It was therefore agreed last year that the Council would commission consultants to – - examine the potential added value and regeneration impact of the proposed stadia upgrades; and - identify practical opportunities where it might add value to the developments, and to explore how its future investments, resources and assets might be configured to align with the construction of the new stadia and secure optimum social outcomes and community benefits. The scope of this work was limited to the investment in Casement Park and Windsor Park given the proximity of the Council’s leisure assets to these stadia. Following a competitive tendering process Deloitte were appointed to progress this work. 1.6 It should be noted that this work is being undertaken in parallel to the work which is being progressed by the sport’s governing bodies (IFA and GAA) on the development of their business case proposals and the work on the development and design of the stadia themselves. Sport NI, as part of the of the consultation for the Deloitte report, highlighted that the funding for the redevelopments of the stadia is committed under this CSR round and there is a very finite ‘window of opportunity’ in which the Council can input into the design process – in terms of, for example, the integration into the surrounding area and provision of services etc. DCAL highlighted their support for the wider regeneration of ... view the full minutes text for item 16a
Word for word from the decision Belfast published for this meeting.Source: minutes.belfastcity.gov.uk
Report to Pre April-2015 Strategic Policy and Resources Committee
Report to: Strategic Policy & Resources Committee Subject: Investment Programme: Stadia Upgrades – Windsor and Casement Parks Date: 22 June 2012 Reporting Officer: Gerry Millar, Director of Property & Projects Andrew Hassard, Director of Parks & Leisure Contact Officer: Cathy Reynolds (Ext 3497) Sinead Grimes (Ext. 6203)
1.0Background and relevant information
1.1Members will be aware that last year the NI Executive committed significant investment towards local sports facilities including - £61.4m to the IFA (of which £25.2m will go towards the redevelopment of Windsor Park), £61.4m to the GAA for the redevelopment of Casement Park and £15million to the IRFU towards the upgrade of Ravenhill. The respective sporting governing bodies are also expected to provide additional substantial funding of their own towards facilities upgrades. The governing bodies are now in the process of developing full business cases for their respective projects. 1.2 The Council owns a number of leisure assets in the immediate vicinity and surrounding areas of both Windsor Park and Casement Park. These include - - Windsor Park – Olympia Leisure Centre/Community Centre, Boucher Road Playing Fields, head landlord for majority of Boucher Road Estate - Casement Park – Andersonstown Leisure Centre, North Link Playing Fields 1.3 Council related projects aligned to the stadia upgrades are highlighted as emerging projects in the Council’s Investment Programme 2012-2015. In addition, a comprehensive review of the Council’s leisure estate is also a key project under the Investment Programme. 1.4 The Council therefore regarded it as important that these stadia developments and investments were not viewed in isolation but rather that the full regeneration impacts, added value of and synergies between the developments was examined. This will have the potential to help build critical mass, lever further infrastructure investment, engender greater public interest and potentially generate greater economic, social and physical regeneration outcomes for the city. 1.5 It was therefore agreed last year that the Council would commission consultants to - - examine the potential added value and regeneration impact of the proposed stadia upgrades; and - identify practical opportunities where it might add value to the developments, and to explore how its future investments, resources and assets might be configured to align with the construction of the new stadia and secure optimum social outcomes and community benefits. The scope of this work was limited to the investment in Casement Park and Windsor Park given the proximity of the Council’s leisure assets to these stadia. Following a competitive tendering process Deloitte were appointed to progress this work. 1.6 It should be noted that this work is being undertaken in parallel to the work which is being progressed by the sport’s governing bodies (IFA and GAA) on the development of their business case proposals and the work on the development and design of the stadia themselves. Sport NI, as part of the of the consultation for the Deloitte report, highlighted that the funding for the redevelopments of the stadia is committed under this CSR round and there is a very finite ‘window of opportunity’ in which the Council can input into the design process – in terms of, for example, the integration into the surrounding area and provision of services etc. DCAL highlighted their support for the wider regeneration of the stadia areas but it was made clear that the stadia projects have fixed budgets and fixed timescales under which the money has to be spent.
2.0Key issues
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Pre April-2015 Strategic Policy and Resources Committee at Belfast and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.