RESOLVED a) that the current significant items on the Corporate Risk Register, as presented, be received and noted; b) the updated Corporate Risk Strategy be received and endorsed. Reasons: 1. To prioritise and manage the mitigation of risk in order that the Council can achieve its objectives. 2. The Corporate Risk Strategy had been updated and aligned with DMA impacts on associated corporate risk responsibilities and accountabilities.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
For Cabinet to review the Corporate Risk Register and the analysis of movement in risk and mitigating actions in respect of those risks.
Recommendation(s)
• To note the current significant items on the Corporate Risk Register and to consider whether any further immediate actions are necessary to mitigate those risks. • To endorse the updated Corporate Risk Strategy
Reasons for Recommendation(s)
To prioritise and manage the mitigation of risk in order that the Council can achieve its objectives. The Corporate Risk Strategy has been updated aligned with DMA impacts on associated corporate risk responsibilities and accountabilities.
Alternative options considered
None. In accordance with the Corporate Risk Strategy, it is the role of Cabinet to monitor the Council’s risk management and internal control arrangements, as part of the established quarterly monitoring and to recommend action where necessary. Detailed Information
All organisations are required to consider potential risks which may impede the delivery of corporate objectives. Effective risk management processes strengthen the ability of the Council to react to all situations and protect its own interests and those of the District, ensuring essential service delivery, through actively managing and mitigating risk effectively and innovatively. The management of risk forms an integral part of the Council’s business. Effectively managing our risks means that we can maximise opportunities and minimise the costs and disruption to the Council which may possibly be caused by undesired events.
All strategic risk at corporate and service level is incorporated into the Pentana performance system to enable quarterly updates at the same time as updating performance, therefore enhancing the consideration of risk in the delivery of services. All levels of risk are discussed bi-annually in detail with each Assistant Director as a standing agenda item for Performance Boards, led by the Chief Executive and Assistant Director – Policy and Performance.
In summary, overall, the current corporate risk position indicates the positive management of risk: - • In the last 12 months, one new risk has been added and two risks removed from the Corporate Risk Register. There are two additional new risks currently being finalised for addition to the register. • Most, 92% of the remaining corporate risks have been effectively managed without an increase in risk assessment rating in the last 12 months. • Of these, positively, 23% of corporate risks have been effectively managed and mitigated with a reduction in risk assessment rating in the last 12 months.
Corporate Risk Register
The Corporate Risk Register (current position at July 2025) is appended to this report.
There is a continued review of our corporate risk in alignment with the Corporate Risk Strategy and Risk Appetite Framework, and as such, the risk relating to meeting the requirements of the Election Act has been removed from the Corporate Risk Register to be monitored at service level.
Those corporate risks which remain significant are: -
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.