That the Manydown Executive Committee: 1) Consider the comments of the Manydown Overview Committee in respect to the matters contained in the report 2) Note the progress made with the Manydown project 3) Notes the representation made on the Draft Manydown Development Brief (Appendix 1 of the report) 4) Note the representation made on the Community Infrastructure Levy Draft Charging Schedule (Appendix 2 of the report) 5) Note the consolidated financial statement for the Manydown project in 2015/16 (Appendix 3 of the report) 6) Approve the release of up to £244k additional funding from the Strategic Capital Reserve into the Manydown project budget Reasons for decision: To continue to pursue the development of Manydown and secure the better planning of the area in accordance with the Full Council resolution on 12 July 2012 by proceeding with work to finalise an overall masterplan and submit relevant planning applications for Manydown .
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
1.1This report provides an update on progress with the Manydown project.
Recommendation
It is recommended that the Manydown Executive Committee:
i. considers the comments of the Manydown Overview Committee in respect to the matters contained in this report
ii. notes the progress made with the Manydown project
iii. notes the representation made on the Draft Manydown Development Brief (Appendix 1 to follow)
iv. notes the representation made on the Community Infrastructure Levy Draft Charging Schedule (see Appendix 2)
v. notes the consolidated financial statement for the Manydown project in 2015/16 (see Appendix 3)
vi. approves the release of up to £244k additional funding from the Strategic Capital Reserve into the Manydown project budget
Page 1 of 12 PRIORITIES, IMPACTS AND RISKS
Contribution to Council Priorities This report accords with the council’s Budget and Policy Framework and directly supports the Council Plan priority of planning policies that safeguard local distinctiveness to: “Promote the use of Manydown land to deliver much needed high quality homes and facilitate wider borough benefit, which protects local communities”
GLOSSARY OF TERMS Term Definition BDBC Basingstoke and Deane Borough Council CIL Community Infrastructure Levy CDE Community Design Event DCLG Communities Local Government department Deco Development Company EM3 Enterprise M3 Local Enterprise Partnership EPH Economic Planning and Housing Committee EIA Environmental Impact Assessment EIP Examination in Public HCA Homes and Community Agency HCC Hampshire County Council JV Joint Venture LPA Local Planning Authority Manydown OSCOM (until March Manydown Overview and Scrutiny Committee 2014) MAP Members’ Advisory Panel MEC Manydown Executive Committee MOC (since April 2014) Manydown Overview Committee MUSCo Multi-Utility Service Company NPPG National Planning Policy Guidance NPPF National Planning Policy Framework NP Neighbourhood Plan OJEU Official Journal of the European Union PRS Private Rental Sector (housing tenures) PPA Planning Performance Agreement SPV Special Purpose Vehicle
Page 2 of 12 MAIN CONSIDERATIONS
3 The Proposal
Background
3.1The Manydown project continues to progress its work on schedule to prepare an outline planning application and identify a delivery strategy in order to actively promote the development. A public consultation has recently taken place on the proposed masterplan for the development alongside a statutory pre-application consultation with the Local Planning Authority (LPA). The intention is to proceed with submission of an outline planning application at the end of 2016.
3.2Update on Progress
Local Plan update
3.2.1 At the last MEC meeting held on 28 June 2016, it was reported that the Basingstoke and Deane Local Plan 2011 to 2029 was formally adopted by members at the Full Council meeting held on 26 May 2016. The new plan forms the development plan for the borough, and this supersedes the Adopted Local Plan 1996 – 2011, adopted in 2006.
3.2.2 The Adopted Local Plan was subject to a six week legal challenge period where applications could be made to the High Court on the grounds that the plans are not within the appropriate powers and/or a procedural requirement has not been complied with. The six week period of legal challenge ended on 7 July 2016. It is understood that no legal challenges were received.
Draft Manydown Development Brief
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Manydown Executive Committee at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
Manydown Programme Update Report· The progress being made on the Manydown Programme be noted. · The comments of the Manydown Overview Committee at Ap...
Manydown Programme Update Report1) Note the progress made on the Manydown Programme. 2) Note the comments of the Manydown Overview Committee 3) Appro...
Manydown North Project Update Report1) Note the progress made on the Manydown project. 2) Note the comments of the Manydown Overview Committee. 3) Note t...
Southern Manydown Project Update Report1) Note the progress made on the southern Manydown project. 2) Note the comments of the Manydown Overview Committee. ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.