Bedford Western Bypass Phase 1- Contract Close Out

Decided Executive 2 papers

Executive decided this item on Wednesday 20 June 2012. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

Description of Decision (1) That the financial settlement reached with the main contractor be endorsed. (2) That the experience gained from this contract be applied to future projects of a similar type. (3) That the allocation of a one-off Reserve to cover the predicted residual scheme costs for future years of £262,800 be supported (see Decision 10 below: 2011/2012 Provisional Outturn). (4) That the saving of £1.579 million made against the original Provision for the contract be released and reallocated to Town Centre investment as a key capital priority. Reason for Decision To ensure that the Council understands the reasons for the cost overruns and applies the lessons learnt in the preparation of future contracts of this type.
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Executive, 11 pages

Executive summary

This report records the circumstances surrounding the financial completion of the contract to build the first phase of Bedford Western Bypass and concludes the examination of issues that caused the costs to overrun substantially from the tender price. As a consequence of the work to reduce the contractual claim and securing agreement on the contractual settlement at a value of £29.163million a sum of £1.579million is recommended to be released from the £4.400million provision established to meet the likely final contract cost. The report also seeks to identify lessons to be learnt from the project for application on future contracts of this type and advises on the reallocation of surplus funding provision arising from the project.

Recommendations

The Executive is invited to consider and, if satisfied, to;

(a) Endorse the financial settlement reached with the main contractor;

(b) Approve that the experience gained from this contract is applied to future projects of a similar type;

(c) Support the allocation of a one-off Reserve to cover the predicted residual scheme costs for future years of £262,800 (see separate 2011/2012 provisional outturn report on the agenda);

(d) Agree that the saving of £1.579 million made against the original Provision for the contract be released and reallocated to Town Centre investment as a key capital priority.

Reason for recommendations

To ensure that the Council understands the reasons for the cost overruns and applies the lessons learnt in the preparation of future contracts of this type.

12(1) 4. Key Implications

4.1Legal Issues

There are no legal implications arising directly from this report. Decisions on forms of contract to be used for other projects will need to take account of issues raised in relation to this project.

4.2Policy Issues

There are no direct and immediate Policy changes needed in relation to the way projects of this scale and magnitude are managed. The experience gained through this contract can be considered in future reviews of the Council‟s Procedure Rules and Capital Investment Strategy.

A key objective of the Corporate Plan is “Protecting and preserving the natural and built environment whilst enabling and supporting sustainable growth”. Central to delivering on this objective will be to improve the infrastructure within the Borough, particularly in the Town Centre which acts as a hub of the Council‟s economic development ambitions. A vibrant and prosperous Town Centre is a critical building block to support economic activity.

The release of £1.579 million from the Provision allows the opportunity to reinvest this sum into Town Centre infrastructure projects which can be targeted at improving the „offer‟ of the Town Centre.

Competition for business is fierce and the Council needs to continue to demonstrate its confidence in the regeneration of the Town Centre as not only does this help to provide a healthy and vibrant town centre attracting shoppers and encouraging businesses it acts as a wider catalyst to promoting economic development in the Borough which is essential to helping all sectors of business and the community enjoy a better level of prosperity.

A key project is the refurbishment of the Allhallows Multi-Storey Car Park. This car park, built in the early 1960‟s, is nearing the end of its current design life and needs significant investment to make it fit for purpose. It is part of the gateway to the Town Centre and, for many visitors, is the first and last impression they have of the Town. Refurbishing the car park is considered to be a key project to help arrest the decline of this area of the Town.

4.3Resource Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bedford Western Bypass Phase 1- Contract Close OutReport 11 pages DownloadRead as text
PDF
Item 12: Bedford Western Bypass: APPENDIX AAppendix 2 pages Download

At this meeting

Whole meeting

On this subject at Bedford

Search all
  1. Bedford Western Bypass Phase 1- Contract Close OutThis decision
  2. Bedford Western Bypass Northern SectionNoted

More from Bedford Executive

All decisions
MeetingDecisionOutcome
15 Jul 2026 Minutes of Previous MeetingDescription of Decision That the Minutes of the meeting of the Executive held on 3 June 2026 be confirmed. Reason for... Decided Open
15 Jul 2026 Local Government and Social Care Ombudsman Annual Review Letter 2025/2026Description of Decision That the Local Government and Social Care Ombudsman’s Annual Review letter for 2025/2026 for ... Noted Open
15 Jul 2026 RIPA Annual ReportDescription of Decision (1) That it be noted that, in the period 1 April 2025 to 31 March 2026, there were no applica... Noted Open
15 Jul 2026 Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026... Approved Open
15 Jul 2026 Corporate Plan 2024-2028 Performance Report year-end 2025/2026Description of Decision That the latest performance as outlined within the Key Indictor Performance Report at Appendi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies