CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bedford Borough Council
Full Council, Wednesday 2 February 2022 at 6.30pm

REPORT OF THE GENERAL PURPOSES COMMITTEE

Approved Committee 2 papers

Full Council approved this item on Wednesday 2 February 2022. Below is the council's own wording, with the papers it was decided on.

Item94

Resolved

That the revised Planning Committee Scheme of Delegation as set out in Appendix 1 of the report be adopted.
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Full Council, 5 pages

Executive summary

1.1Following agreement at Planning Committee (in June 2021) and General Purposes Committee (in September 2021) a revised Scheme of Delegation was approved by Full Council in October 2021.

1.2In reaching its decision, Full Council resolved:

 That the Portfolio Holder for Town Centres and Planning work with Officers to being forward a review to Planning Committee, and hence to General Purposes Committee and Full Council, that will include proposals on how reserved matters are dealt with under the Scheme of Delegation.

1.3This paper proposes a further revision to the Scheme of Delegation to allow Members to “call in” major applications for Reserved Matters. This type of application has previously been determined by officers under delegated powers.

Recommendation

2.1To adopt, if satisfied, the revised Scheme of Delegation as set out in Appendix 1.

11.1(1) 3. REASON FOR RECOMMENDATION

3.1The proposals will increase the ability of the Planning Committee to exercise its oversight of new major developments.

4. KEY IMPLICATIONS

4.1Legal Issues The Council is entitled to delegate to officers such matters as it considers appropriate subject to the requirements of the Council’s constitution. Any changes to the scheme which are approved by Planning Committee pursuant to this report will require subsequent approval by Full Council in accordance with the constitution.

4.2Policy Issues None.

4.3Resource Implications The alteration to the Scheme of Delegation will increase the workload for the available staff resources in the planning department by increasing the need for the preparation of reports and the work associated with preparing Committee items. This increase can be accommodated within the additional resources recently agreed for the department.

4.4Risk Implications No risks have been identified from taking some previously delegated decisions to Committee.

4.5Environmental Implications None

4.6Equalities Impact In preparing this report, due consideration has been given to the Borough Council’s statutory Equality Duty to eliminate unla wful discrimination, advance equality of opportunity and foster good relations, as set out in Section 149(1) of the Equality Act 2010.

It is considered that there is no overall adverse effect on equality, and the temporary scheme of delegation does not discriminate against any of the protected groups in isolation.

11.1(2) 5. Details

5.1There are two main types of planning application – applications for Full planning permission and applications for Outline planning permission.

5.2An application for Full planning permission results in a decision on the detailed proposals of how a site can be developed. If planning permission is granted, and subject to compliance with any planning conditions that are imposed, no further engagement with the Local Planning Authority is required to proceed with the development granted permission, although other consents may be required.

5.3An application for Outline planning permission allows for a decision on the general principles of how a site can be developed. Outline planning permission is granted subject to conditions requiring the subsequent approval of one or more ‘Reserved Matters’.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 11.1 Appendix AAppendix 16 pages Download
PDF
REPORT OF THE GENERAL PURPOSES COMMITTEEReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Bedford

Search all
  1. REPORT OF THE GENERAL PURPOSES COMMITTEEThis decision
  2. Reports of the general purposes committeeApproved
  3. Report of the general purposes committeeApproved
  4. Reports of the general purposes committeeApproved
  5. Report of the general purposes committeeApproved
  6. Reports of the general purposes committeeApproved

More from Bedford Full Council

All decisions
MeetingDecisionOutcome
1 Jul 2026 MINUTESTo approve as a correct record and to authorise the Speaker to sign the Minutes of the Annual Council meeting held on... Approved Open
1 Jul 2026 Report of the bedfordshire fire and rescue authorityThat the report of Bedfordshire Fire and Rescue Authority be received. Decided Open
1 Jul 2026 Report of the mayor/executive membersThat the use of the Special Urgency Procedure be noted. (2) Membership of Executive and Changes to Executive Committe... Noted Open
1 Jul 2026 Reports of the general purposes committee(1) That the Executive and Overview & Scrutiny Protocol and Employee Partnership Terms of Reference be adopted as par... Approved Open
1 Jul 2026 Report of the audit committeeThat the updated Local Code of Corporate Governance be adopted. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies