Resolved
(1) That the update relating to Executive Decision 1154 be noted. (2) That the Committee be kept informed of progress on the bypass. SOSO
Environment and Sustainable Communities Overview and Scrutiny Committee noted this item on Thursday 16 January 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) That the update relating to Executive Decision 1154 be noted. (2) That the Committee be kept informed of progress on the bypass. SOSO
1.1The Bedford Western Bypass – Northern Section (“the Scheme”) is a key element of the Local Transport Plan 2011 – 2021 and other Council policies as a high priority major project to be delivered.
1.2Previous decisions have authorised the development of the design and publication of a Compulsory Purchase Order (CPO) and Side Roads Order (SRO) (“the Orders). As a consequence of objections to the CPO and SRO Government announced the intention to hold a Local Public Inquiry, but before this took place the Orders were withdrawn in the light of concerns over aspects of the objections made.
1.3At the time the CPO and SRO were published (authorised by Decision 1049), the likelihood of being able to fund land acquisition, compensation and construction of the Bypass was considered. An element of the funding was to be provided from the adjoining housing development.
1.4In the year since the Orders were first made the anticipated progress has not been made in relation to the housing developments. The situation now is that negotiations on an acceptable development package continue, but with significant issues still to be resolved. The recommendations in this report are not affected by the outcome of those negotiations.
1.5Progress has now been made in investigating the objections made to the original Bypass Orders. As a result it is now believed that the Bypass could be promoted successfully through the necessary statutory procedures.
1.6The purpose of this report is to consider whether to adopt a Bypass delivery approach based on the Council promoting and funding the Scheme itself.
*(1) That in relation to the Bedford Western Bypass – Northern Section it is recommended that the Mayor:
1. Reaffirms the Council’s intention to implement Phase 2 of the Bedford Western Bypass (the Scheme) in accordance with Executive Decision 1049 at the earliest opportunity,
2. Approves the principle of the Council funding the Scheme as “Highway Authority” by means of the resources and commitment outlined at paragraphs 4.7 to 4.9 of this report,
3. Approves the making of a Compulsory Purchase Order and Side Roads Order in accordance with Executive Decision 1049 and the Scheme design changes since then outlined in this report ,
4. Confirms that the Assistant Director (Highways and Direct Works) be authorised to approve such minor amendments to the Scheme design referred to at paragraph 3 above as may be required as a consequence of enquiries regarding interests in the CPO land and surrounding land or of negotiations with affected landowners, or of consultations with Government (as confirming authority),
5. Acknowledges the intention to refresh the capital allocation for the provision of the Scheme to ensure that the capital programme includes the estimated full scheme costs, including the associated design, promotion and procedure costs outlined at paragraph 4.8 and 5.11 of the report, and
6. Acknowledges the risks outlined in the report and confirms that, whilst the funding currently available is considered to be adequate, the commitment of the Council to fund from the Council's own resources any additional costs that may arise from unforeseen events, including compensation claims that exceed the current estimates and contingencies included within the current Scheme value.
3.1Completion of the Bedford Western Bypass – Northern Section is a high priority for the authority and for the future economic development of the area. It was originally envisaged that the Bypass would be implemented by the private sector as a development led project, but lack of progress has required the Council to take an increasingly proactive role in securing its delivery.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Bedford Western Bypass Northern SectionDecisions | 25 pages | DownloadRead as text |
Follow Environment and Sustainable Communities Overview and Scrutiny Committee at Bedford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Previous MinutesRESOLVED That the Minutes of the meeting of the Committee held on the 18 June 2026 be confirmed. Chair | Decided | Open |
| 16 Jul 2026 | Local Plan 2050RESOLVED That the Committee noted the update. HCPI&ST | Noted | Open |
| 16 Jul 2026 | Executive DecisionsRESOLVED 1. The Committee noted that there were no meetings of Executive prior to the publication of the agenda, deci... | Noted | Open |
| 16 Jul 2026 | Notice of Forthcoming Decisions to be taken by the ExecutiveThat the Notice of Forthcoming Decisions for the period 1 August 2026 to 30 November 2026 be received. SDSO | Decided | Open |
| 16 Jul 2026 | Committee Work ProgrammeThat an item on Biddenham (Great Ouse Way) Country Park be added to the Committee’s Work Programme. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.