Basingstoke and Deane Borough Council
Cabinet, Tuesday 9 December 2025 at 6.30pm

Quarter 2 Capital Monitoring Report as at 30 September 2025

Agreed Executive 1 paper

AI summaryCabinet noted the Q2 capital forecast of £19.131M for 2025/26, £3.387M below the £22.518M budget, with the four-year programme fully funded from council resources to 2028/29.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedForecast £19.131M, £3.387M below budget
Money£19.131M2025/26 forecast, £3.387M below £22.518M budget
What happens nextFully funded to 2028/29Capital programme funded from own resources
Who it affectsBorough-wide servicesAll wards; capital projects across services

What was decided

Cabinet noted the forecast capital expenditure for 2025/26 of £19.131M, which is £3.387M lower than the latest agreed capital programme budget of £22.518M. Report P6, 1.1, 3.3

Cabinet noted approved increases to the 2025/26 capital budget from S106 contributions, capital grants and scheme rephasing under the Chief Finance Officer's delegated powers, including £0.338M for Home Improvement Financial Assistance and £0.013M for a new bus shelter. Report P6, P11, 2.1, 2.2

Cabinet noted the significant forecast variations for 2025/26 and explanations for them, the latest forecast of capital receipts, grants and contributions, and the risks associated with the forecasts. Report P6, 1.1, 3.3

Why

The £3.387M variance is mainly due to delays in completing delivery of property related schemes of £1.589M and the 5G Living Lab scheme of £0.625M, and a rephasing of £0.624M for the Property Investment Strategy. Report 1.1, 3.3

Home Improvement Financial Assistance is forecast to be £0.603M overspent in 2025/26 because the anticipated reduction in referrals from Hampshire County Council has not materialised, with caseload remaining consistent with previous years. Report 2.1

The capital programme remains fully funded from the council's own resources based on the latest forecast of available resources up to 2028/29. Report P6, 3.1

What happens next

The council will continue to review the existing capital programme to ensure all expenditure is essential and is supported by robust business cases, with any identified savings built into future capital programme updates. Report 3.1

Budgets for delayed schemes are expected to be rephased into future years, including property schemes, the 5G Living Lab, the Property Investment Strategy, and various Resident Services schemes. Report 1.1, 3.3, P33, P34

The capital programme will continue to be monitored on a quarterly basis in line with the council's Capital Strategy, with updates reported to Cabinet and Council. Report P7

The money

  • £19.131M Forecast capital expenditure for 2025/26 Report P6, 1.1, 3.3, P17
  • £22.518M Latest agreed capital programme budget for 2025/26 Report P6, 1.1, 3.3, P17
  • £3.387M Variance below budget (15.04%) Report P6, 1.1, 3.3
  • £101.071M Total capital programme for 2025/26 to 2028/29 Report P28, P29, P34
  • £0.603M Forecast overspend on Home Improvement Financial Assistance in 2025/26 Report 2.1
  • £2.037M Latest forecast of capital receipts due in 2025/26 Report P25
  • £3.423M Forecast 2025/26 capital grants and contributions Report 4.3, P27
  • £0.616M Budget additions to 2025/26 capital programme under delegated powers since Q1 Report P11

Options considered

  • Rejected: Defer, cancel or refinance capital schemes to release funding. Programme remains fully funded and no changes proposed in this report Report 1.1, 3.1

Implications

  • Financial: The capital programme for 2025/26 to 2028/29 remains fully funded from the council's own resources based on the latest forecast of available resources. Report P6, 3.1
  • Risk: The Co-Leader and Cabinet Member for Finance and Property recognises ongoing challenges in build cost inflation and supply chain issues that could affect both budget control and delivery times. Report P5
  • Other: Some schemes are funded from S106 developers' contributions or Community Infrastructure Levy and must be used in accordance with the purposes set out in the agreement. Report 2.2, P7

Who and where

  • All wards in the borough Report P3
  • Residents receiving Home Improvement Financial Assistance due to higher than expected caseload Report 2.1
  • Service areas: Central Services and Climate Change; Customers, Digital and Improvement; Regeneration; Resident Services Report P17
  • Users of deferred Regeneration schemes including 5G Living Lab, Basing View Car Parks, Maidenwell Pavilion and Property Investment Strategy Report 1.1, 3.3, P33

Timeline

  • 30 September 2025: Q2 capital monitoring date Report P1, P7, P30
  • October 2025: Capital programme outturn last reported to Council; Q1 changes approved Report 1.1, P11
  • 9 December 2025: Cabinet decision on Q2 capital monitoring report Report P1, P30
  • 2026/27: Rephased schemes planned for delivery, including Basing View Car Parks, Maidenwell Pavilion, Housing and Homelessness IT System, and Low Cost Home Ownership Report P33, P34

Plain English for the jargon

  • AMP: Asset Management Programme
  • CIL: Community Infrastructure Levy
  • HCC: Hampshire County Council
  • LEP: Local Enterprise Partnership
  • LIF: Local Infrastructure Fund
  • MHCLG: Ministry of Housing, Communities and Local Government
  • RRCP: Revenue Reserve for Capital Purposes
  • S106: Section 106 Developers' Contributions
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item56

Resolved

Cabinet note: 1) The forecast capital expenditure for 2025/26 of £19.131M which is £3.387M lower that the latest agreed capital programme budget of £22.518M; 2) The approved increases to the 2025/26 capital budget from S106 contributions, capital grants and scheme rephasing under the Chief Finance Officer’s delegated powers as shown in section 2 of the report; 3) The 2025/26 significant forecast variations and explanations for them as shown in section 3 of the report; 4) The latest forecast of capital receipts, grants and contributions for 2025/26 in section 4 of the report; 5) The risks associated with the capital forecasts are as detailed in section 8 of the report; 6) The latest approved capital programme for 2025/26 to 2028/29 and the financing as shown in section 5 and detailed in Appendix 1 of the report; and 7) The capital programme remains fully funded from the council’s own resources up to 2028/29, based on the latest forecast of available resources.
Word for word from the decision Basingstoke and Deane published for this meeting. Source: democracy.basingstoke.gov.uk

Follow this further

Built from Basingstoke and Deane's papers

What the report saysPro

Report to Cabinet

Cabinet Date: 9 December 2025 Quarter 2 Capital Monitoring Report as at 30 September Subject: 2025 Cllr Gavin James – Co-Leader and Cabinet Member for Report of: Finance and Property

Lead Officer: Chief Finance Officer (Section 151 Officer) Chief Finance Officer (Section 151 Officer) – Adam Swain [email protected] Contact Officer: Accountancy Manager and Deputy Section 151 Officer – Sarah Finch – Tel 01256 845330 or email [email protected]

Ward(s): All Key Decision: No Appendix 1: Latest Approved Capital Programme 2025/26 to 2028/29

Exempt or Confidential Information It is considered that information contained within this report and appendix does not contain exempt information under the meaning of Schedule 12A of the Local Government Act 1972, as amended, and therefore can be made public.

Foreword – Cllr Gavin James Co-Leader and Cabinet Member for Finance and Property This report sets out the position on the council’s capital programme for the second quarter of 2025/26. The current forecast outturn for capital expenditure is £19.131M which is £3.387M below the latest approved programme for the year. This is due to changes in the expected timing of a number of programmes which will result in delayed spend, offset by expenditure on another scheme being brought forward. While the forecast capital expenditure for 2025/26 of £19.131M is a positive position, there remains challenges in terms of build cost inflation and supply chain issues. I recognise that this could have an impact on our capital projects, both in terms of budget control and delivery times Recommendation to Cabinet

It is recommended that Cabinet note: 1. The forecast capital expenditure for 2025/26 of £19.131M which is £3.387M lower that the latest agreed capital programme budget of £22.518M; 2. The approved increases to the 2025/26 capital budget from S106 contributions, capital grants and scheme rephasing under the Chief Finance Officer’s delegated powers as shown in section 2; 3. The 2025/26 significant forecast variations and explanations for them as shown in section 3; 4. The latest forecast of capital receipts, grants and contributions for 2025/26 in section 4; 5. The risks associated with the capital forecasts are as detailed in section 8; 6. The latest approved capital programme for 2025/26 to 2028/29 and the financing as shown in section 5 and detailed in Appendix 1; and 7. The capital programme remains fully funded from the council’s own resources up to 2028/29, based on the latest forecast of available resources.

Background, corporate objectives and priorities In accordance with the council’s Financial Procedure Rules, the Chief Finance Officer (CFO) has a responsibility to provide financial information and to report on the overall budget position of the council. To provide assurances that the council’s budgets are well managed and maintained, regular budget monitoring is undertaken with variances and required actions reported. The capital programme is reviewed on a quarterly basis in accordance with the council’s Capital Strategy, with a quarterly update reported to Cabinet and Council (for approval if required). This is only required to enable capital schemes in the programme to proceed and approve additions and changes to the programme. This report provides the forecast 2025/26 outturn position for capital spend at 30 September 2025. The forecasts and explanations have been discussed and agreed with Directors, Heads of Services and Project Managers in accordance with the council’s Policy and Budgetary Framework and supports the development of an effective and efficient council. Glossary of terms

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarter 2 Capital Monitoring Report as at 30 September 2025Report 294 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 8 attended
PH
Councillor Paul HarveyChair, expected
OC
Councillor Onnalee CubittCommittee Member, expected
GJ
Councillor Gavin JamesCommittee Member, expected
LJ
Councillor Laura JamesCommittee Member, expected
AK
Councillor Andy KonieczkoCommittee Member, expected
JM
Councillor John McKayCommittee Member, expected
KM
Councillor Kerry MorrowCommittee Member, expected
CT
Councillor Chris TomblinCommittee Member, expected

On this subject at Basingstoke and Deane

Search all
  1. Quarter 2 Capital Monitoring Report as at 30 September 2025This decision
  2. Quarter 3 Capital Monitoring Report as at 31 December 2025Approved
  3. Quarter 1 Capital Monitoring Report as at 30 June 2025Approved
  4. Quarter 1 Capital Monitoring Report as at 30 June 2025Agreed
  5. Quarter 3 Capital Monitoring Report 2024/25Agreed
  6. Quarter 2 Capital Monitoring Report as at 30 September 2024Agreed

More from Basingstoke and Deane Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Motion referred from Council - Protecting South Ham And Buckskin Residents From Compulsory Purchase And Ensuring Full Democratic AccountabilityThat Cabinet note the motion referred by Council and agree to progress the actions within the motion in accordance wi... Noted Open
8 Sep 2026 Motion referred from Council - Increasing Biodiversity Net Gain Through the Local PlanThat Cabinet support the direction of travel set out in the motion and continue work through the Local Plan process t... Decided Open
8 Sep 2026 Recommendations from the Environment and Infrastructure Committee – Climate Emergency StrategyThat Cabinet endorse the recommendations of the Environment and Infrastructure Committee and incorporate them into th... Decided Open
8 Sep 2026 Local Plan - Next Steps1) Agree that work on a new local plan should proceed under the new planning system as set out in the Planning and Co... Agreed Open
8 Sep 2026 Regeneration Lettings Plans – Amendment to Housing Allocations Scheme1) Approve the Regeneration Priority Assessment Framework as at Appendix 2 of the report. 2) Authorise the Head of Le... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies