Bedford Borough Council
Executive, Wednesday 7 January 2026 at 6.30pm

Improvement Plan

Approved Executive 3 papers

AI summaryBedford Borough Council Executive approves an Improvement Plan to support financial sustainability, the 2026/2027 budget, the Medium-Term Financial Strategy, and an Exceptional Financial Support application.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedWith new governance and oversight structures
MoneyNot stated
What happens nextChief Executive to produce delivery plansWith service dashboards and targets, as a matter of urgency
Who it affectsCouncil services and residentsThrough work to restore financial sustainability

What was decided

The Executive approved the Improvement Plan set out in Appendix A to support the 2026/2027 budget, ongoing delivery of the Medium-Term Financial Strategy, and an application for Exceptional Financial Support. Report P4

The Executive approved setting up an Improvement Plan Board of Executive Members to oversee delivery, and supported moving the Independent Improvement and Assurance Panel from informal to formal status. Report P5, P7, 5.8, 5.9

The Chief Executive was instructed to bring forward detailed delivery plans for each package, with service-specific dashboards, targets and performance measures, with progress reported through Member Briefings. Report P8, P9, 5.3

Why

The Council's financial position in 2025/2026 has been challenging, with significant pressures in temporary accommodation, adults' packages, children's placements and agency staff, and a significant gap is forecast over the MTFS period. Report 4.1

The Improvement Plan builds on the Stability Plan agreed by the Executive on 23 April 2025 and on the CIPFA Resilience Review approved by Executive Decision 1820 on 5 September 2025, which recommended a single Improvement Plan. Report 4.2

Strong oversight is needed through the Executive, with external challenge from an Independent Improvement and Assurance Board, and wider support from Full Council. Report 3.1, 5.7

What happens next

The Chief Executive will bring forward detailed delivery plans for each of the 9 packages, with service-specific dashboards, stretch targets and performance measures. Report P8, 5.3

Resource requirements will be built into the 2026/2027 and later capital and revenue budgets, and the Plan will support any request for Exceptional Financial Support. Report P29, P30, 5.5

Updates on delivery will be given through Member Briefings, with the new Executive Improvement Plan Board, a formal Independent Improvement and Assurance Panel, an internal Officer Improvement Leadership Team, and Overview and Scrutiny involvement providing oversight. Report P9, 5.7, 5.8, 5.9, 5.10, 5.11

Options considered

  • Rejected: Not to have an Improvement Plan. Given the Council's financial position there is a need for a consolidated Improvement Plan with clear governance structures. Report 6.1
  • Rejected: Not to have an Independent Improvement and Assurance Panel. The level of scrutiny from organisations such as the LGA and MHCLG makes an IIAP important. Report 6.2
  • Rejected: To delay the Improvement Plan. The Plan is needed to support the 2026/2027 budget and the MTFS position; delay would not give required assurance. Report 6.3

Implications

  • Legal: The Council has a legal duty to set a balanced budget; the Plan will assist development of budget proposals for 2026/2027 and the MTFS. Report 7.1
  • Financial: Resource implications of delivering the Plan will need to be built into the budget and into any application for Exceptional Financial Support. Report 7.3, 5.4
  • Risk: The key risk being managed is setting a sustainable financial framework; a more detailed risk assessment is attached as Appendix B. Report 7.4
  • Equalities: A more detailed Equalities Impact Assessment will be published to support the budget proposals. Report 7.6
  • Other: No specific implications identified for environment, families, community safety, or health and wellbeing, though the Plan links to wider financial sustainability which supports those areas. Report 7.5, 7.7, 7.8, P71

Who and where

  • Members and political group leaders supported by Local Government Association Peer Mentors
  • The Council's workforce, including Corporate Leadership Team leading improvement packages Report 5.10, P55
  • Service areas covered by Newton Consulting diagnostics, including Adult Services, Children's Services, Temporary Accommodation and wider corporate services Report 4.5
  • Council taxpayers and residents, through the impact on the Council's budget and services Report 7.1, 7.3

Timeline

  • 23 April 2025: Executive agreed a Stability Plan driving the current improvement approach. Report 4.2
  • 5 September 2025: Executive Decision 1820 approved the CIPFA Resilience Review, which recommended a single Improvement Plan. Report 4.2
  • 2025/2026: Financial pressures identified in temporary accommodation, adults' packages, children's placements and agency staff. Report 4.1
  • 7 January 2026: Executive considered this report and approved the Improvement Plan and its governance arrangements. Report P6
  • 2026/2027: Improvement Plan to support the budget and the MTFS, and any application for Exceptional Financial Support. Report P4, 4.6, 5.6

Plain English for the jargon

  • MTFS: Medium-Term Financial Strategy, the Council's multi-year financial planning framework.
  • LGA: Local Government Association, providing sector support and Peer Mentors.
  • IIAP: Independent Improvement and Assurance Panel, providing external oversight and challenge.
  • CIPFA: Chartered Institute of Public Finance and Accountancy, which produced the Resilience Review and is supporting the Improvement Plan.
  • MHCLG: Ministry for Housing, Communities and Local Government, a key external stakeholder receiving progress reports.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item67

Resolved

Description of Decision : (1) That the sector support being provided by the Local Government Association (LGA) in the Council’s journey be acknowledged. (2) That the set out in Appendix A to support the development of the 2026/2027 budget and the ongoing work on the delivery of the MTFS and in an application for Exceptional Financial Support be approved. (3) That the establishment of an Board of Executive Members to oversee the delivery of the be approved. (4) That the commitment to seeking support from Full Council on the delivery of the be confirmed. (5) That the arrangements for an independent Improvement and Assurance Panel (IIAP) to provide independent oversight and challenge to the delivery of the be supported. (6) That the Chief Executive be instructed to bring forward the detailed delivery plans for each of the packages as a matter of urgency, together with service specific dashboards with defined targets and performance measures that enable effective tracking and monitoring of performance and success consistent with the expected high performance, benchmarked service delivery critical to sustainable recovery and continuous improvement. (7) That it be confirmed that updates on the delivery of the will be made by Member Briefings. Reason for Decision To acknowledge the significant support received from the LGA in the current period. The has been developed to support the Council in addressing its current financial position. It is important that there is strong oversight and governance through Executive and with external oversight and challenge from an Independent Improvement and Assurance Board. It will also be important that there is wider support for the delivery of the by Full Council.
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Executive

Executive summary

1.1This report seeks approval of the Improvement Plan to support the Council’s journey to financial sustainability. It also sets out the approach to the governance of the Improvement Plan and the resources that will be required to deliver the plan.

Recommendations

2.1The Executive is recommended to consider and, if satisfied, to:

(1) Acknowledge the sector support being provided by the Local Government Association (LGA) in the Council’s Improvement Plan journey.

(2) Approve the Improvement Plan set out in Appendix A to support the development of the 2026/2027 budget and the ongoing work on the delivery of the MTFS and in an application for Exceptional Financial Support.

(3) Approve the establishment of an Improvement Plan Board of Executive Members to oversee the delivery of the Improvement Plan.

Improvement Plan/ Executive/7 January 2025 6(1) (4) Confirm the commitment to seeking support from Full Council on the delivery of the Improvement Plan.

(5) Support the arrangements for an independent Improvement and Assurance Panel (IIAP) to provide independent oversight and challenge to the delivery of the Improvement Plan.

(6) Instruct the Chief Executive to bring forward the detailed delivery plans for each of the packages as a matter of urgency, together with service specific dashboards with defined targets and performance measures that enable effective tracking and monitoring of performance and success consistent with the expected high performance, benchmarked service delivery critical to sustainable recovery and continuous improvement.

(7) Confirm that updates on the delivery of the Improvement Plan will be made by Member Briefings.

Reasons for recommendations

3.1The Council has received significant support from the LGA in the current period and this is acknowledged. The Improvement Plan has been developed to support the Council in addressing its current financial position. It will also be important that there is strong oversight and governance through Executive and with external oversight and challenge from an Independent Improvement and Assurance Board. It will also be important that there is wider support for the delivery of the Improvement Plan by Full Council.

4. THE CURRENT POSITION

4.1The Council’s financial position has been challenging during 2025/2026 with significant pressures in temporary accommodation, adults’ packages, children’s placements and agency staff. Actions have been taken in-year to mitigate some elements of overspending, but which have not yet brought about a balanced budget. The Council has also agreed a Medium-Term Financial Strategy which identifies, based on financial forecasts, a significant gap over the MTFS period. The MTFS will also need to reflect the impact of the Fairer Funding Reforms on the Council’s budget position.

4.2The Executive, on 23 April 2025, agreed a Stability Plan which has been driving the current approach to improvement. It reflected that there would be a need to update the Plan in light of the CIPFA Resilience Review which was approved by an Executive Decision 1820 on 5 September 2025. The CIPFA Review recommended that there was a single Improvement Plan for the Council, and this report reflects the progress that has been made.

Improvement Plan/ Executive/7 January 2025 6(2) 4.3 Given the financial position the Council has been receiving support from the Local Government Association (LGA) with Peer Mentors being put in place for the Mayor, Finance Portfolio Holder, Leader of the Conservative Group, Leader of the Liberal Democrat Group, Leader of the Labour Group, Green Group conveyor and a representative of the Independent Councillor.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Executive: 7 January 2025: Improvement Plan: Appendix AAppendix 550 KB Download
PDF
Executive: 7 January 2025: Improvement Plan: Appendix BAppendix 81 KB Download
PDF
Improvement PlanReport 134 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 19 attended
BF
Councillor Ben FoleyBorough Councillor, in attendance
MF
Councillor Marc FrostCommittee Member, present
SG
Councillor Sarah GallagherCommittee Member, present
NG
Councillor Nicola GribbleCommittee Member, present
MH
Councillor Michael HeadleyBorough Councillor, in attendance
ZL
Councillor Zara LayneBorough Councillor, in attendance
PM
Councillor Phillippa Martin-Moran-BryantCommittee Member, present
DM
Councillor Doug McMurdoBorough Councillor, in attendance
CM
Councillor Carl MeaderBorough Councillor, in attendance
SO
Councillor Sue OliverBorough Councillor, in attendance, virtual
RR
Councillor Robert RigbyCommittee Member, present
DS
Councillor Dylan SimmonsBorough Councillor, in attendance

All 19 on the meeting page

On this subject at Bedford

Search all
  1. Improvement PlanThis decision
  2. Corporate Improvement Plan ProgressNoted
  3. Progress on Improvement Plan SavingsNoted
  4. Procurement Initiatives and Improvement PlanDecided
  5. Adult Services Improvement PlanApproved
  6. Corporate Improvement Plan ProgressNoted

More from Bedford Executive

All decisions
MeetingDecisionOutcome
15 Jul 2026 Minutes of Previous MeetingDescription of Decision That the Minutes of the meeting of the Executive held on 3 June 2026 be confirmed. Reason for... Decided Open
15 Jul 2026 Local Government and Social Care Ombudsman Annual Review Letter 2025/2026Description of Decision That the Local Government and Social Care Ombudsman’s Annual Review letter for 2025/2026 for ... Noted Open
15 Jul 2026 RIPA Annual ReportDescription of Decision (1) That it be noted that, in the period 1 April 2025 to 31 March 2026, there were no applica... Noted Open
15 Jul 2026 Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026... Approved Open
15 Jul 2026 Corporate Plan 2024-2028 Performance Report year-end 2025/2026Description of Decision That the latest performance as outlined within the Key Indictor Performance Report at Appendi... Decided Open