Ashfield District Council
Cabinet, Monday 15 June 2026 at 10.00am

Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) – Update

Noted Executive 2 papers

AI summaryCabinet noted that construction contracts are in place and work restarted on 11 May 2026 on the ADMC and AITP projects, with completion expected by December 2027. It approved a draft Improvement Plan and asked Audit Committee to monitor its delivery.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet also noted contracts, restart and project management
Money£7,761,342Capital Programme allocation approved by Council in April 2026
What happens nextAITP business case to CabinetExpected September or October 2026
Who it affectsContractors, MHCLG, future businesses and learnersADMC site construction, AITP commercial development pipeline

What was decided

Cabinet noted that required contractual arrangements were in place, work restarted on site on 11 May 2026, and project management arrangements had been put in place, alongside further work to identify improvements to the management of capital projects. Report P8, P11, P14, P15, P16

Cabinet approved the draft Improvement Plan attached at Appendix 1, noting where improvements had already been made. Report P18

Cabinet asked Audit Committee to monitor delivery of the Improvement Plan, to ensure transparency and accountability. Report P24

Why

Cabinet requested an update at its June meeting following consideration of various reports in April 2026 in response to the Monitoring Officer's report under Section 5A of the Local Government and Housing Act 1989. Report P1, P2, P3

The Improvement Plan is to be monitored by the Audit Committee to ensure transparency and accountability, taking account of the Independent Review recommendations. Report P3, P18

What happens next

The S278 Highways Act 1980 agreement with Nottinghamshire County Council is to be finalised, signed and sealed. Report P9

Initial foundation and ground works are due to be completed by end of July 2026, enabling initial steelwork to be erected in August 2026, with overall estimated completion in December 2027. Report P12, P13

The full AITP business case will be brought to Cabinet in September or October 2026, with an outline planning application to be submitted in advance, and a further Deep Dive report on the Improvement Plan is expected with the Chief Executive at the end of May 2026. Report P18, P20, P21

The money

  • £7,761,342 Additional capital funding allocated from the Capital Programme for the ADMC and AITP projects, approved by Council on 13 April 2026 Report P4

Options considered

  • Chosen: Bring forward the whole AITP site as one development. One of the two preferred options identified in April 2026, to be developed further Report P3, P20
  • Chosen: Bring forward the AITP development in two phases. Other preferred option identified in April 2026, to be developed further Report P3, P20

Implications

  • Financial: Risk of insufficient funding to deliver the approved outline business case is being mitigated by the increased Capital Programme allocation; contracts with suppliers lock in costs but contingency is needed for changing construction costs and land values. Report P33, P34
  • Legal: External legal advice has been obtained to support the Council's actions so as to reduce the risk of legal challenge; the S278 Highways Act 1980 agreement with Nottinghamshire County Council is being finalised. Report P9, P28, P34
  • Risk: Risk of MHCLG requiring repayment of Towns Fund grant monies if the ADMC cannot proceed has been addressed through a meeting with MHCLG, who are content with the steps taken and have given no indication grant monies are at risk; a Memorandum of Understanding has extended the Towns Fund delivery timeframe to March 2028. Report P34
  • Other: Engagement has taken place with MHCLG, Mazars (external auditors), CMAP (internal auditors) and the Chair and Vice Chair of the Audit Committee throughout the process, and will continue alongside Audit Committee monitoring. Report P23, P24
  • Equalities: No equalities issues were identified, and it was assessed that an Equalities Impact Assessment was not required. Report P37
  • Staffing: Additional external project management support has been brought in alongside the existing team and the Senior Responsible Officer to improve monitoring, reporting and governance. Report P14, P15, P16, P35

Who and where

  • Lindum Group Ltd (building construction and highways/infrastructure contractor) Report P6, P11
  • YMD Boon (agent for Armson & Partners Ltd) and Armson & Partners Ltd (design services up to RIBA Stage 4) Report P6
  • Nottinghamshire County Council (S278 Highways Act 1980 agreement) Report P6, P9
  • MHCLG (Towns Fund grant provider) Report P23, P34
  • Mazars (external auditors) and CMAP (internal auditors) Report P23
  • Future businesses and learners expected to use the ADMC services Report P34

Timeline

  • 13 April 2026: Cabinet considered the S5A Report and Council approved £7,761,342 additional capital funding for the two projects Report P1, P2, P3, P4
  • 20 April 2026: Cabinet approved direct awards to Lindum Group Ltd, YMD Boon and Armson & Partners Ltd, and authorised signing of the S278 agreement Report P5, P6
  • End of May 2026: Deep Dive report on the Improvement Plan expected with the Chief Executive Report P18
  • 11 May 2026: Substantive construction works recommenced on site Report P11
  • End of July 2026: Initial foundation and ground works due to be completed Report P13
  • August 2026: Initial steelwork due to be erected Report P13
  • September or October 2026: Full AITP business case to be brought to Cabinet, with outline planning application submitted in advance Report P21
  • December 2027: Estimated completion date for the ADMC construction Report P12
  • March 2028: Extended Towns Fund delivery timeframe under the Memorandum of Understanding with MHCLG Report P34

Plain English for the jargon

  • ADMC: Automated Distribution and Manufacturing Centre, the construction project led by the Council
  • AITP: Ashfield Innovation and Technology Park, the wider commercial development site
  • S278: Section 278 Highways Act 1980 agreement, under which developers fund or carry out highway works
  • S5A Report: Report by the Monitoring Officer under Section 5A of the Local Government and Housing Act 1989
  • MHCLG: Ministry of Housing, Communities and Local Government, the Towns Fund grant provider
  • Towns Fund: UK government funding programme for town centre regeneration
  • RIBA: Royal Institute of British Architects work stages, used here up to and including Stage 4
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.3

Resolved

RESOLVED that a) the following be received and noted: · all required contractual arrangements were now in place; · work recommenced on site on 11 May 2026; · the project management arrangements put in place; · the further work undertaken to identify improvements to the Council’s management of capital projects; b) the draft Improvement Plan attached at Appendix 1 noting where improvements had already been made, be approved; c) Audit Committee to be asked to monitor the delivery of the Improvement Plan. Reasons: 1. To ensure that Cabinet is updated in relation to the ADMC and AITP projects. Cabinet requested an update be brought to its June meeting following consideration of various reports in April 2026 in response to the report of the Monitoring Officer pursuant to S5A Local Government and Housing Act 1989. 2. It is recommended that the Improvement Plan is monitored by the Audit Committee to ensure transparency and accountability.
Word for word from the decision Ashfield published for this meeting. Source: democracy.ashfield.gov.uk

Follow this further

Built from Ashfield's papers

What the report saysPro

Report to Cabinet

Background

On 13 April 2026 the Cabinet received a report prepared by the Executive Director, Governance and Monitoring Officer issued under Section 5A of the Local Government and Housing Act 1989 (S5A Report). It also received a further report in order to consider what actions to take in response to that report.

On 13 April Cabinet:

1. Considered the report prepared by the Executive Director, Governance and Monitoring Officer issued under Section 5A of the Local Government and Housing Act 1989. 2. Noted the communication and engagement with stakeholders and partners and their responses. 3. Noted and considered the Independent Review report. 4. Recommended that the Chief Executive develops an Improvement Plan taking account of the recommendations of the Independent Review to be reported back to Cabinet in June with the intention of referral to the Audit Committee to monitor its implementation. 5. Received and accepted the outline business case relating to AITP identifying that options 2 and 3 are to be developed further with the expectation that the Chief Executive brings a detailed business case to the Cabinet meeting in June. 6. Recommended that Council approve additional capital funding for the ADMC and AITP projects.

At the Council meeting on 13 April, Council resolved to approve additional capital funding for the ADMC and AITP projects. Council approved £7,761,342 be allocated from the Capital Programme to allow the two interdependent projects to proceed.

Cabinet met again on 20 April 2026 following Council approving additional capital funding and:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP): UpdateReport 114 KB DownloadRead as text
PDF
Corporate Assurance Improvement PlanReport 69 KB Download

At this meeting

Whole meeting

Who was there

7 of 23 attended
SD
Councillor Samantha DeakinChairman, present
PG
Councillor Paul GraftonCommittee Member, present
VH
Councillor Vicki HeslopCommittee Member, present
CH
Councillor Christopher HuskinsonCommittee Member, apologies
RM
Councillor Rachel MaddenCommittee Member, apologies
AM
Councillor Andy MeakinCommittee Member, present
MR
Councillor Matthew RelfCommittee Member, present
HS
Councillor Helen-Ann SmithCommittee Member, present
JW
Councillor John WilmottCommittee Member, present
JZ
Councillor Jason ZadroznyChairman, apologies
JB
John BennettOfficer, in attendance
CB
Craig BonarOfficer, in attendance

All 23 on the meeting page

On this subject at Ashfield

Search all
  1. Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) – UpdateThis decision
  2. Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - UpdateNoted
  3. Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - Capital Programme FundingApproved
  4. Automated Distribution and Manufacturing Centre (ADMC)Noted

More from Ashfield Cabinet

All decisions
MeetingDecisionOutcome
27 Jul 2026 Local Government Reorganisation (Verbal Update and Q/A Session)RESOLVED that a) the information provided and the ongoing work being undertaken to support the transition programme, ... Noted Open
27 Jul 2026 Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be... Noted Open
27 Jul 2026 Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas... Noted Open
27 Jul 2026 Update - Charitable Trust Issues at Lord Francis Park (Kirkby-in-Ashfield), Hucknall Leisure Centre and Titchfield Park (Hucknall)RESOLVED that a) the current position relating to Charitable Trust Issues at Lord Francis Park (Kirkby-In-Ashfield), ... Noted Open
27 Jul 2026 Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ... Noted Open