BDBC Internal Audit Report on the Audit of Business Continuity Arrangements
Audit work undertaken: January 2022 Report issued: March 2022
1. Audit Opinion Internal Audit is able to offer Reasonable Assurance (3) that there are adequate controls in place to ensure the integrity and operation of systems concerning council Business Continuity Arrangements.
(1) Full Assurance There is a comprehensive system of internal controls in place designed to achieve the system/function/process objectives. These controls are operating effectively and are being consistently applied.
(2) Substantial Assurance Key controls designed to achieve the system/function/process objectives are in place. There are opportunities to enhance/strengthen those controls.
(3) Reasonable Assurance Basic controls designed to achieve the system/function/process objectives are in place. Improvements are required if key controls are to be established.
(4) Limited Assurance Minimal controls designed to achieve the system/function/process objectives are in place. Significant improvements are required if key controls are to be established.
2. Audit Opinion History
Year 2019/20 2020/21 2021/22 Level of Assurance Reasonable n/a Reasonable Appendix 2
3. Key Findings.
Control Objective 1: The council has up-to-date business continuity policies and procedures that are compliant with the latest ISO standard. Appropriate resource and expertise is assigned to the role of business continuity.
An initial Business Continuity Board Meeting was held in January 2022 but a considerable amount of work still needs to be undertaken if new governance arrangements are to be designed, implemented and enforced. Recommendations from the previous audit therefore remain to which an update was provided by the Head of HR, Policy & Communications for this year’s audit. Revised completion dates for these recommendations have been agreed as part of this audit.
Control Objective 2: Business continuity plans exist for all areas of the council according to appropriate risk assessment. These plans are up-to-date, regularly reviewed and tested.
Several Service Recovery Plans have been updated since the last audit was undertaken in 2019 but the majority remain unchanged. As highlighted in audit reports during this time, Services have been operating during the pandemic in a business continuity scenario to enable key customer services to be provided. Service Recovery Plans do need to be updated to account for both new best practice and council requirements as well as council reorganisation that has gone on since the last audit review making current plans obsolete.
4. Management Response
Head of HR, Policy & Communications (February 2022) I would like to thank my colleagues in the audit team for undertaking this audit. Business Continuity remains a high priority within the authority and the COVID-19 pandemic coupled with the move to Smarter Ways of Working provides us with the opportunity to review our existing processes and practices as well as the templates provided for services to enable them to complete their Business Continuity plans, reviews and process testing. Underpinning this the overarching plans which provide the framework within which the council’s Business Continuity activity takes place are also being reviewed to ensure that we incorporate both the lessons learnt in the past 18 months as well as reflecting our new ways of working.
5. Summary of Recommendations
No new recommendations arising due to relevant issues being covered by existing audit recommendations although revised completion dates have been agreed. Appendix 2
6. Timetable
Scope of audit Fieldwork Fieldwork Draft report issued: Management Final Report agreed: commenced: completed: responses received: Issued: 21st Dec 2021 5th Jan 2022 20th Feb 2022 21st Feb 2022 7th Mar 2022 14th Mar 2022
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
App2 /22Report | 137 KB | DownloadRead as text |
PDF |
App3 /22Report | 133 KB | Download |
PDF |
App4 /22Report | 144 KB | Download |
PDF |
App5 /22Report | 254 KB | Download |
PDF |
/22Appendix 1 | 353 KB | Download |
PDF |
Internal Audit Progress Report (March-May 2022)Report | 381 KB | Download |
Follow Audit and Accounts Committee at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Jul 2026 | EY Audit Planning Report 2025/26The Committee note the EY Planning report. | Noted | Open |
| 1 Jul 2026 | Internal Audit Progress Report (April - June 2026)The Committee considers the Internal Audit Progress Report (April-June 2026) and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Internal Audit Annual Report 2025/26The Committee considers the Internal Audit Annual Report 2025/26 and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Fraud Update – Protecting The Public PurseThe Committee considers the Fraud Update- Protecting the Public Purse and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Local Code of Corporate Governance 2026/2027The Committee approve the . | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.