new affordable homes.
4. To grant delegated authority to the Director of Housing and Assets, in conjunction with the Chief Finance Officer, to negotiate and formalise final scheme costs, specification and delivery. 5. To grant delegated authority to the Director of Housing and Assets, to procure and appoint a contractor to develop the site.
6. To grant delegated authority to the Director of Housing and Assets to contract, on behalf of the Council, with Homes England, for the purposes of receiving subsidy to ensure that developments are viable and fall within the Council’s 30-year business plan model.
7. To grant delegated authority to the Director of Housing and Assets, in conjunction with the Director of Legal and Governance, to negotiate a settlement figure with The Welbeck Estate, to allow the removal of a covenant on the title that currently forbids development.
8. To delegate authority to the Director of Housing and Assets in conjunction with the Director of Legal and Democratic Services to apply to the Secretary of State to release the land for the purposes of social housing.
Reasons for Recommendation(s)
The development will help to achieve the Council’s Corporate Plan objective of delivering much needed additional good quality affordable housing in the District.
The development will bring into use, in an extremely positive way, an under used site.
Alternative options considered
Do nothing with the land. This was rejected because the land is not currently being used and has development potential. Sell the land for private development. This was rejected as the existing covenant would negate private development
Detailed Information
The Corporate Plan sets out the Council’s ambition to ensure there is sufficient good quality, affordable housing for the residents of Ashfield. To achieve this the Council cannot rely upon Registered Providers and private house builders alone; it is important that the Council looks at the opportunities to develop new affordable housing on sites it owns.
Within the curtilage of the Council owned allotment site on Wesley Street, Annesley, is a section of unused land that has been identified as being potentially suitable for affordable housing.
The proposal is the use the section of land to construct 12 two-bedroom bungalows. Demand for such accommodation; during the last 12-month period 11 two-bedroom bungalows have become available in the Kirkby area with each property attracting an average of 37 bids. Bungalows will also be in keeping with the existing street scene.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.