Resolved
The Committee notes the report.
Audit and Accounts Committee decided this item on Monday 6 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee notes the report.
Internal Audit Progress Report (November 22-February 23)
Report to Audit and Accounts Committee – 6th March 2023 Ward(s): All Key Decision: No
Appendix 1 Audit Recommendations – Current Position as at 28/02/23 Appendix 2 Creditors Summary Report Appendix 3 Health & Safety Summary Report Appendix 4 Parking Services Summary Report Appendix 5 Information Governance Summary Report Appendix 6 Local Tax Administration & Billing Summary Report Appendix 7 Local Tax Recover & Enforcement Summary Report Appendix 8 Bank Reconciliation Summary Report
1 Foreword
This report is to inform members of the Audit and Accounts Committee of the work completed by the Internal Audit Team during the period November 2022 to February 2023 and the current position with all audit recommendations.
Recommendation to the committee:
That the contents of the report are noted
2 Background, corporate objectives and priorities
2.1Internal Audit’s primary objective is to “Provide an efficient, risk based independent, objective assurance and consulting service designed to add value and improve the council’s operations whilst ensuring effective risk management, control and governance processes are in place”.
(Taken from the Corporate Services Directorate Service Plan 2020-24)
2.2The annual audit plan for 2022/23 was approved by the Audit and Accounts Committee on 22nd March 2022 and will assist the Chief Internal Auditor in providing an annual opinion on the effectiveness of the council’s risk management, control and governance processes.
3 Glossary of Terms
3.1Audit Levels of Assurance Each audit report provides an opinion as to the adequacy of the control environment for the processes reviewed. The levels of assurance that can be given are:
Full Assurance – There is a comprehensive system of internal controls in place designed to achieve the system/function/process objectives. These controls are operating effectively and are being consistently applied.
Substantial Assurance - Key controls designed to achieve the system/function/process objectives are in place. There are opportunities to enhance/strengthen those controls.
Reasonable (Moderate) Assurance – Basic controls designed to achieve the system/function/process objectives are in place. Improvements are required if key controls are to be established.
Limited Assurance – Minimal controls designed to achieve the system/function/process objectives are in place. Significant improvements are required if key controls are to be established.
No Assurance – No controls that achieve the system/function/ process objectives are in place.
3.2Audit Categories of Recommendations
Audit recommendations are categorised according to their level of perceived risk, as follows:
Fundamental (Red) - A control weakness that could: Have a major impact in the achievement of the objectives of the system, function or process under review, Have a major financial impact on the Council, Breach the law or regulations resulting in fines & consequences which have a major impact on the system function or process under review, or the Council as a whole, Have a major impact on the reputation of the Council.
Significant (Amber) - A control weakness that could: Have a moderate impact in the achievement of the objectives of the system, function or process under review, Have a moderate financial impact on the Council, Breach the law or regulations resulting in fines & consequences which have a moderate impact on the system function or process under review, or the Council as a whole, Have a moderate impact on the reputation of the Council.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
/22Appendix 1 | 431 KB | Download |
PDF |
/22Appendix 2 | 149 KB | Download |
PDF |
/22Appendix 3 | 148 KB | Download |
PDF |
/22Appendix 4 | 165 KB | Download |
PDF |
/22Appendix 5 | 278 KB | Download |
PDF |
Internal Audit Progress Report (November 22: February 23)Report | 377 KB | DownloadRead as text |
Follow Audit and Accounts Committee at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Jul 2026 | EY Audit Planning Report 2025/26The Committee note the EY Planning report. | Noted | Open |
| 1 Jul 2026 | Internal Audit Progress Report (April - June 2026)The Committee considers the Internal Audit Progress Report (April-June 2026) and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Internal Audit Annual Report 2025/26The Committee considers the Internal Audit Annual Report 2025/26 and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Fraud Update – Protecting The Public PurseThe Committee considers the Fraud Update- Protecting the Public Purse and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Local Code of Corporate Governance 2026/2027The Committee approve the . | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.