CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bedford Borough Council

Winter Gritting

Noted Committee 1 paper

Environment, Regeneration and Corporate Services Policy Review and Development Committee noted this item on Thursday 8 July 2010. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

(1) That the position statement be noted. (2) That the Committee receive a report on the provision and maintenance of salt bins at its next meeting. (3) That a further report on winter maintenance and the preparations for the 2010-11 winter be presented to the Committee at its meeting on 29 November 2010. AD(E&C)
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Environment, Regeneration and Corporate Services Policy Review and Development Committee, 4 pages

Executive summary

1.1This report provides an update on progress in reviewing policy for the forthcoming winter as a result of the severe winter of 2009/10

1.2A key issue was the inability to procure replenishment stock of salt. This meant a reduction in the number of routes treated.

Recommendations

2.1That the position statement is noted.

Reason for recommendation

3.1To ensure that Committee are fully briefed on the Council’s Winter Maintenance strategy.

4 Implications

Legal

4.1Bedford Borough Council is the highway authority for the Borough and its duty to maintain the highway is set out by Section 41 of the Highways Act 1980 as amended by S111 of the Railways and Transport Safety Act 2003 (which came into force on 1st November 2003): This amendment inserted after section 41(1) of the Highways Act 1980 (c. 66) (duty of highway authority to maintain highway) the following requirement “(1A) In particular, a highway authority are under a duty to ensure, so far as is reasonably practicable, that safe passage along a highway is not endangered by snow and ice”.

Policy

4.2The Council’s current winter maintenance plan has key objectives of keeping the roads clear of ice and snow. Resource

4.3The Winter Maintenance service is delivered in part through the Highways term Contract with Amey, and in part through in house delivery via CSD.

4.4Funding to cover the Amey lump sum costs, and anticipated CSD costs have been included in the 2010/11 Highways Revenue budget based on a ‘normal’ winter period. Should severe weather occur which necessitates additional snow clearance to be undertaken then consideration will need to be given to provide additional resources to maintain the service; this is usually through a call on general contingency funds.

4.5As part of the winter maintenance budget an allocation is made for the purchase of salt. As the winter season develops salt is replenished through supply contracts and this cost is covered from existing resource. Additional funding has already been made available from the Council’s general contingency fund to purchase and store 3,000 tonnes of marine salt from abroad in order to ensure the council is fully prepared in the event of a further severe winter (see Executive Decision 825).

Risk

4.6In the event of another severe winter it is likely there will be another national shortage of salt supplies, particularly as current suppliers are struggling to meet existing requirements. If this happens then the Council will be required by Government to reduce the number of roads that are treated in anticipation of ice.

Environmental

4.7The value of keeping roads open and relatively safe in icy conditions using salt is widely acknowledged. If roads are not cleared, the impact of accidents and increased fuel consumption are likely to be as significant in environmental and economic terms.

Equalities

4.8Increasing the robustness of our winter maintenance service can ensure that the priority highway network is available for all to use during periods of adverse weather.

5 Details

As a result of the last winter a number of reviews are underway at national, regional and local level. Our review of the Winter Maintenance Service includes the following areas of consideration:-

5.1Coordination

5.1.1 The decision-making protocol is to be clarified with roles better defined. 5.1.2 Decisions on when to salt are likely to remain delegated to Amey, given that they currently maintain the Icelert stations around the Borough. They also have a vigorous decision making progress designed to give a strong case to defending winter maintenance decisions against potential claims. The decision is taken daily and is emailed to relevant parties.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 8 Winter MaintenanceReport 4 pages DownloadRead as text

At this meeting

Whole meeting

More from Bedford Environment, Regeneration and Corporate Services Policy Review and Development Committee

All decisions
MeetingDecisionOutcome
31 Mar 2011 MinutesThat the of the meeting of the Committee held on 1 March 2011 be confirmed. Chair Decided Open
31 Mar 2011 Forward Plan of Key DecisionsThat the Forward Plan of Key Decisions for the period April – July 2011 be noted. Chair Noted Open
31 Mar 2011 Benefits Service Review(1) That the recommendations and conclusions sections of the report on the be agreed, with the addition of the follow... Agreed Open
31 Mar 2011 Electric Car Charging FacilitiesThat the position statement be noted. AD(H&T) Noted Open
31 Mar 2011 Winter Maintenance PlanThat the position statement be noted. Chair Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies