Finance and Improvement Committee, Wednesday 3 June 2026 at 6.30pm

Progress on Improvement Plan Savings

Noted Finance 3 papers

AI summaryFinance and Improvement Committee noted that the Council is forecast to miss its £18,646k 2026/2027 savings target by £1,626k, and called for the pace of change to be accelerated on the Council Tax Reduction Scheme and Special Area Charges proposals.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedVariance of £1,626k forecast against £18,646k savings target for 2026/2027
Money£1,626k shortfallAdverse variance against the £18,646k savings target for 2026/2027
What happens nextAccelerate pace of changeMembers want Council Tax Reduction Scheme and Special Area Charges proposals progressed
Who it affectsCouncil services and taxpayersRisks to delivery of 2026/2027 budget and improvement plan savings projects

What was decided

The Committee noted progress against the savings targets in Appendix A and the actions needed to address the £1,626k adverse variance from the £18,646k target. Report 2.1

The Committee noted that Members wish to see the pace of change accelerated.

The Council Tax Reduction Scheme and Special Area Charges proposals were identified as needing to be progressed.

Why

To demonstrate robust governance and oversight of the Improvement Plan Savings Projects, strengthening transparency and accountability. Report 3.1

Regular scrutiny of progress against savings targets supports timely decision-making and early identification of risks or slippage, enabling mitigating action. Report 3.2

A robust reporting framework manages and monitors progress, ensuring transparency on project status and allowing timely corrective action. Report 4.1

What happens next

Conclude consultations on Design and Print income opportunities by 31/05/26 and present options during June 2026, with delivery of a preferred option from August 2026 subject to decision. Report P24

Continue the THRIVE Trial and Iterate phase across four workstreams and validate early operational indicators of financial benefit. Report 5.6, P17

Finalise the Children's Services HR Business Case by June 2026 and start the HR process in Q2 to address the restructuring delay. Report P34

The money

  • £18,646k Total savings target for 2026/2027 Report 5.4
  • £17,020k Most recent forecast of savings against target Report 5.4
  • £1,626k Forecasted adverse budget variance against target Report 2.1, 5.4
  • c£8m Total savings realised to date Report 5.5
  • £2.6m Savings achieved in this reporting period Report 5.5
  • £1.3m Period savings from a review of vacancies removed from the establishment Report 5.5
  • £240k Savings realised by reducing the Ward Members' Fund allocation Report P19, 5.7
  • £100k Additional income from leasing spare office space at Borough Hall Report P20, 5.7
  • £162k Reduced staffing costs from the previous Voluntary Redundancy Programme Report P21, 5.7
  • £640k Savings from reductions on the Blue/White Peris, Kempston Outdoor Centre and Oasis leisure contracts Report P22, 5.7
  • £2.0m Savings target for the Children's Services, Temporary Accommodation and Corporate Services programmes Report P26
  • £0.7m Shortfall from the diagnostic exercise in 2026/2027 under review Report P28
  • £450k Anticipated shortfall in savings brought forward from 2025/2026 Report 5.9
  • £150k Overtime reduction element of the £450k brought-forward shortfall Report 5.9

Options considered

  • Rejected: Alternative reporting arrangements with less frequent or focused reporting. Insufficient frequency and focus to support oversight of savings delivery Report 6.1, P38

Implications

  • Risk: Failing to monitor projects would reduce transparency, limit Members' ability to intervene early, undermine accountability and damage public and stakeholder confidence. Report 7.4, P48
  • Financial: Several challenges in delivering savings are identified, with £1,626k adverse variance forecast and £450k carried forward from 2025/2026. Report 7.3, P46, 5.4, 5.9
  • Staffing: Children's Services restructuring is delayed, with the HR Business Case due by June 2026 and the HR process starting in Q2. Report P34

Who and where

  • Bedford Borough Council services and council taxpayers, through the impact of the £1,626k forecast savings shortfall Report 2.1, 5.4
  • Ward Members, with the Ward Members' Fund allocation reduced from £340k to £100k Report P19
  • Adult social care service users, affected by the THRIVE reablement changes including doubled reablement visits per support worker per day Report P17, 5.6
  • Children in care, subject to a review of care packages for potential shared funding with the Integrated Care Board Report P29, P31

Timeline

  • May 2026: Previous Financial Improvement Committee meeting Report 5.2
  • May 2026: Meeting scheduled to explore commissioning a former ICB link person to review existing packages of care Report P32
  • 8 May 2026: THRIVE Implementation call-off contract with Newton Consulting Ltd signed Report 5.6
  • 31/05/26: Deadline to conclude consultations on Design and Print income opportunities Report P24
  • June 2026: Present Design and Print options for consideration and finalise the Children's Services HR Business Case Report P24, P34
  • Q2 (2026/2027): Anticipated start of the Children's Services HR process Report P34
  • 01/06/26: Prioritise development of proposed options for the Design and Print service Report P24
  • August 2026: Mobilise delivery of a preferred Design and Print option, subject to informed decision-making Report P24

Plain English for the jargon

  • RAG rating: Red, Amber, Green status used to rate projects on delivery, cost, resources and savings progress
  • SRO: Senior Responsible Owner, accountable for raising delivery concerns
  • CLT: Corporate Leadership Team, which conducts monthly reviews of Savings Projects
  • THRIVE: Bedford Borough Council's Adults' Services Transformation Programme
  • CHC: Continuing Healthcare, the health funding arrangement relevant to children in care
  • ICB: Integrated Care Board, the NHS body the Council liaises with on shared funding for children in care
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

Description of Decision (1) That the progress achieved in meeting the savings targets outlined in Appendix A, as well as the actions necessary to address the forecasted adverse budget variance of £1,626k from the £18,646k target, be noted. (2) That it be noted that Members wish to see the pace of change accelerated and that the Council Tax Reduction Scheme and that the Special Area Charges proposals need to be progressed. Reason for Decision To demonstrate robust governance and oversight of the Improvement Plan Savings Projects, which strengthens transparency and accountability. Regular scrutiny of progress against savings targets will support timely decision ? making and early identification of risks or slippage to enable mitigating action to be taken.
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Finance and Improvement Committee

Executive summary

1.1This report outlines the progress toward achieving the Council’s Improvement Plan Savings targets and highlights the steps needed to meet the required savings for 2026/2027.

Recommendations

2.1The Committee is requested to review the progress achieved in meeting the savings targets outlined in Appendix A, as well as the actions necessary to address the forecasted adverse budget variance of £1,626k from the £18,646k target.

Reasons for recommendations

3.1The Council is required to demonstrate robust governance and oversight of its Improvement Plan Savings Projects, which strengthens transparency and accountability.

3.2Regular scrutiny of progress against savings targets will support timely decision‑making and early identification of risks or slippage to enable mitigating action to be taken.

8(1) 4. BACKGROUND

4.1As part of the Improvement Plan, a comprehensive range of savings proposals has been developed to support the Council in achieving financial sustainability. There is a robust reporting framework in place to effectively manage and monitor progress. This approach ensures transparency regarding the status of individual projects and allows for timely corrective actions when necessary. The Improvement Plan savings provide substantial targets for major projects, which require close oversight to ensure that the 2026/2027 budget stays on track while delivering future financial sustainability and improvements in governance.

4.2The Corporate Leadership Team conducts a monthly review of the Savings Projects, which is then followed by the Executive Improvement Plan Board. Each project is assigned a RAG rating based on delivery timelines, costs, resources, and progress toward financial savings.

4.3Escalation of savings that begin to slip or fall off track is initiated by the Head of Strategic Programmes and Senior Responsible Owners (SRO), who are accountable for raising concerns promptly and ensuring they are reported to the Corporate Leadership Team (CLT) and the Executive Improvement Plan Board. Red rated actions are subject to immediate scrutiny, discussed at senior leadership level, and escalated to the Executive Improvement Plan Board with oversight led by the Mayor. These actions must produce strengthened mitigation plans, undergo more frequent review cycles, and demonstrate measurable progress within agreed timeframes.

4.4For actions that remain Amber across multiple reporting periods, a formal escalation pathway is triggered: issues are first addressed by the Head of Strategic Programmes for corrective action, then escalated to the SRO and senior leadership team if risks persist. Continued lack of progress results in escalation to the Chief Executive and the Executive Improvement Plan Board, ensuring unresolved risks receive the highest level of oversight and that accountability for delivery is firmly maintained at the top of the organisation.

5. DETAILS

5.1Improvement Plan - Savings Dashboard – see appendix A

5.2There has been a limited gap between this meeting and the Financial Improvement Committee on the14 May 2026 and preparing papers for this meeting. A total of 76 savings proposals were approved during the 2026/2027 budget setting process. Of these, 36 are considered inflight projects, 1 has not yet begun, and 39 are categorised as non- projects. 8(2) 5.3 Non-projects (budget adjustments) are primarily a financial transaction with minimal or no deliverables associated with benefit realisation. These are managed by the service and finance as part of the monthly financial budget monitoring process.

5.4The total savings target for 2026/2027 stands at £18,646k, with 16% rated as Red, 34% as Amber, and 50% as Green or non-projects. The most recent forecast projects savings of £17,020k against this target, resulting in a variance of £1,626k.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 08 Appendix A: Savings DashboardAppendix 524 KB Download
PDF
Item 08 Appendix B: Reablement UpdateAppendix 222 KB Download
PDF
Progress on Improvement Plan SavingsReport 130 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 13 attended
LB
Councillor Lucy BywaterObserver, in attendance
GC
Councillor Graeme CoombesCommittee Member, apologies
MF
Councillor Marc FrostCommittee Member, present
MH
Councillor Michael HeadleyObserver, in attendance
DM
Councillor Doug McMurdoCommittee Member, present
DS
Councillor Dylan SimmonsObserver, in attendance
AS
Councillor Abu SultanCommittee Member, present
MT
Councillor Martin TowlerCommittee Member, present
HV
Councillor Henry VannCommittee Member, present
JW
Councillor Jane WalkerCommittee Member, present
JW
Councillor James WeirCommittee Member, present
JW
Councillor John WheelerObserver, in attendance

All 13 on the meeting page

On this subject at Bedford

Search all
  1. Progress on Improvement Plan SavingsThis decision
  2. Corporate Improvement Plan ProgressNoted
  3. Progress on Improvement Plan SavingsNoted
  4. Corporate Improvement Plan ProgressNoted
  5. Corporate Improvement Plan ProgressDecided
  6. Progress on Improvement Plan SavingsNoted

More from Bedford Finance and Improvement Committee

All decisions
MeetingDecisionOutcome
15 Jul 2026 Minutes of Previous MeetingDescription of Decision That the Minutes of the meeting of the Committee held on 3 June 2026 be confirmed. Reason for... Decided Open
15 Jul 2026 Corporate Improvement Plan ProgressDescription of Decision (1) That the advice from the Independent Assurance and Improvement Panel be noted. (2) That t... Noted Open
15 Jul 2026 Progress on Improvement Plan SavingsDescription of Decision That the progress achieved in meeting the savings targets outlined in Appendix A, as well as ... Noted Open
15 Jul 2026 Work ProgrammeDescription of Decision That the work programme be received. Reason for Decision To enable the Committee to consider ... Decided Open