Fanum House Redevelopment Strategy

Approved Executive 2 papers

AI summaryCabinet approves demolishing Fanum House on Basing View to clear a prime site for redevelopment through a new Investment Partnership, with final costs and procurement delegated to officers.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFull demolition including the multi-storey car park
MoneyNo figures stated in the report
What happens nextPrior approval notice and procurementFunding to be reported to Council in July 2026
Who it affectsBasing View site and surroundingsResidents, businesses, visitors and partners including Vodafone and Homes England

What was decided

Cabinet approved a strategy to demolish Fanum House, a vacant building on the western end of Basing View, to support its redevelopment as a prime site through the council's proposed Investment Partnership. Report 12.1, 17.1

Authority was delegated to the Director of Regeneration, working with the Chief Finance Officer, to submit a prior approval notice for demolition and to agree the scope of works, final costs and procurement of a contractor. Report 12.3

Cabinet recommended that Council note that funding requirements for the project will be included in the MFTS Update and Capital Programme Outturn, to be reported to Council in July 2026. Report 17.4

Why

The building has been vacant and is deteriorating, creating ongoing holding costs, security liabilities and risks of unauthorised access and anti-social behaviour. Report 13.2, 17.1

Clearing the site creates a development-ready asset, which the council says will de-risk future schemes and strengthen its position in securing an Investment Partner. Report 17.3

The recommendation is Option 4: full demolition including the multi-storey car park, judged to offer the best balance of cost, risk and strategic benefit. Report 17.1, 17.5

What happens next

Appoint a consultant team and commission key surveys, including a Refurbishment and Demolition survey, ecological surveys and intrusive investigations where needed. Report 10.5, 10.8, 17.4

Submit a prior approval notice for demolition to the planning authority and serve a demolition notice, with pre-application advice covering the Site of Importance for Nature Conservation. Report 12.3, 15.3

Run a communication and engagement plan, including targeted engagement with Vodafone, Network Rail, Homes England and neighbouring businesses. Report 14.1

Options considered

  • Chosen: Option 4: full demolition of Fanum House including the multi-storey car park. Removes holding costs and maintenance liability at the earliest opportunity, transfers site risks to the contractor, and creates a development-ready asset for the Investment Partnership. Report 17.1, 17.3, 17.5

Implications

  • Risk: Overall risk profile rated HIGH due to uncertainties in demolition and site remediation; mitigation includes site surveys, early market engagement, contingency allowance and ongoing risk review. Report 10.1, 10.2, 10.9
  • Financial: Pre-tender budget may not cover all demolition, clearance and remediation costs; a contingency allowance is being considered and detailed cost estimates will inform a revised budget. Report 10.2
  • Legal: Demolition requires prior approval under Schedule 2 Part 11 Class B of the Town and Country Planning (General Permitted Development) (England) Order 2015, plus a demolition notice. Report 12.3
  • Climate: Materials from demolition will be recycled where possible; concrete will be crushed for reuse and asbestos removed to licensed facilities; any future development will be designed to current sustainability standards. Report 15.1
  • Equalities: Initial assessment indicates no negative differential impact on groups with protected characteristics; a full Equality Impact Assessment will be completed at future redevelopment stages if needed. Report 13.1, 13.4
  • Other: Building is occasionally used as a roost by peregrine falcons, a Schedule 1 species, and demolition works may need a specific licence or permit, particularly during the March to May nesting season. Report 15.4
  • Other: Site includes Fanum House Lawn Site of Importance for Nature Conservation, supporting 0.6ha of herb-rich chalk grassland; any future redevelopment will need to achieve 10% biodiversity net gain unless exempt. Report 15.3
  • Staffing: Officers confirm there are no HR implications from this report. Report 16.1

Who and where

  • Residents, workers and visitors to Basing View Report 13.2, 14.1
  • Vodafone, Network Rail, Homes England and neighbouring businesses
  • The AA, in relation to existing parking obligations Report 17.2
  • Protected species including peregrine falcons and potentially bats and nesting birds Report 15.4, 15.5
  • Future Investment Partner and developer for the cleared site Report 17.3

Timeline

  • 9 June 2026: Cabinet takes the decision Report P48
  • March to May inclusive: Peregrine falcon nesting season, when any works that may disturb an active nest need a licence or permit Report 15.4
  • July 2026: Funding requirements for the project to be reported to Council within the MFTS Update and Capital Programme Outturn Report 17.4

Plain English for the jargon

  • MSCP: Multi-storey car park
  • SINC: Site of Importance for Nature Conservation
  • CIL: Community Infrastructure Levy, a charge developers can pay or offset against existing floorspace
  • Prior approval: Permission needed under permitted development rights before demolition can proceed
  • MFTS: Medium Term Financial Strategy, the council's rolling financial planning document
  • Investment Partnership: The council's proposed arrangement with a partner to redevelop the cleared site
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11/26

Resolved

That Cabinet: 1) Approve the proposed strategy to demolish Fanum House to support redevelopment of this prime site on Basing View. 2) Delegate authority to the Director of Regeneration in consultation with the Chief Finance Officer (Section 151 officer) to submit a prior approval notice for demolition, approve the scope of works, final costs and procurement of a contractor for the demolition of Fanum House. 3) Recommends to Council to note that the funding requirements for this new project will be included in the MFTS Update and Capital Programme Outturn and updated to Council in July 2026.
Word for word from the decision Basingstoke and Deane published for this meeting. Source: democracy.basingstoke.gov.uk

Follow this further

Built from Basingstoke and Deane's papers

What the report saysPro

Report to Cabinet

Cabinet Date: 9 June 2026 Subject: Fanum House Redevelopment Strategy Report of: Cllr Gavin James, Cabinet Member for Finance and Property

Lead Officer: Sarah Longthorpe, Director of Regeneration Contact Officer: Martin Jones, Head of Property and Assets

Ward(s): Eastrop and Grove Key Decision: Yes Appendix 1: Fanum House Site Plan Appendix 2: Financial Implications (CONFIDENTIAL)

Exempt or Confidential Information It is considered that information contained within Appendix 2 contains exempt information under the meaning of paragraph 3 of Schedule 12A of the Local Government Act 1972, as amended, and therefore cannot be made public.

Foreword - Cllr Gavin James, Cabinet Member for Finance and Property

Fanum House has been a familiar feature of Basingstoke’s skyline since it was built in the early seventies and an important part of Basing View’s history. For many residents and businesses, it represents a significant chapter in the borough’s commercial growth and identity. With this in mind, the decision on its future has not been taken lightly and we are very mindful of its legacy and the memories it holds for many.

As this report outlines, the building is now in a condition that makes its continued use neither practical nor financially responsible. Having remained vacant since early 2026 and requiring substantial investment to address structural issues and asbestos, the cost of retention or refurbishment would not represent good use of public money. After careful consideration of all viable options, it is clear that doing nothing is simply not sustainable.

1 of 17 The proposal to demolish Fanum House is not just about removing an ageing structure, it is also about unlocking the potential of a strategically important site in the heart of Basingstoke. This presents an opportunity to bring forward a new vision that of 17 supports economic growth, attracts investment, and meets the evolving needs of our borough for residents and businesses.

Through the council’s emerging investment partnership, we are aiming to accelerate regeneration across Basing View and the town centre. Fanum House is expected to play a key role in this, with the potential to deliver a high-quality, mixed-use development that could include modern office space, educational facilities, and new homes, subject to planning consent.

This report sets out the rationale for the proposed course of action and the opportunity it presents. If approved by Cabinet, further work would be undertaken to progress the surveys and a tender for demolition of the building, engagement with partners and local businesses and consideration of how the history of the site can be recognised as part of future plans.

Recommendation to Cabinet

To approve the proposed strategy to demolish Fanum House to support redevelopment of this prime site on Basing View.

To delegate authority to the Director of Regeneration in consultation with the Chief Finance Officer (Section 151 officer) to submit a prior approval notice for demolition, approve the scope of works, final costs and procurement of a contractor for the demolition of Fanum House.

Cabinet recommends to Council

To note that the funding requirements for this new project will be included in the MFTS Update and Capital Programme Outturn and updated to Council in July 2026.

Background, corporate objectives and priorities

The Council Plan 2023 to 2027 sets out the objectives and priorities for Basingstoke and Deane Borough Council. This includes achieving “a place where people can have pride in their communities and the borough”.

We want our borough to have a thriving economy, be a place that has jobs, skills, opportunities, infrastructure, and services that our communities need.

Key actions from the Council Plan include exploring opportunities to further improve Basing View.

2 of 17 Glossary of terms Term Definition

MSCP Multi-Storey Car Park

The AA The Automobile Association

M&E Mechanical and Electrical

MoD Ministry of Defence

MSCP Multi-storey car park

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Fanum House Site Plan /26Appendix 1 298 KB Download
PDF
Fanum House Redevelopment StrategyReport 200 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
PH
Councillor Paul HarveyChair, present
OC
Councillor Onnalee CubittCommittee Member, present
GJ
Councillor Gavin JamesCommittee Member, present
LJ
Councillor Laura JamesCommittee Member, present
AK
Councillor Andy KonieczkoCommittee Member, present
JM
Councillor John McKayCommittee Member, present
KM
Councillor Kerry MorrowCommittee Member, present
CT
Councillor Chris TomblinCommittee Member, present

On this subject at Basingstoke and Deane

Search all
  1. Fanum House Redevelopment StrategyThis decision
  2. Fanum HouseAgreed
  3. Fanum House, Basing ViewApproved
  4. Fanum House, Basing ViewApproved

More from Basingstoke and Deane Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Motion referred from Council - Protecting South Ham And Buckskin Residents From Compulsory Purchase And Ensuring Full Democratic AccountabilityThat Cabinet note the motion referred by Council and agree to progress the actions within the motion in accordance wi... Noted Open
8 Sep 2026 Motion referred from Council - Increasing Biodiversity Net Gain Through the Local PlanThat Cabinet support the direction of travel set out in the motion and continue work through the Local Plan process t... Decided Open
8 Sep 2026 Recommendations from the Environment and Infrastructure Committee – Climate Emergency StrategyThat Cabinet endorse the recommendations of the Environment and Infrastructure Committee and incorporate them into th... Decided Open
8 Sep 2026 Local Plan - Next Steps1) Agree that work on a new local plan should proceed under the new planning system as set out in the Planning and Co... Agreed Open
8 Sep 2026 Regeneration Lettings Plans – Amendment to Housing Allocations Scheme1) Approve the Regeneration Priority Assessment Framework as at Appendix 2 of the report. 2) Authorise the Head of Le... Approved Open