Agreed: (1) That the emerging proposals for the Bedford Station Quarter development be approved. (2) That the emerging scheme proposals in the outline planning application that aimed to achieve a new office quarter in the Town Centre, a new transport interchange and a significant contribution to the Town’s economic and physical regeneration plans be supported. OD(REG)
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
To report to the Working Group on progress with proposals for the Bedford Station Quarter that aim to achieve a major new office quarter in the town centre, a new transport interchange and a significant contribution to the town’s economic and physical regeneration plans.
Recommendations
The Working Group is invited to:
(a) Consider the emerging proposals for the Bedford Station Quarter development and to seek any clarification in respect of the progress made, development proposals and the project timescales;
(b) Support the emerging scheme proposals in the outline planning application that aim to achieve a new office quarter in the town centre, a new transport interchange and a significant contribution to the town’s economic and physical regeneration plans.
Reasons for recommendations
To enable the Working Group to further consider the emerging regeneration proposals for the Bedford Station Quarter.
4. Key Issues
4.1Policy/Legal Issues
The Bedford Station Quarter is a Key Area of Change in the adopted version of the Bedford Town Centre Area Action Plan (TCAAP). It outlines a vision for the town centre, identifies investment priorities and provides guidelines on shaping the form of the centre over the next 15-20 years. The adopted Local Plan (October 2002) also allocated the railway station area as an “Opportunity Site” suitable for residential and employment use.
rac5154 TCWG – September 2009 5(1)(1) Bedford Station Quarter Progress Report The proposed development of the Bedford Station Quarter has the potential to provide the necessary employment growth to stimulate and create a commercial development in Bedford town centre that will improve private sector confidence and ultimately lead to greater levels of commercial investment and jobs in the future.
4.2Resource Implications
The Council has embraced the Government's growth agenda as set out in the Sustainable Communities Plan and has recognised that growth requires investment in both the local economy and in infrastructure. The availability of Government funding has sought to ensure that the growth achieved is both sustainable and in the best interests of the community and, in this regard, the Department for Communities and Local Government (DCLG) initially awarded £250,000 under the Growth Area Funding (GAF2) scheme for the preparation of a Master Plan for the Bedford Station Quarter and related feasibility work (subsequently increased to £327,606).
While the Council has no current landowner interest in the Station Quarter, it is seeking to fully utilise external grant funding under the DCLG Growth Fund programme to assist the Council with essential land assembly opportunities. In this regard a further allocation of £1,250,000 was made as part of the Growth Area Funding (GAF3) programme towards the delivery of Bedford Station Quarter. Detailed negotiations are taking place with regard to land acquisition and, if necessary, a further update will be provided at the meeting.
The key outputs to date have been the masterplanning exercise, the submission of an outline planning application and preparation of the essential accompanying assessments (i.e. Transport Impact, Environmental Impact and Flood Risk). These latter assessments have been the main pieces of work completed over the last year, alongside extensive and protracted engagement with Network Rail and relevant rail operators, and have required use of the balance of funding previously approved for the project under the Growth Area Funding (GAF2) scheme.
There is a risk that some further work will be required in the course of the consideration of the planning application by the Council’s planning department and, if so, a priority commitment will need to be made against limited existing town centre development budgets.
Risk implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
High Street Environmental ImprovementsAgreed: (1) That the submission of the Heritage Lottery Fund Townscape Heritage Initiative Round One funding bid on 3...
Town Centre West - Progress ReportAgreed: (1) That the progress made to date in respect of the redevelopment of Bedford Town Centre West be acknowledge...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.