Resolved
Agreed: That the modifications to the original scheme proposals as submitted in March 2008, in respect of the emerging proposals for the Bedford Station Quarter development, be supported. HEDR
Town Centre Working Group agreed this item on Monday 8 December 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed: That the modifications to the original scheme proposals as submitted in March 2008, in respect of the emerging proposals for the Bedford Station Quarter development, be supported. HEDR
To report to the Working Group on the emerging proposals for the Bedford Station Quarter development that offers a key opportunity to achieve a major new office quarter in the town centre and a significant contribution to the Town’s economic and physical regeneration plans.
The Working Group is invited to consider the emerging proposals for the Bedford Station Quarter development, to seek any clarification in respect of the progress made, development proposals and the project timescales and, if satisfied, to support the modifications to the original scheme proposals submitted in March 2008.
3. Key Issues
3.1Policy/Legal Issues
The Bedford Station Quarter has been determined as a Key Area of Change in the adopted version of the Bedford Town Centre Area Action Plan (TCAAP), which has been prepared and published by the Borough Council. It outlines a vision for the town centre, identifies investment priorities and provides guidelines on shaping the form of the centre over the next 15-20 years. The adopted Local Plan (October 2002) also allocated the train station as an “Opportunity Site” suitable for residential and employment use.
The Council has embraced the Government's growth agenda as set out in the Sustainable Communities Plan and has recognised that growth requires investment in both the local economy and in infrastructure. The availability of Government funding has sought to ensure that the growth achieved is both sustainable and in the best interests of the community and, in this regard, Executive Decision Number 338 (dated 17 February 2006) confirmed the result of funding bids made in the Bedford area in respect of the second round of Growth Area Funding (GAF2) by the Department for Communities and Local Government (DCLG). This included the award of £250,000 for the preparation of a Master Plan for the Bedford Station Quarter and related feasibility work. Executive Decision 338 authorised acceptance of the grant and that funding agreements be entered into with DCLG. A further sum of £37,800 was secured in April 2007 (Executive Decision 462).
The proposed development of the Bedford Station Quarter has the potential to provide the necessary employment growth to stimulate and create a commercial development in Bedford town centre that will improve private sector confidence and ultimately lead to greater levels of commercial investment and jobs in the future.
3.2Resource Implications
There is currently no landowner interest as far as for as the Council is concerned although the Council is seeking external grant funding to assist with essential land assembly opportunities (Executive Decision 546 fully outlines the potential opportunity that currently exists).
The key output to date has been the masterplanning exercise and the submission of an outline planning application for determination in due course. The scheme is, however, subject to refinement following the issue of a Transport Impact Assessment report and having regard to issues raised by stakeholders in relation to the initial scheme designs (reported to the Working Group at its meeting on 12 March 2008). This second stage of the process has now commenced at a cost of £70,000, for which Bedfordshire County Council have contributed the sum of £35,000.
There is a risk that the development will not proceed to a satisfactory conclusion or will be subject to delay due to economic conditions. The proposed scheme will be subject to the necessary approvals and, generally, the viability of redevelopment schemes is heavily dependant upon the costs of land assembly, ambition of project and the rental/capital value deriving from it. It must be recognised that, even with necessary consents, the eventual development will depend on a financially viable scheme appraisal.
4. Details
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Town Centre Development: Bedford Station Quarter Progress ReportReport | 12 pages | DownloadRead as text |
Follow Town Centre Working Group at Bedford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Mar 2010 | High Street Environmental ImprovementsAgreed: (1) That the submission of the Heritage Lottery Fund Townscape Heritage Initiative Round One funding bid on 3... | Agreed | Open |
| 9 Mar 2010 | Town Centre West - Progress ReportAgreed: (1) That the progress made to date in respect of the redevelopment of Bedford Town Centre West be acknowledge... | Agreed | Open |
| 9 Mar 2010 | Bedford Station Quarter - Progress ReportAgreed: That the progress made to date in respect of the redevelopment of the Bedford Station Quarter be acknowledged... | Agreed | Open |
| 23 Sep 2009 | Bedford Station Quarter - Progress ReportAgreed: (1) That the emerging proposals for the Bedford Station Quarter development be approved. (2) That the emergin... | Agreed | Open |
| 23 Sep 2009 | Bedford Borough Area - Infrastructure Delivery Programme 2009/21Agreed: That the Infrastructure Delivery Programme 2009/2021 be noted and approved for consideration by the Bedford B... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.