RESOLVED that a) the current forecast outturn for the General Fund, Housing Revenue Account (HRA) and Capital Programme for 2021/22, be received and noted; b) the budget adjustments outlined in section 3.1, Table 3 of the report, be approved.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To summarise the Council’s forecast financial outturn position to 31 March 2022 compared to the latest approved budgets for the General Fund, Housing Revenue Account (HRA) and the Capital Programme. The forecast financial outturn is based on the actual financial activity to the 31 January 2022 and forecast costs and income from 1 February 2022 to 31 March 2022.
Recommendation(s)
Cabinet is requested:
(1) To note the current forecast outturn for the General Fund, Housing Revenue Account (HRA) and Capital Programme for 2021/22.
(2) To approve the budget adjustments outlined in section 3.1, Table 3.
Reasons for Recommendation(s) In accordance with the Council’s Financial Regulations to report to those charged with Governance the financial position. Alternative Options Considered None
Detailed Information
1.1Table 1 below shows the current revised budget, based on the original budget approved by Council on the 4th March 2021 and Council approved budget adjustments to 31th January 2022. It sets out the 2021/22 net revenue forecast outturn position based on actual income and expenditure to 31st January 2022 and forecast income and expenditure for the remainder of the year to 31 March 2022.
1.2The current General Fund forecast is a £667k underspend compared to revised budget, including the in-year Covid-19 grant received to date. An increase of £9k underspend since the previous budget monitoring reported to Cabinet as at 31st September 2021.
Table 1 - Net Revenue Forecast to 31 March 2022 by Directorate
Current Previous Revised General Fund Forecast Forecast Forecast Change Budget Variance Variance
£'000 £'000 £'000 £'000 £'000 Directorate Chief Executive Officer 562 561 (1) 14 (15) Legal and Governance 1,787 1,791 4 (27) 31 Resources and Business Transformation 319 (67) (386) (441) 55 Place and Communities 9,905 9,618 (287) (183) (104) Housing and Assets 2,151 2,066 (85) 19 (104) Total Net Directorate Expenditure 14,724 13,970 (754) (618) (136)
Net Recharges (2,744) (2,699) 44 39 5 Capital Financing 2,549 2,368 (181) (181) 0 Net Interest Payable /(Receivable) 8 3 (5) (5) 0 Net Revenue Expenditure 14,537 13,641 (896) (765) (131)
Funding (13,369) (13,377) (8) 0 (8)
Net Revenue Expenditure before 1,168 264 (904) (765) (139) transfer to(from) earmarked reserve
Transfer to(from) earmarked reserve (1,302) (1,065) 237 107 130
Net Revenue Expenditure after transfer (134) (801) (667) (658) (9) to(from) earmarked reserve
1.3Appendix 1 provides details of the variances for each Directorate, Corporate Costs and Funding. 1.4 The main changes since the previously reported position are:
The current forecasts for all directorates have been updated to include 1.75% for the 2021/22 pay award. Legal and Governance - pay award reflected and pay vacancy factor not being achieved in some service areas due to the need to temporarily engage more costly agency staff. Resources and Business Transformation – Increase to the forecast loss on Housing Benefit overpayments. Place and Communities - Increase in income for planning fees and sales of vehicles. Housing and Assets – Employee costs savings due to vacancies.
1.5Appendix 2 provides details of the approved and forecast earmarked reserves movements as at 31st January 2022.
2. Covid-19 Grant
2.1The Council has received Covid funding of £817k in 2021/22 to date. Table 2 below shows the utilisation of the funding to 31st January 2022 of £774k. This position is reflected in the forecast outturn position in Table 1, the overall forecast outturn of £801k includes £43k unutilised in year Covid funding.
Table 2 – Covid-19 costs and loss of income
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.