RISK MANAGEMENT - UPDATE REPORT - FINANCIAL MANAGEMENT SYSTEM

Noted Finance 1 paper

AI summaryThe Audit Committee noted the financial management system report and requested a further update in six months on implementation progress [D]. No direct resource implications were identified [5.1].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFurther update requested in six months on system implementation [D]
MoneyNo direct resource implications [5.1]Information and update report [5.1]
What happens nextFurther update in six months [D]On financial management system implementation progress [D]
Who it affectsFinancial controls and external audit [3.2]Significant impact from the proposed system replacement [3.2]

What was decided

The Audit Committee noted the report [D].

It asked to receive a further update in six months on progress implementing the Council's financial management system [D].

Why

The Committee oversees the Council's risk management framework and provides assurance that systems are in place and working [3.1]. Report 3.1

The proposed replacement of the financial management system significantly affects financial controls and the external audit process [3.2]. Report 3.2

A detailed presentation is planned for the meeting, and the report summarises the overall risk management framework [3.3]. Report 3.3

What happens next

The Committee is to receive a further update in six months on financial management system implementation progress [D].

Options considered

  • Chosen: Receive a further update in six months on system implementation. To receive progress on the financial management system implementation process [D]

Implications

  • Financial: The proposed replacement of the financial management system significantly affects financial controls and the external audit process [3.2]. Report 3.2
  • Risk: The Corporate Risk Register contains 28 risks owned by the Corporate Management Team and 7 risks in watching brief mode [3.10]. Report 3.10
  • Other: The Committee provides assurance, while responsibility for individual risks remains with the relevant service area [3.1]. Report 3.1
  • Risk: The risk approach accepts some risk transparently while seeking to minimise adverse impacts and maximise benefits [3.4] [3.5]. Report 3.4, 3.5
  • Financial: The report identifies no direct finance, property or people implications [5.1]. Report 5.1
  • Risk: No new significant risks are identified for consideration in relation to the report [6.1]. Report 6.1
  • Equalities: The equalities assessment identified no significant issues [7.1]. Report 7.1
  • Climate: There are no direct climate change implications, while climate risks are captured in the Corporate Risk Register and other risk registers [8.1]. Report 8.1

Who and where

  • Audit Committee Report 3.1
  • Council service areas Report 3.1
  • Corporate Management Team Report 3.10
  • Officers and Members Report 3.7
  • Council services Report 3.5
  • Citizens and customers Report 3.4
  • S151 Officer Report 10.1
  • External audit process Report 3.2

Timeline

  • in six months: The Committee will receive a further update on financial management system implementation progress [D].
  • quarterly: The Corporate Management Team formally reviews the Corporate Risk Register [3.10]. Report 3.10
  • currently: The Corporate Risk Register contains 28 risks and 7 risks in watching brief mode [3.10]. Report 3.10
  • at the meeting: The meeting includes a detailed presentation on the financial management system update [3.3]. Report 3.3

Plain English for the jargon

  • Corporate Risk Register (CRR): It records corporate risks, leads, actions, status, mitigation and risk assessments [3.10] [3.11].
  • watching brief mode: A status for seven risks with outlines recorded in the register [3.10] [3.12].
  • Three Lines of Defence Model: The model in which risk management forms the organisation's second line [3.8].
  • risk appetite and risk tolerance: Framework assessments recorded with inherent, residual and changed risk [3.11].
  • S151 Officer: The Council officer consulted about the report [10.1].
  • financial management system: The system proposed for replacement, significantly affecting financial controls and external audit [3.2].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item35

Resolved

RESOLVED to note the report and receive a further update in six months on progress with regards to the implementation process of the Council’s financial management system.
Word for word from the decision Bath and North East Somerset published for this meeting. Source: democracy.bathnes.gov.uk

Follow this further

Built from Bath and North East Somerset's papers

What the report saysPro

Report to Audit Committee, 5 pages

Recommendation

2.1The Corporate Audit Committee is asked to:

Note the report and receive a further update in six months on progress with regards to the implementation process of the Council’s financial management system.

3 THE REPORT

3.1The Corporate Audit Committee has responsibility for overseeing the risk management framework within the Council. This does not mean accountability or responsibility for the risks which clearly sit with the respective Service area but the Committee does have a role in providing assurance that a system is in place and working.

3.2As part of its ongoing review of key risks throughout the Council it was agreed the Committee would include reviews of specific themes as well as corporate risks and this meeting details an update on the proposed replacement of the Council’s Financial Management System which clearly has a significant impact on financial controls and the External Audit process.

3.3A detailed presentation will be given at the meeting and the remainder of the report reminds the committee on our overall risk management framework.

Printed on recycled paper Context – Risk Management Framework

3.4Our strategy to manage risk recognises that both taking and accepting more risk is part of modern service delivery. However in accepting more risk we will do this in both a transparent and informed way to achieve the best results for citizens and customers.

3.5Therefore we want to promote an approach that focusses on the effective identification and management of risks to ensure the council is focussed on minimising adverse impacts and maximising benefits within the delivery of its objectives throughout all of its services.

3.6Active risk management is an integral component of our local code of corporate governance which is designed to help us achieve our aspirations, priorities and outcomes to deliver the Council’s Vision. This strategy therefore expects that we focus on taking the right actions to address risks and opportunities both in a transparent way and based on evidence.

3.7The framework is therefore designed to support Officers and Members in delivering on the Council’s plans and operational objectives.

3.8Risk Management forms the second line in the ‘Three Lines of Defence Model’ protecting our organisation.

3.9We do this in a sensible and proportionate way to actively manage risks down the risk matrix in terms of their potential impact on the organisation.

Printed on recycled paper LIKELIHOOD Almost Rare Unlikely Possible Likely Certain Catastrophic

Major IMPACT

Moderate

Minor

Negligible

Corporate Risk Register (CRR) (Appendix 1)

3.10All risk registers are dynamic documents, currently the CRR contains 28 risks which are owned by the Corporate Management Team and 7 risks in watching brief mode. Corporate Management Team review the register formally on a quarterly basis. The CRR identifies themes, service area/ director/ officer leads and describes the risks and commentary around actions, status and mitigation. This allows regular review of the changing landscape in local government and ability to provide co- ordinated responses to major threats.

3.11The inherent, residual and risk change are also captured along with an assessment of risk appetite and risk tolerance and structured around the following themes.

Regional Partnership Working Resource & Budget Management

Climate Change Transformation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
RISK MANAGEMENT: UPDATE REPORT: FINANCIAL MANAGEMENT SYSTEMReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Bath and North East Somerset

Search all
  1. RISK MANAGEMENT - UPDATE REPORT - FINANCIAL MANAGEMENT SYSTEMThis decision
  2. Risk Management ReviewNoted
  3. Risk Management ReviewNoted
  4. Risk Management Framework Review for periods ending 30 June 2026Noted
  5. Risk Management ReviewNoted
  6. Risk Management ReviewNoted

More from Bath and North East Somerset Audit Committee

All decisions
MeetingDecisionOutcome
13 May 2026 MINUTES: 11th February 2026RESOLVED that the minutes of the meeting held on 11 th February 2026 be confirmed as a correct record and signed by t... Decided Open
13 May 2026 Annual Plan - Internal Audit - 2026/27RESOLVED to approve the Internal Audit Plan 2026/27. Approved Open
13 May 2026 Committee Work Plan - 2026/27RESOLVED to note their 2026/27 workplan. Noted Open
11 Feb 2026 Minutes - 26th november 2025RESOLVED that the minutes of the meeting held on 26 th November 2025 be confirmed as a correct record and signed by t... Decided Open
11 Feb 2026 External audit - updateRESOLVED to note the Audit Update Report. Noted Open