Description of Decision That the Risk Management Policy, Statement and Strategy, as attached at Appendix A to the report, be approved. Reason for Decision To ensure that the Risk Management Policy, Statement and Strategy are current and effective in enabling risks and opportunities faced by the Council to be identified and managed appropriately.
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
1.1The Council’s Risk Management Policy requires the Strategy be reviewed on an annual basis to ensure that it remains appropriate in enabling the Council to identify and manage risks.
1.2Following the review and updated Risk Management Policy, Statement and Strategy is proposed.
1.3Key changes are (i) clarification of definition between Strategic Risks and Business Risks, (ii) addition of Project and Partnership risks within this Risk Management Framework (iii) the reclassification of high rated risks from Catastrophic to Severe. Consideration is also being given to risk mitigation, quantification of risk appetite, tolerance and capacity as well as reviewing the process for equality risk assessment and other risks such as climate change within the overall Risk Management Framework.
Recommendation
The Executive is invited to consider and, if satisfied, to approve the Risk Management Policy, Statement and Strategy attached at Appendix A.
Risk Management Policy, Statement & Strategy /Executive/8th January 2025 7(1) 3. REASONS FOR RECOMMENDATION(S)
3.1To ensure that the Risk Management Policy, Statement and Strategy are current and effective in enabling risks and opportunities faced by the Council to be identified and managed appropriately.
4. THE CURRENT POSITION
4.1The Council has an effective Risk Management Strategy and risk management system which currently tracks over 300 individual risks and 800 control measures, thereby facilitating an overall view of risk across the Council. This is further enhanced via a network of Risk Champions across the council who meet regularly to peer review risk outputs and to horizon scan for any upcoming risk issues for the council’s plans and duties.
4.2Whilst significant time and resource has been spent to develop these risk management processes across the Council, the Officers have taken time to review the extent to which this can be further developed to improve our risk definitions and also the quantification of risk appetite, tolerance and capacity. The proposed amendments to the existing Risk Management Policy, Statement and Strategy are contained in the Appendix
4.3The Officers consider the council’s approach to risk has matured but, the Officers recognise there is more to be done, specifically (i) the need to review the process for equality risk assessments and others specifics such as climate change and (ii) consider Risk Mitigation, develop the Risk Appetite, Risk Tolerance and Risk Capacity statements for a) the council as a whole b) Each Directorate or Project/Partnership c) each individual risk.
4.4The current risk appetite statement is that the Council is risk adverse. The existing statement does not take into account the need for the Council to be able to accept certain risks in relation to key projects within its Corporate Plan. Therefore, following review, the Officers propose to amend the current risk appetite statement to:
“The Council should normally seek to avoid significant risk taking. However, to facilitate the delivery of its Corporate Plan, there will, on occasion, be times where considered/quantified risk taking may be appropriate”.
4.5In addition, as part of our Strategy review, The Officers have developed a clearer statement that will differentiate between different types of risk for example: -
Risk Management Policy, Statement & Strategy /Executive/8th January 2025 7(2) a. Strategic – Risks that relate to the Councils overall Strategy, Vision and Corporate Plan b. Business – Risks that relate to executing the overall strategy, and day to day operations of the Council. Business risks are sub divided into 4 sub areas: (i) Operational, (ii) Opportunity, (iii) Project, (iv) Partnership
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.