Executive, Wednesday 8 June 2022 at 6.30pm

Risk Management Arrangements - Review of Risk Management Strategy

Approved Executive 2 papers

Executive approved this item on Wednesday 8 June 2022. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

Description of Decision That the Risk Management Strategy be approved. Reason for Decision To ensure that the Council has an effective Risk Management Strategy.
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Executive, 4 pages

Executive summary

To undertake an annual review of the Risk Management Strategy.

Recommendations

The Executive is requested to consider the report and, if satisfied, approve the Risk Management Strategy.

Reason for recommendation

To ensure that the Council has an effective Risk Management Strategy. 4. KEY IMPLICATIONS

(a) Legal Issues

The Accounts and Audit (England) Regulations 2015, Regulation 3 requires that “A relevant authority must ensure that it has a sound system of internal control which— (a) facilitates the effective exercise of its functions and the achievement of its aims and objectives; (b) ensures that the financial and operational management of the authority is effective; and (c) includes effective arrangements for the management of risk”.

(b) Policy Issues

Risk management is a key element of the Council’s Corporate Governance arrangements and, as part of these arrangements, the Council has an approved Risk Management Strategy (Appendix A).

15(1) (c) Resource Implications

There are no direct additional resource requirements arising from this report.

(d) Risk Implications

This report is a key component of the Council’s overall assurance framework.

(e) Environmental Implications and contribution to achieving a net zero carbon Council by 2030

There are no direct environmental implications arising from this report.

(f) Equality Analysis

In preparing this report, due consideration has been given to the Borough Council’s statutory Equality Duty to eliminate unlawful discrimination, advance equality of opportunity and foster good relations, as set out in Section 149(1) of the Equality Act 2010.

A relevance test for equality has been completed. The equality test determined that the activity has no relevance to Bedford Borough Council’s statutory equality duty to eliminate unlawful discrimination, advance equality of opportunity and foster good relations. An equality analysis is not needed.

5. DETAILS

The Council has an approved Risk Management Strategy (Appendix A) which provides guidance on evaluating the likelihood and potential impact of risk. The Strategy recommends that consideration is given to the following factors when evaluating risk:

 Service Disruption  Financial  Reputation  People  Governance

15(2) The Risk Management Strategy is reviewed on an annual basis to ensure that the Strategy remains appropriate for the determination of risk, the assessment and management of risk and the reporting of risk – this was last undertaken on the 9 June 2021. This review has determined that the Risk Management Strategy remains fit for purpose and is set out at Appendix A.

The Council’s Risk Management arrangements are consistent with the Institute of Internal Audit Three Line Model, which is applied to corporate governance assurance processes.

The 1st Line of Assurance are the Risk Registers that are owned by Directorates, i.e. Operational Risk Registers. The 2nd Line of Assurance incorporates a range of corporate control measures and includes a review of the Strategic Risk Register undertaken by the Insurance and Risk Team Leader on a quarterly basis in addition to a consideration of risks included in

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 15 Risk Management Strategy Appendix AAppendix 19 pages Download
PDF
Risk Management Arrangements: Review of Risk Management StrategyReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Bedford

Search all
  1. Risk Management Arrangements - Review of Risk Management StrategyThis decision
  2. Risk Management Arrangements - Review of Strategic and Corporate RisksNoted
  3. Risk Management Policy, Statement and StrategyApproved
  4. Risk Management Arrangements - Review of Strategic and Corporate RisksDecided
  5. Local Flood Risk Management Strategy 2022Approved
  6. Risk Management Arrangements - Review of Strategic and Corporate RisksDecided

More from Bedford Executive

All decisions
MeetingDecisionOutcome
15 Jul 2026 Minutes of Previous MeetingDescription of Decision That the Minutes of the meeting of the Executive held on 3 June 2026 be confirmed. Reason for... Decided Open
15 Jul 2026 Local Government and Social Care Ombudsman Annual Review Letter 2025/2026Description of Decision That the Local Government and Social Care Ombudsman’s Annual Review letter for 2025/2026 for ... Noted Open
15 Jul 2026 RIPA Annual ReportDescription of Decision (1) That it be noted that, in the period 1 April 2025 to 31 March 2026, there were no applica... Noted Open
15 Jul 2026 Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026... Approved Open
15 Jul 2026 Corporate Plan 2024-2028 Performance Report year-end 2025/2026Description of Decision That the latest performance as outlined within the Key Indictor Performance Report at Appendi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies