Resolved
That the report be noted and approved. ED(E&SC)
Environment, Regeneration and Corporate Services Policy Review and Development Committee noted this item on Monday 30 November 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted and approved. ED(E&SC)
1.1This report provides members with an outline of the steps and process followed to develop a forward programme of highway works.
2.1The Committee’s view on the outline methodology for determining the forward programme of works is requested.
3.1This report provides details of how the highways works programme is developed and forms part of a major review of Highways maintenance issues. Its aim is to assist Members in gaining a full understanding of the issues and to enable them to consider improvements to this critical Council service.
4 KEY ISSUES
Legal
4.1Bedford Borough Council is responsible for the management, maintenance and improvement of the non-trunk highway network in Bedford Borough. The Council has a legal responsibility for the highway network in terms of keeping the highway available and safe for passage for the travelling public. It undertakes this duty in its role as the Highway Authority.
4.2‘Maintenance’ includes carrying out large scale programmed repairs to existing roads and pavements. These are usually planned many months (or even years) in advance.
4.3‘Improvements’ includes changes to the network designed to modify or influence travel behaviour to help deliver the Council’s transportation policies as set out in (for example) the Local Transport Plan. Works of this nature are commonly described as Integrated Transport Schemes and may include pedestrian crossings, safer routes to schools schemes and traffic management schemes.
Policy
4.4The Borough Council is currently utilising the former Bedfordshire County Council ‘Highways Maintenance Plan’. The principles of the highway maintenance strategy are:
• to deliver the statutory obligations of the authority; • to be responsive to the needs of users’ and the community; • to contribute to effective highway asset management and maintain the asset value; • to support effective delivery of the statutory network management duty; • to support and add value to local transport objectives; • to support and add value to wider corporate policy objectives.
4.5The main components of an effective Highway Maintenance Plan include having a defined hierarchy for all elements of the network, setting a robust framework of policies and objectives for the service and maintaining a detailed inventory of all relevant components of the asset and their condition.
4.6To be effective, these key components need to be supplemented by the following; • a comprehensive management system for inspecting, recording, analysing, prioritising and programming maintenance works to optimise their asset management contribution. • arrangements to finance, procure and deliver maintenance works, in accordance with the principles of sustainability and value for money.
• a risk management strategy clearly identifying and evaluating the risks and consequences of investment decisions and measures to mitigate them.
• arrangements to monitor, review and update as necessary, each component of the strategy and the performance of the strategy.
4.7This Committee’s review of Highway Maintenance issues will inform and guide revisions to the Highway Maintenance Plan of the Council.
4.8The Borough Council is currently working to the former Bedfordshire County Council second Local Transport Plan (2006/7-2010/11). The Borough Council is currently developing a draft third Local Transport Plan (LTP3). The LTP3 will be developed in partnership with a Local Transport Forum as part of LAA Partnership working arrangements. The LTP3 will provide over arching polices for all modes of transport and cover their maintenance, management and improvement. Risk
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Review of Highways MaintenanceReport | 5 pages | DownloadRead as text |
Follow Environment, Regeneration and Corporate Services Policy Review and Development Committee at Bedford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 31 Mar 2011 | MinutesThat the of the meeting of the Committee held on 1 March 2011 be confirmed. Chair | Decided | Open |
| 31 Mar 2011 | Forward Plan of Key DecisionsThat the Forward Plan of Key Decisions for the period April – July 2011 be noted. Chair | Noted | Open |
| 31 Mar 2011 | Benefits Service Review(1) That the recommendations and conclusions sections of the report on the be agreed, with the addition of the follow... | Agreed | Open |
| 31 Mar 2011 | Electric Car Charging FacilitiesThat the position statement be noted. AD(H&T) | Noted | Open |
| 31 Mar 2011 | Winter Maintenance PlanThat the position statement be noted. Chair | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.