Ashfield District Council
Council, Monday 13 April 2026 at 7.00pm

Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - Capital Programme Funding

Approved Committee 1 paper

AI summaryAshfield Council approved £7,761,342 of additional capital funding for the ADMC and AITP projects, subject to Cabinet backing the same day. Two councillors voted against.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor ADMC and AITP, two councillors voted against
Money£7,761,342Additional capital to be added to Capital Programme
What happens nextCabinet to consider outline business caseSame day, before Council meeting
Who it affectsBusinesses, residents and learners in AshfieldPlus Towns Fund partners MHCLG, NTU and VWNC

What was decided

Council approved additional capital funding for the ADMC and AITP projects as recommended by Cabinet, subject to Cabinet approval earlier the same day. Report P3

An increase of £7,761,342 to the Capital Programme is to be added to enable the two interdependent projects to proceed. Report P29, P45

Councillors Dawn Justice and Cathy Mason asked for their votes against the decision to be recorded in the minutes.

Why

Nottinghamshire County Council, as highways authority, required significantly enhanced roads, drainage, junctions, cycle paths and lighting to support the full AITP site, raising highways costs from £3.5 million to £9.5 million. Report P5, P26

These highways works form part of the ADMC planning permission, so ADMC cannot proceed without them, and the two projects have become interdependent. Report P5, P27

Without approval, the council would have to repay Towns Fund monies to MHCLG, with £9.7m already spent on the projects to date. Report P7

What happens next

Cabinet to consider the outline business case for AITP on 13 April 2026 before the Council meeting later the same day, with a verbal update to Council. Report P30

A detailed business case on the preferred AITP delivery options will come to a future Cabinet meeting for approval. Report P29

Options for AITP including phasing, seeking a development partner, selling the site or doing nothing are being explored in the outline business case. Report P28, P29

The money

  • £7,761,342 Additional capital funding to be added to Capital Programme for ADMC and AITP Report P29, P45
  • £62.6 million Towns Fund award to Ashfield for 16 regeneration projects, highest single local authority allocation in the country Report P10
  • £19m Towns Fund allocation for ADMC Report P11
  • £10m Approximate match funding in kind from NTU and VWNC for ADMC Report P11
  • £21,733,141 Current budget for the ADMC project Report P29
  • £29,494,483 Total projected cost of constructing ADMC, opening the facility and completing highways works Report P29
  • £4.48 million Total purchase price of the entire ADMC/AITP site Report P26
  • £516,462 Land cost apportioned to ADMC Report P26
  • £3.96 million Land cost relating to the AITP Report P26
  • £265,000 Anticipated cost for masterplanning, surveys and outline planning submission Report P26
  • £3.5 million Original ADMC highways improvements budget Report P26
  • £9.5 million New total expected highways works cost Report P26
  • £6 million Uplift in highways costs attributable to AITP Report P26
  • £9.7m Current spend to date, including land purchase, if projects do not proceed Report P7

Options considered

  • Chosen: Approve additional capital funding of £7,761,342. Required to deliver both interdependent projects and avoid repaying Towns Fund monies to MHCLG Report P3, P6, P7
  • Rejected: Do not approve additional capital funding. Would halt both projects and require repayment of Towns Fund monies to MHCLG Report P7
  • Rejected: Phased development of AITP, development partner, selling the site, or doing nothing. To be set out in outline business case with preferred options coming to a future Cabinet meeting Report P28, P29

Implications

  • Financial: £7,761,342 to be added to the Capital Programme, with some or all potentially reimbursed from future AITP land sales; further funding may be needed depending on the AITP option chosen. Report P45
  • Legal: Approval of changes and additions to the Capital Programme rests with Council, not Cabinet. Report P40
  • Risk: Risk of having to repay Towns Fund grant monies to MHCLG if the ADMC project cannot proceed, mitigated by ongoing engagement and a Memorandum of Understanding extending delivery to March 2028. Report P51
  • Risk: Delivery risks include financial viability, dependency between ADMC and AITP, volatile land values, planning risks around flood mitigation and resident concerns, plus invasive species and drainage issues. Report P28
  • Risk: Changing economic conditions could affect construction costs and land values, with contracts in place to lock in supplier costs but full mitigation not possible. Report P53
  • Equalities: No equalities issues identified and an Equality Impact Assessment was not required. Report P57
  • Staffing: No human resources issues identified in the report. Report P55

Who and where

  • Local businesses in manufacturing, distribution and fulfilment sectors in Ashfield and the wider Midlands Report P13, P15
  • Residents of Kirkby and Sutton, with the project aiming to raise skills, qualifications, job security and wages Report P10, P16
  • Vision West Nottinghamshire College and Nottingham Trent University as delivery partners for skills and training Report P11, P14
  • Future employers and workers on the wider AITP site, with potential for 500 to 1,000 new jobs Report P23
  • Adjacent residential properties to the north of the site, due to retention or enhancement of green buffer space and drainage design for local flooding Report P23

Timeline

  • 2021: Council secured £62.6 million Towns Fund for 16 regeneration projects including ADMC Report P10
  • September 2023: Cabinet approved purchase of the Lowmoor Road site Report P18, P22
  • July 2024: Planning approval secured for the ADMC building Report P18
  • December 2024: Land purchase completed Report P18
  • August 2025: Site preparation work began, including utilities, hedgerow removal and invasive species clearance Report P19
  • 13 April 2026: Cabinet to consider AITP outline business case, with Council to decide on additional capital funding later the same day Report P3, P30
  • March 2028: Extended Towns Fund delivery deadline under a Memorandum of Understanding with MHCLG Report P51

Plain English for the jargon

  • ADMC: Automated Distribution and Manufacturing Centre, the council's flagship Towns Fund project
  • AITP: Ashfield Innovation and Technology Park, the wider commercial site around ADMC
  • Towns Fund: Government funding programme for town centre and regeneration projects
  • MHCLG: Ministry of Housing, Communities and Local Government, the funder of Towns Fund
  • NTU: Nottingham Trent University, a delivery partner for ADMC skills and training
  • VWNC: Vision West Nottinghamshire College, a delivery partner for ADMC skills and training
  • Section 278 agreement: Legal agreement with the Highways Authority for works to the public highway
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC.84

Resolved

RESOLVED that additional capital funding be approved for the Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) projects, as set out in the report, and in accordance with the capital funding recommendations approved by Cabinet earlier in the day. (In accordance with Council Procedure Rule 18.6 [Right to Require Individual Vote to be Recorded], Councillors Dawn Justice and Cathy Mason requested that their votes against the decision taken, be so recorded in the minutes.)
Word for word from the decision Ashfield published for this meeting. Source: democracy.ashfield.gov.uk

Follow this further

Built from Ashfield's papers

What the report saysPro

Report to Council

Purpose of report

This report seeks approval from Council for additional capital funding for the Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) projects.

Recommendation(s)

Subject to recommendations relating to capital funding being approved by Cabinet on 13 April 2026, Council is asked to approve additional capital funding for the Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) projects as set out in the report.

Reasons for Recommendation(s)

Significantly enhanced highways and infrastructure work to support the full build-out of the entire AITP site, rather than just the ADMC works, has led to significant increases in project costs to successfully deliver both projects. As these infrastructure / highways works form a part of the planning permission for ADMC, that project cannot proceed without these wider works also taking place.

The additional project costs for the whole site are not currently included in the Capital Programme. Council approval is required to add these costs to the Capital Programme to enable the two interdependent projects to proceed.

Alternative options considered

To not approve the additional capital funding. This option is not recommended. Without approval for the full project costs as set out in the report, the two projects (ADMC and AITP) will not be able to proceed, this would lead to the Council having to repay Towns Fund monies to MHCLG. Project costs expended to date, plus land purchase costs see current spend totalling £9.7m. Further options regarding the delivery of the AITP and how it and the ADMC project are interdependent are detailed in the report.

Detailed Information

PROJECT BACKGROUND - AUTOMATED DISTRIBUTION AND MANUFACTURING CENTRE (ADMC)

In 2021, Ashfield District Council secured £62.6 million from the Towns Fund to support 16 regeneration projects in Kirkby and Sutton including the Automated Distribution and Manufacturing Centre (ADMC). The Towns Fund award represents the highest allocation for a single local authority area in the country.

The ADMC is the Council’s flagship Towns Fund project. The Towns Fund allocation for ADMC was £19m with additional match funding (in kind) in the region of £10m from other partners, namely Nottingham Trent University (NTU) and Vision West Notts College (VWNC).

The ADMC project is being created as a national centre of excellence for automation, based in Ashfield and serving the wider Midlands region.

The ADMC is being developed as a centre for automation technology and skills development, with a focus on stimulating innovation in businesses working in the local and regional manufacturing, distribution and fulfilment sectors. It aims to boost productivity and competitiveness within local businesses through the enhanced adoption of automation in its different forms.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP): Capital Programme FundingReport 110 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

27 of 47 attended
KB
Councillor Kier BarsbyCommittee Member, present
JB
Councillor Jamie BellCommittee Member, present
WB
Councillor Will BostockCommittee Member, present
IB
Councillor Ian BriggsCommittee Member, present
JC
Councillor Jodine CronshawCommittee Member, present
SD
Councillor Samantha DeakinCommittee Member, present
AE
Councillor Anna EllisCommittee Member, present
AG
Councillor Andy GascoyneCommittee Member, apologies
PG
Councillor Paul GraftonChairman, present
JG
Councillor Julie GregoryCommittee Member, present
DG
Councillor Dale GroundsVice-Chair, present
AH
Councillor Arnie HankinCommittee Member, apologies

All 47 on the meeting page

On this subject at Ashfield

Search all
  1. Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - Capital Programme FundingThis decision
  2. Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - UpdateNoted
  3. Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) – UpdateNoted
  4. Automated Distribution and Manufacturing Centre (ADMC)Noted

More from Ashfield Council

All decisions
MeetingDecisionOutcome
27 Jul 2026 Local Government Reorganisation - UpdateRESOLVED that the information provided, and the ongoing work being undertaken to support the LGR transition programme... Noted Open
27 Jul 2026 Recommendations from the Cabinet and the Council's CommitteesRESOLVED that a) being satisfied that a land exchange is in the best interests of the charitable trust, Council appro... Approved Open
27 Jul 2026 Notice of Motion 1RESOLVED that a) the Council asks the Leader of the Council and Chief Executive to write to Government calling for a ... Decided Open
27 Jul 2026 Notice of Motion 2RESOLVED that this Council agrees to: a) ask Cabinet to bring forward a simple Ashfield Pub Protection Plan; b) revie... Agreed Open
18 May 2026 Election of Chairman of the CouncilRESOLVED that Councillor Dale Grounds be elected Chairman of the Council until the next Annual Meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies