Item7/17

Resolved

That Cabinet: Approves extending the longstop date for completion of the demolition works at the Fanum House site from the original timescale of a total of 14 months (as detailed in the original Heads of Terms as detailed in the Confidential Appendix 1 to the report) to 18 months with delegated authority to the Executive Director for Finance and Resources and the Head of Law and Governance in consultation with the Portfolio Holder for Property and Development to conclude the transaction on this basis. Delegates authority to the Executive Director for Finance and Resources and the Head of Law and Governance in consultation with the Portfolio Holder for Property and Development to vary the heads of term provided the overall transaction remains favourable to the council.
Word for word from the decision Basingstoke and Deane published for this meeting. Source: democracy.basingstoke.gov.uk

Follow this further

Built from Basingstoke and Deane's papers

What the report saysPro

Report to Cabinet

Executive summary

2.1In April 2017 Cabinet approved terms to enable the AA to surrender the remaining term of its lease on Fanum House. The AA is required to take occupation of The Florence Building being developed by Abstract Securities on Plot O, complete demolition of the structures on its site, return to the council a cleared development site, subject to certain conditions, before an agreed defined longstop date and then the lease surrender will be completed.

2.2At the time of the Cabinet decision the demolition works were anticipated to take 40 weeks. Further investigation by the AA and its demolition contractor have resulted in this timescale increasing to 50 weeks. The AA is therefore seeking an extension of time for the longstop date.

3 The Proposal

3.1To agree to the requested extension of time.

4 Key issues for consideration

4.1The Council’s Economic Master Plan for Basingstoke 2033 includes ambitions to fully regenerate Basing View to provide a business location of regional importance. The aim is to deliver new jobs and increased GVA in a thriving business park by targeting inward investment and the provision of new commercial development of grade A offices.

4.2The Council Plan 2016-2020 includes an objective to ‘Create jobs and opportunities by supporting new and existing business’ and highlights work to proactively revitalise Basing View and attract new companies, together with existing occupiers, to invest in the business area resulting in increased take up of new office accommodation.

4.3In terms of the regeneration of Basing View, letting The Florence Building during construction represents a significant catalyst which would engender confidence and momentum with the potential to encourage existing businesses within Basing View to remain and grow, and importantly encourage new businesses to locate to the area.

2 of 5 4.4 Abstract Securities secured Plot O to bring forward speculative development and have achieved a letting of the whole building ahead of schedule.

4.5Once cleared the Fanum House site provides a significant site for redevelopment which can be brought forward as part of the ongoing redevelopment and regeneration of Basing View.

5 Options Analysis

5.1There are two options for cabinet to consider; to progress with the variation or do nothing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Fanum House, Basing ViewReport 226 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 4 attended
SB
Councillor Simon BoundCommittee Member, present
HE
Councillor Hayley EachusCommittee Member, present
HG
Councillor Hannah GoldingCommittee Member, present
JI
Councillor John IzettCommittee Member, present

On this subject at Basingstoke and Deane

Search all
  1. Fanum House, Basing ViewThis decision
  2. Fanum House Redevelopment StrategyApproved
  3. Fanum HouseAgreed
  4. Fanum House, Basing ViewApproved

More from Basingstoke and Deane Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Motion referred from Council - Protecting South Ham And Buckskin Residents From Compulsory Purchase And Ensuring Full Democratic AccountabilityThat Cabinet note the motion referred by Council and agree to progress the actions within the motion in accordance wi... Noted Open
8 Sep 2026 Motion referred from Council - Increasing Biodiversity Net Gain Through the Local PlanThat Cabinet support the direction of travel set out in the motion and continue work through the Local Plan process t... Decided Open
8 Sep 2026 Recommendations from the Environment and Infrastructure Committee – Climate Emergency StrategyThat Cabinet endorse the recommendations of the Environment and Infrastructure Committee and incorporate them into th... Decided Open
8 Sep 2026 Local Plan - Next Steps1) Agree that work on a new local plan should proceed under the new planning system as set out in the Planning and Co... Agreed Open
8 Sep 2026 Regeneration Lettings Plans – Amendment to Housing Allocations Scheme1) Approve the Regeneration Priority Assessment Framework as at Appendix 2 of the report. 2) Authorise the Head of Le... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies