Resolved
Description of Decision That the progress achieved in meeting the savings targets outlined in Appendix A, as well as the actions necessary to address the forecasted adverse budget variance of £1,731k from the £18,646k target, be noted. Reason for Decision To demonstrate robust governance and oversight of the Improvement Plan Savings Projects, which strengthens transparency and accountability. Regular scrutiny of progress against savings targets will support timely decision ? making and early identification of risks or slippage to enable mitigating action to be taken.