Resolved
The committee notes the content of the report.
Audit and Accounts Committee decided this item on Monday 26 June 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
The committee notes the content of the report.
Internal Audit Progress Report (January-May 2017)
Report to Audit and Accounts Committee – 26th June 2017 Ward(s): All Key Decision: No Appendix 1: Summary of overdue recommendations Housing Benefit-Recovery of Invoiced Overpayments Summary Appendix 2: Report Appendix 3: Income Collection Processes Summary Report Appendix 4: Insurance Processes Summary Report Appendix 5: Risk Management Summary Report Appendix 6: Grants to Voluntary Organisations Summary Report Appendix 7: Asset Register (Movable Assets) Summary Report Appendix 8: Property Maintenance Summary Report Appendix 9: Car Park Income Processes Summary Report Appendix 10: Basing View Governance Arrangements Summary Report Appendix 11: Revenue Contracts-M&E & Cleaning Services Summary Report Appendix 12: Accountancy and Budgetary Control Summary Report Appendix 13: Manydown Project Governance Arrangements Summary Report Appendix 14: Corporate Governance Summary Report Appendix 15: Contract Processes Summary Audit Report Appendix 16: Summary of outstanding (not overdue recommendations)
Papers relied on: None
1 Foreword
This report is to inform members of the Audit and Accounts Committee of the work completed by the Internal Audit Team during the period January – May 2017 and the current position with outstanding audit recommendations.
Recommendation to the committee:
That the contents of the report are noted 2 Background, corporate objectives and priorities
2.1Internal Audit provides an assurance and consulting service in respect of the council’s control environment designed to add value and improve the council’s operations and help the council to accomplish its objectives.
(Taken from the Finance and Resources Directorate’s Service Plan 2016-2020)
2.2The annual audit plan for 2016/17 was approved by the Audit & Accounts Committee on 11th April 2016. During the year there were no changes to the plan.
3 Glossary of Terms
3.1Audit Levels of Assurance Each audit report provides an opinion as to the adequacy of the control environment for the processes reviewed. The levels of assurance that can be given are:
Full Assurance – There is a comprehensive system of internal controls in place designed to achieve the system/function/process objectives. These controls are operating effectively and are being consistently applied.
Substantial Assurance - Key controls designed to achieve the system/function/process objectives are in place. There are opportunities to enhance/strengthen those controls.
(Reasonable) Moderate Assurance – Basic controls designed to achieve the system/function/process objectives are in place. Improvements are required if key controls are to be established.
Limited Assurance – Minimal controls designed to achieve the system/function/process objectives are in place. Significant improvements are required if key controls are to be established.
No Assurance – No controls that achieve the system/function/ process objectives are in place.
3.2Audit Categories of Recommendations
As a reminder to members of the committee, audit recommendations are categorised according to their level of perceived risk, as follows:
Fundamental (Red) - A control weakness that could: Have a major impact in the achievement of the objectives of the system, function or process under review, Have a major financial impact on the Council, Breach the law or regulations resulting in fines & consequences which have a major impact on the system function or process under review, or the Council as a whole, Have a major impact on the reputation of the Council.
Significant (Amber) - A control weakness that could: Have a moderate impact in the achievement of the objectives of the system, function or process under review, Have a moderate financial impact on the Council, Breach the law or regulations resulting in fines & consequences which have a moderate impact on the system function or process under review, or the Council as a whole, Have a moderate impact on the reputation of the Council.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Summary of Overdue Recommendations /17Appendix 1 | 113 KB | Download |
PDF |
HB Recovery of Overpayments Summary Report /17Appendix 2 | 125 KB | Download |
PDF |
Income Collection Summary Report /17Appendix 3 | 158 KB | Download |
PDF |
Insurance Summary Report /17Appendix 4 | 131 KB | Download |
PDF |
Risk Management Summary Report /17Appendix 5 | 132 KB | Download |
PDF |
Internal Audit Progress Report (January: May 2017)Report | 377 KB | DownloadRead as text |
Follow Audit and Accounts Committee at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Jul 2026 | EY Audit Planning Report 2025/26The Committee note the EY Planning report. | Noted | Open |
| 1 Jul 2026 | Internal Audit Progress Report (April - June 2026)The Committee considers the Internal Audit Progress Report (April-June 2026) and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Internal Audit Annual Report 2025/26The Committee considers the Internal Audit Annual Report 2025/26 and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Fraud Update – Protecting The Public PurseThe Committee considers the Fraud Update- Protecting the Public Purse and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Local Code of Corporate Governance 2026/2027The Committee approve the . | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.