RESOLVED that a) the current forecast outturn for the General Fund, Housing Revenue Account (HRA) and Capital Programme for 2024/25, be received and noted; b) the reserve movements outlined in section 3.2 of the report, be approved; c) Council be recommended to approve the amendments and the addition of new schemes to the Capital Programme 2024/25 to 2028/29 and the funding of the Capital Programme as set out in Section 6 and Appendix 3 of the report; d) the monitoring of Prudential and Treasury Management indicators for 2024/25, as detailed in Appendix 4, be noted. Reason: In accordance with the Council’s Financial Regulations to report to those charged with Governance the financial position.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To summarise the Council’s forecast financial outturn position to 31 March 2025 compared to the latest approved budgets for the General Fund, Housing Revenue Account (HRA) and the Capital Programme. The forecast financial outturn is based on the actual financial activity to 31 July 2024 and forecast costs and income from 1 August 2024 to 31 March 2025.
Recommendation(s)
Cabinet is requested:
(1) To note the current forecast outturn for the General Fund, Housing Revenue Account (HRA) and Capital Programme for 2024/25.
(2) To approve the reserve movements outlined in section 3.2.
(3) To recommend to Council the amendments and the addition of new schemes to the Capital Programme 2024/25 to 2028/29 and the funding of the Capital Programme as set out in Section 6 and Appendix 3 of the report.
(4) To note the monitoring of Prudential and Treasury Management indicators for 2024/25 detailed in Appendix 4.
Reasons for Recommendation(s)
In accordance with the Council’s Financial Regulations to report to those charged with Governance the financial position. Alternative Options Considered The financial position has to be reported to those charged with governance. Therefore, there are no other options.
Detailed Information
Budget Monitoring April 2024 to July 2024 (General Fund and HRA)
1. Summary Budget for General Fund
1.1Table 1 below sets out the 2024/25 net revenue forecast outturn position based on actual income and expenditure to July 2024 and forecast income and expenditure from August 2024 to March 2025, compared to the current revised budget (based on original budget approved by Council on the 4th March 2024 and Council approved budget adjustments to 31st July 2024).
1.2The current General Fund forecast is a £524k underspend compared to the budget.
Table 1 - Net General Fund Revenue Forecast to 31 March 2025 by Directorate
Current Original General Fund Forecast Forecast Budget Variance
Net Recharges (3,486) (3,486) 0 Capital Financing 3,553 2,987 (566) Net Interest Payable /(Receivable) (135) (71) 64 Net Revenue Expenditure 16,844 16,444 (400)
Funding (17,570) (17,570) 0
Net Revenue Expenditure before transfer to(from) (726) (1,126) (400) earmarked reserve
Transfer to(from) earmarked reserve 726 602 (124)
Net Revenue Expenditure after transfer to(from) 0 (524) (524) earmarked reserve 1.3 Appendix 1 provides details of the variances for each Directorate, Corporate Costs and Funding.
1.4Appendix 2 provides details of the approved and forecast earmarked reserves movements as at 31 July 2024.
1.5The projected overspend in the Transformation Directorate relates directly to the utilisation of agency in relation to the implementation of the new Finance system, Technology One. These costs will be covered through the Corporate Transformation Reserve.
1.6The main reason for the projected underspend in the Place Directorate is vacancies in Community Safety, ASBO Case Officers and Regeneration.
1.7The Operations Directorate projected overspend is mainly due to staff cost pressures and additional vehicle hire costs, largely mitigated by staff vacancies and reduced fuel costs.
1.8The variances in Capital Financing Costs and Net Interest are mainly due to higher than expected interest receivable on investments and due to slippage on capital expenditure on schemes in the Capital Programme. This gives a projected net underspend of £502k.
2. General Fund Savings/Efficiencies Monitoring 2024/25
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.