CONSULTATION ON THE DEVELOPMENT OF THE INTERNAL AUDIT PLAN 2026/27

Noted Finance 1 paper

AI summaryBath and North East Somerset Council's Audit Committee resolved to comment on themes for the 2026/27 internal audit plan and noted regular review with a six month assessment to prioritise resources. [D] [2.2] No direct resource implications were identified. [5.1]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAudit themes for inclusion; resources reviewed at six months [2.1] [2.2]
MoneyNo direct resource implications [5.1]
What happens nextPlan finalised in early March [P14]Second half priorities and resources will be reviewed [2.2] [P12]
Who it affectsNot stated

What was decided

The Audit Committee resolved to comment on areas or themes for inclusion in the Internal Audit Plan for 2026/27. [D] [2.1] Report 2.1

It noted the intention to keep the plan under regular review, including a six month progress assessment, to prioritise resources as required. [D] [2.2] Report 2.2

Why

The planning process must deliver enough work for the Head of Internal Audit to independently assess the internal control framework and give a reasonable assurance opinion at the end of each year. [3.1] The Audit Committee is a key stakeholder and has responsibility for approving the plan. [P14] Report 3.1, P14

The method uses 8 high level themes and 3 detailed assessment factors. [P7] [P8] The factors are materiality, inherent risk and audit history. [P8] Consultation with officers, groups and the Audit Committee usually takes place from January to March. [3.1] [P9] Report P7, P8, 3.1, P9

The report set out five risk areas to help the committee consider useful audit coverage. [P14] They were cybersecurity and data security, human capital, digital disruption, new technology and AI, regulatory change, and business resilience. [P15] [P16] [P17] [P18] [P19] Cybersecurity and data security remain the top organisational risk, and 82% of Chief Audit Executives rated it their most important threat. [P15] Report P14, P15, P16, P17, P18, P19

What happens next

Feedback will be considered before the plan is finalised in early March. [P14] Stakeholder discussions with the listed officers and groups will take place up until the end of March. [3.1] [P9] Report P14, 3.1, P9

A full year plan for 1st April 2026 to 31st March 2027 will be produced and kept under continual review for unforeseen requirements. [3.2] [P12] Report 3.2, P12

A formal review at the six month stage may reprioritise and resource the second half of the financial year. [3.2] [P12] Any proposed changes will be notified to the Audit Committee. [P12] Consultation with the Audit Committee will continue throughout the year after the plan has been approved. [10.1] Report 3.2, P12, 10.1

Implications

  • Risk: An ineffective Internal Audit Service could cause a lack of internal control, failures of governance, weak risk management, supplementary External Audit Fees, undetected fraud and inadequate coverage. [6.1] Report 6.1
  • Staffing: Audit resources may be redirected to unforeseen issues, including investigations and urgent audit support. [P11] [P12] Staff may also act as Investigating Officer in financial irregularity investigations under the Council's disciplinary procedures. [P25] Report P11, P12, P25
  • Other: Internal Audit will continue work on the Annual Governance Statement, the Cabinet Office Data Matching National Fraud Initiative, internal control advice, external grant examinations and investigations of financial irregularities. [P20] [P21] [P22] [P23] [P24] [P25] Report P20, P21, P22, P23, P24, P25
  • Legal: There are no specific statutory considerations related to this report. [4.1] Internal Audit provision is expected to meet the Accounts & Audit Regulations, S151 of the Local Government Act, CIFPA Codes of Practice and global professional standards. [4.1] Report 4.1
  • Equalities: The audit process includes compliance with statutory guidance and regulations relating to equality and diversity. [7.1] Report 7.1
  • Climate: The plan process will consider climate change risks and opportunities. [8.1] It will report whether assurances can be given on delivery of the plan to mitigate this risk. [8.1] Report 8.1
  • Risk: Directorate and Strategic Risk Registers are reviewed when the plan is developed. [6.1] Internal Audit helps identify risks, improvement areas and recommend good practice. [6.1] Report 6.1
  • Financial: There are no direct resource implications relevant to this report. [5.1] Report 5.1

Who and where

  • Audit Committee [P14] [P12] Report P14, P12
  • Council services and corporate governance [P21] [P23] [P25] Report P21, P23, P25
  • Finance and risk functions [P6] [6.1] Report P6, 6.1
  • Internal Audit Service and staff [P11] [P12] [P25] Report P11, P12, P25
  • External funding bodies, including West of England Combined Authority [P24] Report P24
  • Officers and groups consulted during planning [3.1] [P9] Report 3.1, P9

Timeline

  • January to March [3.1] [P9]: Stakeholder conversations usually take place with officers and groups. [3.1] [P9] Report 3.1, P9
  • early March [P14]: Feedback is considered before the Internal Audit Plan is finalised. [P14] Report P14
  • 1st April 2026 to 31st March 2027 [3.2] [P12]: The initial full year audit plan covers the period. [3.2] [P12] Report 3.2, P12
  • six month stage [3.2] [P12]: A formal review may reprioritise and resource the second half of the financial year. [3.2] [P12] Report 3.2, P12
  • throughout the year after the plan has been approved [10.1]: Ongoing consultation with the Audit Committee continues. [10.1] Report 10.1

Plain English for the jargon

  • Reasonable Assurance Model: Planning method used to support an annual reasonable assurance opinion on internal controls. [3.1]
  • Annual Governance Statement: The Council statement supported by annual governance review work. [P21]
  • National Fraud Initiative: Cabinet Office Data Matching work coordinated and investigated by Internal Audit. [P22]
  • six month progress assessment: Formal review for prioritising and resourcing the second half of the financial year. [2.2] [P12]
  • Human Capital: A risk area covering diversity, talent management and employee retention. [P16]
  • Business Resilience: A risk area covering business continuity, disaster response and crisis management. [P19]
  • Digital disruption: The move from manual to digital processes, linked to new technology and AI. [P17]
  • AI: A technology area where the report says governance should ensure safe implementation. [P17]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item36

Resolved

RESOLVED 1) To comment on any areas or themes that they would like to be considered for inclusion in the Internal Audit Plan for 2026/27; and 2) To note the intention to keep the plan under regular review, including a six-month progress assessment, in order to prioritise resources as required.
Word for word from the decision Bath and North East Somerset published for this meeting. Source: democracy.bathnes.gov.uk

Follow this further

Built from Bath and North East Somerset's papers

What the report saysPro

Report to Audit Committee, 5 pages

Recommendation

2.1The Audit Committee is asked to comment on any areas or themes that they would like to be considered for inclusion in the Internal Audit Plan for 2026/27.

2.2Note the intention to keep the plan under regular review, including a six-month progress assessment, in order to prioritise resources as required.

3. THE REPORT

3.1Internal Audit Planning Methodology - Reasonable Assurance Model

3.1.1. The planning process is based on the fundamental requirement that the audit plan proposed will deliver sufficient work to enable the Head of Internal Audit to independently assess the internal control framework and give a reasonable assurance opinion at the end of each year. 3.1.2. The model used to develop the audit plan – the Reasonable Assurance Model - has regularly been described to the Committee in detail. It was created and adopted in conjunction with a number of other councils in the South West and its approach won a Public Finance award. Printed on recycled paper 1 3.1.3. The outline of the model is as follows with the key elements in the middle section which introduce a high-level assessment of themes based on good governance.

Organisational •Vision & Corporate Plan •Budget & MTFP Context •Corporate Risks

•8 Themes - High Level Assessment •Governance, Finance, IM&T, Assets, Risk, Procurement, Programmes, Performance

•3 Audit Factors - Detailed Assessment •Materiality, Inherent Risk, Audit History

3.1.4. A key part of the planning process is therefore extensive stakeholder consultation. Conversations in this regard usually take place between January to March and discussions will therefore take place with the following officers/ groups up until the end of March: • Section 151 Officer • Senior Finance Managers • Service Directors • Statutory Officers inc. Chief Executive and Monitoring Officer • Executive Leadersip Team • Audit Committee

3.2Rolling Plan Review

3.2.1. Members will be aware that some changes to planned work has been required in previous years in order to redirect audit resources to unforeseen issues arising in-year, such as where investigations or urgent audit support is required.

3.2.2. Whilst only relatively minor adjustments have been required to audit plans in recent years, the Internal Audit Service have continued to ensure a fluid approach is maintained to planned audit work. Therefore, whilst the usual consultation process will follow and a full-year audit plan will initially be produced to cover the period 1st April 2026 – 31st March 2027, the plan will be kept under continual review and adjusted to cover any further unforeseen requirements. A formal review of the annual plan will then take place at the six- month stage, if necessary, in order to adequately prioritise and resource the second half of the financial year. Any proposed changes will be notified to the Audit Committee.

3.3Audit Committee Consultation and Input

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CONSULTATION ON THE DEVELOPMENT OF THE INTERNAL AUDIT PLAN 2026/27Report 5 pages DownloadRead as text

At this meeting

Whole meeting

More from Bath and North East Somerset Audit Committee

All decisions
MeetingDecisionOutcome
13 May 2026 MINUTES: 11th February 2026RESOLVED that the minutes of the meeting held on 11 th February 2026 be confirmed as a correct record and signed by t... Decided Open
13 May 2026 Annual Plan - Internal Audit - 2026/27RESOLVED to approve the Internal Audit Plan 2026/27. Approved Open
13 May 2026 Committee Work Plan - 2026/27RESOLVED to note their 2026/27 workplan. Noted Open
11 Feb 2026 Minutes - 26th november 2025RESOLVED that the minutes of the meeting held on 26 th November 2025 be confirmed as a correct record and signed by t... Decided Open
11 Feb 2026 External audit - updateRESOLVED to note the Audit Update Report. Noted Open