AI summaryCabinet accepted Football Foundation grant of up to £1,846,854 for the Sutton Lawn Sports Hub in Kirkby and Sutton and authorised the Executive Director Place to sign the funding agreement.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedFor Sutton Lawn Sports Hub
Money£1,846,85440% of project cost, capped
What happens nextSign Football Foundation agreementSubject to further decisions
Who it affectsSutton Lawn users, local clubsFootball and tennis facility users in Kirkby and Sutton
What was decided
Cabinet accepted Football Foundation grant funding of up to £1,846,854 for the Sutton Lawn Sports Hub, having considered the project proposals and associated risks. Report P1, P3
Cabinet authorised the Executive Director Place to sign the Football Foundation grant funding agreement for up to £1,846,854. Report P3
The Hub is part of the Council's Regeneration Programme to enhance sport and leisure provision in the District. Report P5
Why
The project supports the Council's Health and Happiness priority, covering community cohesion, pride, mental and physical health, and reducing health inequalities. Report P29
It delivers improved and expanded sports facilities, with benefits including increased access to sport and physical activity and improved wellbeing. Report P6
The Council has worked with the Football Foundation for the last five years to develop football hub plans for Kingsway Park and Sutton Lawn. Report P15
What happens next
The Executive Director Place will finalise and sign the Football Foundation grant agreement, with the charitable trust removed as a signatory. Report P23, P27
Phase 1 works (pavilion refurbishment and car park) will proceed on site with Towns Fund covering the full contract, avoiding further cost increases. Report P20
Procurement and award of the Phase 2 contract for two 3G pitches through the Football Foundation's framework is subject to a further decision. Report P21
The money
£1,846,854 Football Foundation capital grant offer, 40% of total project cost, capped Report P7
c.£5.5m Overall cost of the Sutton Lawn football hub Report P7
£3,182,633 Allocated from Towns Fund and Academy Transformation Trust Report P7
£2,486,368.27 Maximum Phase 1 contract value agreed with Lindum Group Ltd, with further reductions possible Report P20
Options considered
Chosen: Accept Football Foundation grant and deliver the full project. Delivers improved and expanded sports facilities, increased access to sport and physical activity, improved wellbeing, and contributes to Corporate Plan priorities Report P6
Rejected: Do not proceed with the project. Would not deliver improved and expanded sports facilities or the subsequent community benefits Report P6
Rejected: Only move ahead with Phase 1 (car park and changing rooms). Would not deliver the improved and expanded sports facilities or directly contribute to Corporate Plan priorities Report P6
Implications
Legal: The Council remains liable to the Football Foundation for the full grant if ATT defaults on conditions the Council cannot control, including potential repayment in full or part. Report P23, P24, P25, P31
Financial: Costs will be charged to capital scheme TF15 Sutton Lawn Sports Hub (700036), funded through the Towns Fund grant from MHCLG within the current approved Capital Programme. Report P32
Risk: Identified risks include grant repayment, negative public perception, construction disruption, match funding shortfalls, contractor underperformance, and design team underperformance, each with stated mitigations. Report P36, P37, P38, P39, P40
Equalities: No direct equalities implications from the decision; duties on buildings and facilities are discharged through the design process and an Equalities Impact Assessment. Report P43
Staffing: No direct HR implications arising from the report. Report P41
Climate: Environmental and sustainability matters are managed through a materials and waste management plan and monitored through the social value reporting process. Report P42
Other: Local Government Reorganisation could affect funding and compliance responsibilities, though the effect is unclear. Report P25
Who and where
Sutton Lawn sports facility users and clubs Report P38
Local residents and businesses near the site during construction Report P37, P38
Academy Transformation Trust (co-signatory and 125-year leaseholder, will own and manage the facilities) Report P15, P23
Football and tennis community in Kirkby and Sutton Report P7, P15
Nottinghamshire County Council (landowner) Report P15, P23
Timeline
2021: Towns Fund secured to deliver projects across Kirkby and Sutton including the Sutton Lawn Sports Hub Report P7
February 2025: Football Foundation grant offer received by the Council Report P23
November 2025: Cost resolution meeting held; maximum Phase 1 contract value of £2,486,368.27 agreed with Lindum Group Ltd Report P20
December 2025: Executive Decision Record signed off by the Executive Lead Member for Growth, Regeneration and Local Planning on the project Report P8
January: Asbestos found in the existing changing rooms, expected to increase Phase 1 contract cost, to be covered within existing budgets Report P20
2026-02-23: Cabinet decision to accept Football Foundation grant and authorise signing of the agreement
Plain English for the jargon
3G pitch: Third generation artificial grass pitch used for football, built to current standards.
Towns Fund: Government programme providing grant funding for projects in selected towns.
MHCLG: Ministry of Housing, Communities and Local Government, the source of the Towns Fund grant.
ATT: Academy Transformation Trust, leaseholder and co-signatory that will own and manage the completed facilities.
ODR: Officer Decision Record, an internal record of an executive decision.
Phase 1: Pavilion extension and refurbishment plus new car park with 57 spaces and an overflow area of 28 spaces.
Phase 2: Removal of the existing all-weather pitch and replacement with two new 3G pitches.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.59
Resolved
RESOLVED that a) having considered the Sutton Lawn Sports Hub project proposals and its associated risks, the grant funding from the Football Foundation for a value of up to £1,846,854, be accepted; b) the Executive Director Place be authorised to sign the Football Foundation grant funding agreement for a value of up to £1,846,854 in relation to the Sutton Lawn Sports Hub project. Reason: The creation of the Sutton Lawn Sports Hub is part of the Council’s Regeneration Programme to enhance sport and leisure provision within the District .
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To update Cabinet on the project to enable a decision to be made on whether to accept grant funding from the Football Foundation of up to £1,846,854.
Recommendation(s)
a) Consider whether to accept the risks associated with acceptance of the grant funding from the Football Foundation for a value of up to £1,846,854 in relation to the Sutton Lawn Sports Hub, and subject to this decision. b) Authorise the Executive Director Place to sign the Football Foundation grant funding agreement for a value of up to £1,846,854 in relation to the Sutton Lawn Sports Hub.
Reasons for Recommendation(s)
The creation of the Sutton Lawn Sports Hub is part of the Council’s Regeneration Programme to enhance sport and leisure provision within the District.
Alternative Options Considered To not proceed with the project or only move ahead with phase 1 (car park and changing rooms) – these options would not deliver the improved and expanded sports facilities at Sutton Lawn and the subsequent benefits to the community through increased access to sport and physical activity and improved wellbeing, and therefore would not directly contribute to the priorities of the Corporate Plan.
Detailed Information Ashfield District Council secured funding from the government through the Towns Fund programme in 2021 to deliver projects across Kirkby and Sutton including the Sutton Lawn Sports Hub which will provide enhanced facilities for tennis and football. The overall cost of the football hub is c.£5.5m, with £3,182,633 allocated from Towns Fund and Academy Transformation Trust. . The Football Foundation has approved a capital grant offer of 40% of the total project cost subject to a maximum payment of £1,846,854.
An Executive Decision Record was signed off by the Executive Lead Member for Growth, Regeneration and Local Planning in December to undertake the following:
a) To enter into contract with Lindum Group Ltd as Principal Contractor to carry out the construction works at Sutton Lawn Sports Hub to the maximum value as outlined in the report.
b) To Grant delegated authority to the Executive Director – Place, in consultation with the Executive Lead Member for Growth, Regeneration and Local Planning, to join the Football Foundation’s Framework for 3G pitches and enter into contract for the construction of two 3G pitches.
c) To accept and sign the Football Foundation funding agreement for the value of £1,846,854 (40% of costs capped at £1,846,854) (subject to further ODR).
d) Grant delegated authority to the Executive Director – Place, in consultation with the Executive Lead Member for Growth, Regeneration and Local Planning to sign and enter into a ‘Partnership Agreement’ and ‘License to Occupy’ with Academy Transformation Trust. The agreements detail obligations and responsibilities of both parties including the terms and conditions of the Football Foundation funding (subject to further ODR).
Due to ongoing discussions with the Football Foundation following this decision and subsequent legal advice, it is now considered that only recommendation (a) above should be implemented (subject to confirmation of revised budgets due to the need for additional works as described further below) and that Cabinet needs to be brought up to date with the risks for the Council associated with the grant funding conditions before a final decision is taken on accepting the funding.
The Project
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.