Town Centre and Basing View Delivery Strategy

Noted Executive 4 papers

AI summaryBasingstoke and Deane Cabinet agreed to set up an Investment Partnership model to deliver regeneration of the town centre and Basing View, with a partner selection exercise planned from April to August 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet agreed to commence a selection process for an Investment Partner
MoneyNo new spending confirmedLegal advice and advertising costs to be met from existing budgets
What happens nextPartner selection April to August 2026Partnership expected to commence September 2026
Who it affectsBasingstoke town centre and Basing View65 acre business district and town centre regeneration

What was decided

Cabinet noted progress to date and strong market interest from potential partners following a scoping exercise. Report 3.1, 3.5

Cabinet agreed to proceed with the recommended Investment Partnership model and to commence a selection process for an Investment Partner, subject to further legal and procurement advice. Report 5.2, 5.22, 6.3

Cabinet noted the next steps required to inform a proposal pack, selection process and indicative timelines. Report 15.7, 15.8

Why

The Investment Partnership is considered a low risk, flexible model that lets the Council keep strategic influence, share in value uplift and use an experienced partner's capacity, without the procurement burden of a traditional joint venture. Report 5.17, 15.3

The IP model is treated as a commercial entity, not a contracting authority, so it falls outside the Procurement Act 2023, though partners were reluctant to engage in full public procurement processes. Report 15.4

Other options were ruled out: doing nothing, in-house delivery, land disposal, joint venture and a wholly owned company, all due to lack of resources, limited control, high cost or lengthy procurement. Report 5.4, 5.6, 5.9, 5.11, 5.23

What happens next

Obtain further legal and procurement advice to refine the IP model from January 2026 and appoint a consultant advisor to design the selection process. Report 15.8, P134, P135

Prepare a marketing pack between January 2026 and April 2026, working with the Portfolio Holder to set strategic priorities. Report P136, P129

Run the selection exercise from April 2026 to August 2026, seek Cabinet approval for the chosen partner in August 2026 and commence the partnership in September 2026. Report P137, P138, P139

The money

  • over £44M Recent investment in refurbishments at Grosvenor House and Plant, Basing View, providing 206,000 sq ft of Grade A office space Report 2.3
  • over £100M Gross development value of Packaged Living's View Point scheme for 326 new homes, subject to Section 106 agreement Report 2.3
  • circa £5.5m inclusive of VAT Procurement Act 2023 works contract threshold for the current year Report P47

Options considered

  • Rejected: Do nothing. Would result in no further action to progress development and regeneration Report 5.4
  • Rejected: In-house delivery and management. Lack of resources, external funding and extensive procurement requirements make it unviable Report 5.5, 5.6
  • Rejected: Land deal or disposal. Does not allow the Council to shape development or generate ongoing income streams Report 5.7, 5.8, 5.9
  • Rejected: Joint Venture (contractual). Comprehensive procurement requirement likely to take around 18 months Report 5.11
  • Chosen: Investment Partnership model. Flexible, low risk structure; treated as commercial entity outside Procurement Act 2023; enables Council to retain influence and share in value uplift Report 5.12, 5.13, 5.17, 5.22
  • Rejected: Wholly Owned Company. High risk profile, substantial set up costs and reliance on securing external funding Report 5.23

Implications

  • Legal: Council has powers under the Local Government Act 2003 and Localism Act 2011 to enter an IP and trade for a commercial purpose; further specialist legal advice to confirm powers for the final structure. Report 6.1, 6.3
  • Financial: At this stage there are minimal financial considerations; costs of independent legal advice and advertising the opportunity to be met from existing budgets; future site development will need separate appraisal. Report 7.1, 7.2
  • Equalities: An Equalities Impact Assessment will be completed as part of the partner selection process. Report 11.1
  • Climate: The IP approach should have a positive carbon impact compared with a land disposal as it lets the Council set sustainability standards; developments will need Biodiversity Net Gain and protected species mitigation. Report 13.1, 13.3, 13.4
  • Risk: Independent legal advice on the structure will further inform risks; any final option risks will be managed under the Corporate Risk Management Approach. Report 8.1, 8.2
  • Other: There are no HR implications; communications plan to be produced to share decisions with residents, businesses and partners. Report 14.1, 12.1

Who and where

  • Residents of Basingstoke town centre and Basing View Report 15.1, 2.6
  • Businesses and investors in the borough Report 2.6, 12.1
  • Developers and operators approached during the scoping exercise Report 3.1, 3.3
  • Council as freeholder of Basing View and town centre sites Report 2.1, 2.8

Timeline

  • December 2025: Cabinet approval to proceed with the recommended Investment Partnership model Report P133
  • January 2026: Seek further legal and procurement advice to refine the IP model Report P134
  • January 2026: Appoint consultant to advise on detailed selection process and preparation of marketing pack Report P135
  • January 2026 to April 2026: Prepare marketing pack for the selection exercise Report P136
  • April 2026 to August 2026: Selection exercise for Investment Partner Report P137
  • August 2026: Seek Cabinet approval for chosen partner Report P138
  • September 2026: Commence partnership Report P139

Plain English for the jargon

  • Investment Partnership (IP): A finance based joint venture, typically structured as a Limited Liability Partnership, where the Council contributes land value via a loan note and the partner covers planning and operational costs, with 50/50 control.
  • LLP (Limited Liability Partnership): A legal structure combining features of a partnership and a limited company, used here so the IP is treated as a commercial sector entity and not a contracting authority.
  • Procurement Act 2023 (PA23): UK legislation in force from 24 February 2025 setting out the procedures local authorities must follow when procuring goods, works or services; the IP model is structured to fall outside its scope.
  • BREEAM Outstanding: The highest rating under the Building Research Establishment Environmental Assessment Method, a standard for sustainable building design.
  • Build to Rent (BTR): Purpose built housing designed specifically for the rental market, usually built and managed by a single landlord or operator.
  • GDV (Gross Development Value): The total market value of a proposed development once completed.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item61

Resolved

Cabinet: 1) Note the progress to date and positive market interest from potential partners following the scoping exercise to identify an appropriate delivery strategy to drive regeneration across the Town Centre and Basing View. 2) Agree to proceed with the recommended Investment Partnership model and commence a selection process for an Investment Partner subject to further legal and procurement advice. 3) Note the next steps required to inform a proposal pack, selection process and indicative timelines.
Word for word from the decision Basingstoke and Deane published for this meeting. Source: democracy.basingstoke.gov.uk

Follow this further

Built from Basingstoke and Deane's papers

What the report saysPro

Report to Cabinet

Cabinet Date: 9 December 2025 Subject: Town Centre and Basing View Delivery Strategy Cllr Onnalee Cubitt, Cabinet Member for Major Projects and Report of: Regeneration Lead Officer: Sarah Longthorpe, Director of Regeneration

Contact Officer(s): Martin Jones, Head of Property and Assets Sarah Good, Head of Major Projects and Regeneration Ward(s): Brookvale & Kings Furlong, Eastrop & Grove Key Decision: N/A

Confidential - List of parties engaged in project scoping Appendix 1 exercise Appendix 2 Delivery Options Analysis Appendix 3 Investment Partnership Key Points / Legal Summary Key comparisons between a traditional JV and an Appendix 4 Investment Partnership approach

Exempt or Confidential Information It is considered that information contained within the Appendix 1 contains exempt information under the meaning of paragraph 3 of Schedule 12A of the Local Government Act 1972, as amended, and therefore cannot be made public.

Foreword – Cllr Onnalee Cubitt, Cabinet Member for Major Projects and Regeneration Since June 2023, the Cabinet has been actively reviewing together with officers the previously approved 2022 Town Centre Masterplan by Allies and Morrison, which set out a macro vision for regenerating Basingstoke’s Town Centre and Basing View Business District; over the past 18 months, officers have successfully engaged major FTSE companies and investors, generating enthusiastic market interest in partnering to implement and improve the plan, with a strong focus on creating vibrant mixed-use spaces featuring new homes, leisure, culture, Grade A offices, and higher education to drive economic growth, a skilled workforce, and enhanced infrastructure. A range of delivery models were carefully evaluated, including doing nothing, in-house delivery, land disposal, joint venture (JV), wholly owned company, and the recommended Investment Partnership (IP) model; the IP approach, structured as a commercial Limited Liability Partnership (LLP) with a private sector investor, delivers

1 of 16 exciting flexibility, shared risks and rewards, no exclusivity on sites, agile delivery through multiple developers, while enabling the Council to maintain control and enjoy substantial value uplift. We are confident that the IP model represents the optimal structure to fast-track regeneration, bypassing the lengthy timelines of a traditional JV, and empowering holistic placemaking, access to external expertise and funding, and alignment with Council priorities. This model excitingly bridges from vision to delivery. We want enduring prosperity for residents and businesses alike. It is fantastic that we have sparked such significant market interest. We seek approval to advance with the IP model and launch a transparent selection process for a partner (subject to further legal and procurement advice). Once this Paper is approved, officers will prepare the proposal pack, with an indicative timeline targeting partnership commencement by September 2026. External consultant support will be invaluable to ensure alignment with this Cabinet’s strategic objectives and delivery of our Council Plan priorities. Beauty and Design must be a core objective at the heart of this Partnership Project. We want Basingstoke to have a massive Wow factor. We are located in the midst of a Borough with great wealth and fantastic access to trains and airplanes. Our future depends on that same wealth being attracted to spend money in our Town Centre and our Business District. This Cabinet and officers have high aspirations for Basingstoke, its residents, and its business sector. Basingstoke is perfectly located to "reach for the stars".

Recommendation to Cabinet:

1. Note the progress to date and positive market interest from potential partners following the scoping exercise to identify an appropriate delivery strategy to drive regeneration across the Town Centre and Basing View.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Options AnalysisAppendix 2 131 KB Download
PDF
Freeths Note: Investment Partnerships: Key PointsAppendix 3 73 KB Download
PDF
Key comparasionsAppendix 4 104 KB Download
PDF
Town Centre and Basing View Delivery StrategyReport 398 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 8 attended
PH
Councillor Paul HarveyChair, expected
OC
Councillor Onnalee CubittCommittee Member, expected
GJ
Councillor Gavin JamesCommittee Member, expected
LJ
Councillor Laura JamesCommittee Member, expected
AK
Councillor Andy KonieczkoCommittee Member, expected
JM
Councillor John McKayCommittee Member, expected
KM
Councillor Kerry MorrowCommittee Member, expected
CT
Councillor Chris TomblinCommittee Member, expected

On this subject at Basingstoke and Deane

Search all
  1. Town Centre and Basing View Delivery StrategyThis decision
  2. Proposal to renew an existing Public Space Protection Order to tackle antisocial behaviour in the Town Centre and some surrounding parks and open spacesAgreed
  3. Town Centre Strategy & Basing View UpdateDecided
  4. Report on the Town Centre StrategyApproved
  5. Update Report on the Town Centre StrategyDecided
  6. Town centre update - Consideration of work to date and future approachAgreed

More from Basingstoke and Deane Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Motion referred from Council - Protecting South Ham And Buckskin Residents From Compulsory Purchase And Ensuring Full Democratic AccountabilityThat Cabinet note the motion referred by Council and agree to progress the actions within the motion in accordance wi... Noted Open
8 Sep 2026 Motion referred from Council - Increasing Biodiversity Net Gain Through the Local PlanThat Cabinet support the direction of travel set out in the motion and continue work through the Local Plan process t... Decided Open
8 Sep 2026 Recommendations from the Environment and Infrastructure Committee – Climate Emergency StrategyThat Cabinet endorse the recommendations of the Environment and Infrastructure Committee and incorporate them into th... Decided Open
8 Sep 2026 Local Plan - Next Steps1) Agree that work on a new local plan should proceed under the new planning system as set out in the Planning and Co... Agreed Open
8 Sep 2026 Regeneration Lettings Plans – Amendment to Housing Allocations Scheme1) Approve the Regeneration Priority Assessment Framework as at Appendix 2 of the report. 2) Authorise the Head of Le... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies