RESOLVED that a) the process followed by officers to review the viability and future use of Council owned Housing Revenue Account garage and plot sites, be noted; b) delegated authority be granted to the Executive Director of Transformation, in conjunction with the Executive Director of Governance, to dispose of the sites at Ashgate, Sutton in Ashfield and Lancaster Drive, Hucknall, having been assessed as being economically unviable in current use and unsuitable for the purpose of affordable housing development (with disposal being in accordance with the Council’s Disposals Policy and on the basis of achieving best value wherever possible); c) delegated authority be granted to the Service Manager for Commercial Development to finalise the detail of the transaction(s) with the Assistant Director for Legal. Reasons: 1. The Council has a large number of garage and plot sites under the ownership of the Housing Revenue Account and some are in disrepair with little or no demand from local residents. Where demand is low and the site requires significant investment, it is not economically viable for the Council to retain the site and consideration needs to be given to its future use. 2. Changing use will also help tackle issues of anti-social behaviour that have become evident on some of the sites.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
CABINET Report To: 29TH JANUARY 2024 Date: DISPOSAL OF UNVIABLE GARAGE AND PLOT SITES Heading: CLLR ANDY MEAKIN Executive Lead Member: ANNESLEY & KIRKBY WOODHOUSE, CARSIC, Ward/s: GREENWOOD & SUMMIT, HUCKNALL WEST YES Key Decision: YES Subject to Call-In:
Purpose of Report To advise Members about the process that has been followed to review the viability and future use potential of Council owned garage and plot sites and to recommend disposal for those sites considered unviable and not suitable for the purpose of affordable housing development.
Recommendation(s) 1. To note the process officers have followed to review the viability and future use of Council owned Housing Revenue Account garage and plot sites.
2. To grant delegated authority to the Executive Director of Transformation, in conjunction with the Executive Director of Governance, to dispose of sites assessed as being economically unviable in current use and unsuitable for the purpose of affordable housing development. Disposal will be in accordance with the Council’s Disposals Policy and will be on the basis of achieving best value wherever possible.
3. To delegate authority to the Service Manager – Commercial Development to finalise the detail of the transaction(s) with the Assistant Director - Legal Reasons for Recommendation(s) The Council has a large number of garage and plot sites under the ownership of the Housing Revenue Account. Some sites are in good condition, have a high level of demand and generate a steady income stream, others are in disrepair with little or no demand from local residents. Where demand is low, and the site requires significant investment, it is not economically viable for the Council to retain the site as it is and consideration needs to be given to its future use. A small number of sites will be suitable for affordable housing development but where this is not possible consideration needs to be given to disposing of the site, to remove the ongoing maintenance and potentially generate a capital receipt for the Council’s Housing Revenue Account.
Changing use will also help tackle issues of anti-social behaviour that have become evident on some of the sites.
Alternative Options Considered Continue to use all sites for plot/garage purposes. This is not appropriate as a number of sites require significant investment with little likelihood of expenditure being recovered through rental income and low demand at these locations.
Detailed Information The Council owns garage and plots sites across the District. Plots sites are those whereby a resident rents a section of land, large enough to park their vehicle and they erect their own garage.
Sites vary in respect of their size; some are large enough to accommodate 20+ garages whereas others contain as few as 2 garages. Likewise, demand varies enormously, a small number of garage sites have full occupancy along with a small waiting list, whereas on some other sites there is a 100% vacancy rate. A small number of sites have been fenced off and secured due to the garages being in a dilapidated state, beyond economical repair. Vacancy rates on plot sites are particularly high, in part because of the requirement of the plot holder to erect a garage at their own expense.
As part of the review the following was considered for each site:
• Current and likely future levels of demand • Rental income levels • Current and future maintenance and repair obligations • Investment needed in the site as a whole. • Payback period, i.e., how long will it take to recover what has been spent from the rental income • Alternative parking in the local area • Levels of Anti-Social Behaviour and other management issues • Restrictions or caveats in the site deeds • Potential to utilise the site for affordable housing development • Title reports for the sites have been checked to ensure there are no issues regarding a potential sale.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.