Ashfield District Council
Audit Committee, Thursday 25 June 2026 at 7.00pm

FORVIS MAZARS: 2024-25 Audit Opinion Update

Noted Finance 1 paper

AI summaryAudit Committee notes external auditor's update flagging a significant governance weakness over the £19m Towns' Fund ADMC project, with the 2024/25 financial statements opinion still outstanding.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAuditor's 2024-25 update on ADMC matters
Money£19m Towns' Fund for ADMCAllocation to construct the centre
What happens nextAuditor to issue opinion when work concludes. Pending further value-for-money procedures
Who it affectsADMC project and major capital schemesCouncil exposed to financial, legal and reputational risk

What was decided

The Committee received and noted the auditor's update on the 2024-25 audit opinion.

The auditor is to issue the 2024/25 opinion on conclusion of the planned procedures, with a further significant weakness in value for money to be reported. Report P7, P8, P13

Why

Officers alerted the auditor in February 2026 to concerns over the ADMC project, leading to an independent review and a Section 5A report by the Monitoring Officer. Report P7, P8

The review found systemic governance and internal control weaknesses, including works starting without contracts, payments made without contractual cover, weak procurement advice and poor cost monitoring, with no evidence of fraud or intentional misconduct. Report P8, P9, P15

There is also a possibility of material errors in the 2024/25 financial statements that need investigation before the audit can be completed. Report P7

What happens next

The Council must resolve a way forward for the ADMC scheme, including engagement with MHCLG over Towns' Fund monies, and approve an updated business case and additional capital funding. Report P15

The Council must carry out a comprehensive review of all major projects, establish a proper project governance framework, and reinforce officers' understanding of contract and financial rules and the Nolan Principles. Report P15

The auditor will finalise the draft value-for-money wording through internal consistency checks and is awaiting further responses, including a meeting with MHCLG. Report P7

The money

  • £19m Towns' Fund allocation to construct the Automated Distribution and Manufacturing Centre Report P15

Options considered

  • Chosen: Receive and note the auditor's update report. Standard committee action to acknowledge the auditor's position

Implications

  • Legal: Risk of legal challenge and non-compliance with the Public Contracts Regulations 2025 and the Council's own Contract Procedure Rules, with external legal advice already sought. Report P7, P8, P15
  • Financial: Material financial risk from expenditure without signed contracts and the need for additional capital funding for the ADMC and associated projects. Report P7, P8, P15
  • Risk: Auditor has identified a significant weakness in the Council's governance arrangements over a major scheme, exposing the Council to financial loss, legal challenge and reputational harm. Report P8, P15
  • Governance: Systemic weaknesses in governance and internal control over a prolonged period, including failures in risk assessment, decision-making and compliance with procurement and contract management requirements. Report P8, P9
  • Other: Reputational risk to the Council, with MHCLG notified and a Section 5A report issued. Report P7, P8

Who and where

  • The Council and its members Report P7, P8, P15
  • The ADMC project and associated projects Report P15
  • Officers involved in procurement, contract management and project delivery Report P8, P9, P15
  • Suppliers paid without contracts in place Report P8, P15
  • MHCLG, as funder under the Towns' Fund initiative Report P7, P15

Timeline

  • 1 April 2025: HM Treasury changes to non-investment asset valuation effective, moving to a five-yearly revaluation cycle with annual indexation Report P17, P18
  • February 2026: Officers alerted the auditor to significant concerns about the ADMC Report P7
  • 19 March 2026: Verbal update given to the Audit Committee confirming the 2024/25 financial statements opinion was not yet issued Report P10
  • 31 March 2026: Monitoring Officer published the Section 5A Report on the ADMC project Report P15
  • 13 April 2026: Paper presented to the Council on the auditor's planned procedures and results to date Report P10
  • 25 June 2026: Audit Committee meeting at which this update was received and noted
  • 1 January 2027: IFRS 18 Presentation and Disclosure in Financial Statements effective for accounting periods beginning on or after this date Report P22
  • 2028/29 financial year (expected): IFRS 18 expected to be incorporated into the Code of Practice on Local Authority Accounting Report P22

Plain English for the jargon

  • ADMC: Automated Distribution and Manufacturing Centre, the major capital project at the centre of the audit concerns.
  • Section 5A report: Formal report by a local authority's Monitoring Officer under Section 5A of the Local Government and Housing Act 1989 where a proposal, decision or omission may have resulted in unlawful action or non-compliance with an approved code of practice.
  • MHCLG: Ministry of Housing, Communities and Local Government, the government department that allocated Towns' Fund monies to the Council.
  • Towns' Fund: Government funding initiative from which the Council received £19m for the ADMC.
  • Value for money arrangements: The auditor's assessment of whether the Council has made proper arrangements to secure economy, efficiency and effectiveness in its use of resources.
  • IFRS 18: New international accounting standard on Presentation and Disclosure in Financial Statements, replacing IAS 1 and introducing new categories, subtotals and management performance measure disclosures.
  • The Code: Code of Practice on Local Authority Accounting in the United Kingdom, which sets the accounting requirements for local authority accounts.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemAC.6

Resolved

RESOLVED that the update report be received and duly noted.
Word for word from the decision Ashfield published for this meeting. Source: democracy.ashfield.gov.uk

Follow this further

Built from Ashfield's papers

What the report saysPro

Report to Audit Committee

2024-25 Audit Opinion Update Ashfield District Council – Year ending 31 March 2026

June 2026 Contents

2024-25 Audit Opinion Update 3 Value for Money Arrangements Wording 4

Appendices A - Current year updates, forthcoming accounting & other issues 5

This document is to be regarded as confidential to Ashfield District Council. It has been prepared for the sole use of Audit Committee as the appropriate sub-committee charged with governance. No responsibility is accepted to any other person in respect of the whole or part of its contents.

2 2024-25 Audit Opinion Update

In February 2026, officers alerted us to significant concerns relating to the Automated report also indicated that an additional significant weakness will be reported for 2024/25, with Distribution and Manufacturing Centre (ADMC), which led to an independent review and the the draft wording subject to internal consistency checks. We are currently awaiting further Monitoring Officer’s decision to issue a Section 5A report. Under Section 5A of the Local responses, including a meeting with MHCLG, to complete our assessment of the actions taken Government and Housing Act 1989, a Monitoring Officer must formally report where a proposal, and the conclusions reached. decision or omission may have resulted in unlawful action or non-compliance with an approved code of practice. The Council also notified MHCLG and sought external legal advice regarding We have also been alerted to the possibility of material errors in the 2024/25 financial expenditure incurred without signed contracts. statements, which need to be investigated prior to completion.

The issues underpinning the Section 5A report demonstrate that the Council was exposed to We will issue our onion on conclusion of our planned procedures. material financial, legal and reputational risk. The independent review and the Monitoring Officer’s findings identified systemic weaknesses in governance and internal control, including failures to enter into contracts before works commenced, payments made without contractual cover, inadequate procurement advice, and insufficient monitoring of project costs against approved budgets. While no evidence of fraud or intentional misconduct was identified, the failures occurred over a prolonged period and reflect deficiencies in risk assessment, decision-making, and compliance with procurement and contract management requirements.

We have met with senior officers and reviewed the Section 5A report, the independent review, the Strategic Risk Register and the amendments made to the 2024/25 Annual Governance Statement. Our work to date indicates that the Council’s arrangements for overseeing major capital schemes lacked the necessary project-specific risk assessment, documentation and oversight to prevent the issues that materialised within the ADMC project.

At the 19 March Audit Committee meeting, we provided a verbal update confirming that the 2024/25 opinion on the Council’s financial statements has not yet been issued due to the additional value-for-money work required. A paper was presented to the Council on 13 April setting out our planned procedures and results to date in relation to the Section 5A matter. The

3 Value for money arrangements wording

Update since the issuance of our Annual Auditors Report 2024/25

Our finding is set out below, with the wording being draft and subject to finalisation through our internal process.

Identified significant weakness in arrangements Reporting Criteria Recommendation(s) for improvement

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FORVIS MAZARS: 2024-25 Audit Opinion UpdateReport 327 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 17 attended
JB
Councillor Jamie BellCommittee Member, apologies
WB
Councillor Will BostockCommittee Member, apologies
JC
Councillor Jodine CronshawCommittee Member, apologies
TH
Councillor Tom HollisCommittee Member, apologies
DJ
Councillor Dawn JusticeCommittee Member, present
WN
Councillor Warren NuttallChairman, present
DS
Councillor Dave ShawCommittee Member, present
LC
Lynn CainOfficer, in attendance
RD
Ruth DennisOfficer, in attendance
DL
Damon LawrensonOfficer, in attendance
AP
Andrew PageOfficer, in attendance
EW
Emma WimbleOfficer, in attendance

All 17 on the meeting page

On this subject at Ashfield

Search all
  1. FORVIS MAZARS: 2024-25 Audit Opinion UpdateThis decision
  2. FORVIS MAZARS: Auditors Report 2025 - Management ResponseNoted
  3. FORVIS MAZARS: External Audit Progress ReportNoted
  4. FORVIS MAZARS - Audit Strategy Memorandum – Year ending 31 March 2025Noted

More from Ashfield Audit Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 Public Sector Decarbonisation SchemeRESOLVED that a) the findings of the Public Sector Decarbonisation Scheme review, as presented, be received and noted... Noted Open
25 Jun 2026 Section 100A Local Government Act 1972: Exclusion of the Press and PublicRESOLVED that in accordance with the provisions of Section 100A of the Local Government Act 1972, the press and publi... Decided Open
25 Jun 2026 Audit Committee Work Plan and Improvement Plan - 2026/2027RESOLVED that a) the draft Committee Work Plan 2026/2027, as attached at Appendix 1, be approved; b) the draft Improv... Approved Open
25 Jun 2026 Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - UpdateRESOLVED that a) the update report, presented to Cabinet on 15 June 2026, be received and noted; b) in line with the ... Noted Open
25 Jun 2026 Internal Audit Annual Report 2025-26RESOLVED that the Internal Audit Annual Report for 2025/26 including the supporting Internal Audit Opinion, be receiv... Noted Open