Ashfield District Council
Audit Committee, Thursday 25 June 2026 at 7.00pm

Public Sector Decarbonisation Scheme

Noted Finance 1 paper

AI summaryAudit Committee noted findings of a review into the Public Sector Decarbonisation Scheme that found no formal governance and an overspend of about £2 million, and asked the Assistant Director for Assets for a progress report.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAudit review received, update due next meeting
MoneyOverspend of approximately £2 millionPhase 1 leisure centre costs understated by approx. £306k
What happens nextProgress report to next meetingFrom the Assistant Director for Assets
Who it affectsPublic Sector Decarbonisation SchemeDecarbonisation at Council Offices and Hucknall Leisure Centre

What was decided

The Committee received and noted the findings of the Public Sector Decarbonisation Scheme review.

The Assistant Director for Assets was asked to provide a progress report to the next meeting of the Committee.

The Chairman moved to take agenda items 13 (Exemption) and 14 (Investment Property Performance 2025/26) as the next items of business, with Members' agreement.

Why

The Council had identified potential project governance issues and overspends of approximately £2 million and asked the audit partnership to review the scheme. Report P10, P11, P112

The audit gave a No Assurance rating and made 12 recommendations: three low risk, seven moderate, two significant. Report 1.3, P16, P19, P20

The audit found no formal governance structure, weak contractor management, missing business case, accounting errors, and contract variations that were not drawn up by Legal. Report P16, P19, P94, P114, P115, P146, P149, P150

What happens next

The Assistant Director for Assets will provide a progress report to the next meeting of the Committee.

All 12 recommendations have an agreed implementation date of 31/07/2026, with PSDS to report into a new Regeneration and Capital Board. Report P16, P19, P48, P84, P88

The Executive Director, Operations is now Senior Responsible Officer for the project and the governance structure is being reviewed. Report P84, P88, P91

The money

  • approximately £2 million overspend on the Public Sector Decarbonisation Scheme project Report P10, P112
  • £22,200 first contract variation for external project managers (1st April 2023 to 31st March 2024) Report P52, P58
  • £21,600 payments made to project managers under first appointment Report P58
  • £20,000 budget for second appointment of external consultants from 1st April 2024 Report P34, P59
  • £19,125 payments made to project managers under second appointment Report P59
  • £72,247.50 + VAT third appointment value under Consultancy Plus Framework Report P54, P63
  • £363,459.36 value of each of two contractor invoices from December 2023 Report P106
  • approx. £306k understatement of phase 1 Hucknall Leisure Centre outturn costs Report P114
  • £358k proposed further increase reported to Cabinet 16th September 2024 Report P115, P134
  • £2.012m grant funding added to capital programme, approved by Council 2nd March 2023 Report P124
  • £317,167 prudential borrowing matched with grant at September 2023 Report P127
  • £2,329,301 total programme budget at September 2023 Report P127
  • £3.828m approved capital budget for the projects at 16th September 2024 Report P134
  • £4.186m current cost estimate at 16th September 2024 Report P134
  • £200k additional funding requested for Hucknall Leisure Centre new substation Report P130
  • £130k additional funding for Council Offices design costs Report P133
  • circa £1.93m value of contract signed 21st December 2023 with leisure contractor Report P142

Options considered

  • Rejected: Reduce project scope or change delivery approach to manage overspend. Papers note all options under review were likely to lead to additional cost and a shortfall in approved budget, but do not list the individual options. Report P125, P127, P129

Implications

  • Financial: Overspend of approximately £2 million identified and a £306k accounting error understated reported outturn figures. Report P10, P112, P114
  • Legal: Risk of non-compliance with Contract Procedure Rules could lead to disciplinary action and legal proceedings against officers. Report P39, P47, P55, P157
  • Risk: Two significant risk recommendations: lack of formal governance and ineffective arrangements to manage, monitor and govern major projects. Report P16, P19, P81, P149
  • Staffing: Departure of key senior officers left over reliance on the Projects and Procurement Team Leader. Report P19, P86, P87
  • Other: Risk of reputational damage and loss of public confidence if governance of major projects does not improve. Report P39, P55, P94, P102, P157

Who and where

  • Council staff involved in major project delivery, especially the Projects and Procurement Team and the Executive Director, Operations Report P67, P86, P87, P88
  • Contractors engaged on the Public Sector Decarbonisation Scheme, including the leisure contractor and external project managers Report P96, P101, P106, P142
  • Cabinet and Senior Leadership Team, who received erroneous budget updates Report P19, P117
  • Council's Legal Team, which did not receive instructions to prepare a contract variation Report P146
  • Users of Council Offices and Hucknall Leisure Centre, the two sites receiving decarbonisation measures Report P10
  • Audit Committee, which will receive a progress report at its next meeting

Timeline

  • September 2022: Executive Decision Record approved submitting a funding bid for the Public Sector Decarbonisation Scheme Report P86
  • 2nd March 2023: Council approved adding £2.012m to the capital programme Report P124
  • 1st April 2023 to 31st March 2024: First contract variation for external project managers Report P33, P58
  • 31st July 2023: Cabinet funding update flagged potential future funding pressure Report P125
  • September 2023: Cabinet programme monitoring report set total budget of £2,329,301 Report P127
  • 25th September 2023: Council approved additional funding (exempt report) Report P129
  • 15th March 2024: ODR approved a variation to the leisure contractor contract Report P138
  • 1st April 2024: Second appointment of external consultants began, with £20,000 budget set by email Report P34, P59
  • 8th April 2024: Cabinet received 2023/24 forecast outturn and additional funding requests Report P130, P133
  • 16th September 2024: Cabinet received 2024/25 forecast outturn and proposed £358k increase Report P115, P134
  • November 2024: Cabinet received regeneration programmes update Report P135
  • 1st December 2024: Third appointment of external consultants under Consultancy Plus Framework took effect Report P35, P63
  • 20th January 2025: Cabinet report on PSDS 3B prepared but not submitted Report P136
  • 27th February 2025: ODR approved third appointment at £72,247.50 + VAT Report P54
  • 26th June 2025: Internal report to Executive Director, Operations disclosed two accounting errors Report P113
  • August 2025: Audit fieldwork took place Report P72
  • 25th June 2026: Audit Committee received the final audit report
  • 31/07/2026: Agreed implementation date for all 12 audit recommendations Report P16, P19
  • Next meeting of the Committee: Assistant Director for Assets to provide a progress report

Plain English for the jargon

  • PSDS: Public Sector Decarbonisation Scheme, a government grant programme for heat decarbonisation and energy efficiency measures
  • CMAP: The audit partnership that carried out the review, based at Derby City Council
  • ODR: Officer Decision Record, the formal record of a decision taken by a council officer
  • EDR: Executive Function Decision Record, the formal record of a decision taken by an Executive Lead Member
  • RIBA Stage 4: Royal Institute of British Architects design stage for technical design
  • HLC: Hucknall Leisure Centre, one of the two sites receiving decarbonisation measures
  • FHSF: Future High Street Fund
  • SALIX: The funder named in the papers as SALIX, from whom advance funding claims were confirmed
  • SRO: Senior Responsible Officer, the senior officer accountable for a project
  • MTFS: Medium Term Financial Strategy
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemAC.3

Resolved

RESOLVED that a) the findings of the Public Sector Decarbonisation Scheme review, as presented, be received and noted; b) the Assistant Director for Assets be requested to provide a progress report to the next meeting of the Committee. (The Chairman informed Members, in accordance with Council Procedure Rule 4.1 [Order of Business], that he was going to take agenda items 13 (Exemption) and 14 [Investment Property Performance 2025/26] as the next items of business. All Members present at the meeting concurred with this course of action.)
Word for word from the decision Ashfield published for this meeting. Source: democracy.ashfield.gov.uk

Follow this further

Built from Ashfield's papers

What the report saysPro

Report to Audit Committee

Ashfield District Council – Public Sector Decarbonisation Scheme Review Final Audit Report

Providing Excellent Audit Services in the Public Sector April 2026 Our Vision To bring about improvements in the control, governance, and risk management arrangements of our Partners by providing cost effective, high quality internal audit services.

Head of Audit Partnership Email: Tel: Richard Boneham CPFA [email removed] 01332 643280 Audit Managers Adrian Manifold CMIIA [email removed] 01332 643281 Mandy Marples CPFA, CCIP [email removed] 01332 643282 Hannah McDonald CMIIA, APCIP [email removed] 01332 643284 Martin Shipley CMIIA, CCIP [email removed] 01332 643292

c/o Derby City Council Council House Corporation Street Derby, DE1 2FS

Providing Excellent Audit Services in the Public Sector Final Audit Report

ADC – Public Sector Decarbonisation Scheme Review

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Public Sector Decarbonisation SchemeReport 415 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 17 attended
JB
Councillor Jamie BellCommittee Member, apologies
WB
Councillor Will BostockCommittee Member, apologies
JC
Councillor Jodine CronshawCommittee Member, apologies
TH
Councillor Tom HollisCommittee Member, apologies
DJ
Councillor Dawn JusticeCommittee Member, present
WN
Councillor Warren NuttallChairman, present
DS
Councillor Dave ShawCommittee Member, present
LC
Lynn CainOfficer, in attendance
RD
Ruth DennisOfficer, in attendance
DL
Damon LawrensonOfficer, in attendance
AP
Andrew PageOfficer, in attendance
EW
Emma WimbleOfficer, in attendance

All 17 on the meeting page

On this subject at Ashfield

Search all
  1. Public Sector Decarbonisation SchemeThis decision
  2. Global Internal Audit Standards in the UK Public SectorNoted
  3. Public Sector Decarbonisation Scheme - Additional Funding (Exempt by virtue of Paragraph 3)Approved
  4. Public Sector Audit Appointments (PSAA): External Audit Fee 2020/21Noted
  5. The Future of External Audit - Proposal to opt into Public Sector Audit AppointmentsApproved

More from Ashfield Audit Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 Section 100A Local Government Act 1972: Exclusion of the Press and PublicRESOLVED that in accordance with the provisions of Section 100A of the Local Government Act 1972, the press and publi... Decided Open
25 Jun 2026 FORVIS MAZARS: 2024-25 Audit Opinion UpdateRESOLVED that the update report be received and duly noted. Noted Open
25 Jun 2026 Audit Committee Work Plan and Improvement Plan - 2026/2027RESOLVED that a) the draft Committee Work Plan 2026/2027, as attached at Appendix 1, be approved; b) the draft Improv... Approved Open
25 Jun 2026 Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - UpdateRESOLVED that a) the update report, presented to Cabinet on 15 June 2026, be received and noted; b) in line with the ... Noted Open
25 Jun 2026 Internal Audit Annual Report 2025-26RESOLVED that the Internal Audit Annual Report for 2025/26 including the supporting Internal Audit Opinion, be receiv... Noted Open