Belfast City Council

Stadia Upgrades - Windsor and Casement Parks

Agreed Committee 2 papers

Pre April-2015 Strategic Policy and Resources Committee agreed this item on Friday 22 June 2012. Below is the council's own wording, with the papers it was decided on.

Item16a

Resolved

It was therefore agreed last year that the Council would commission consultants to – - examine the potential added value and regeneration impact of the proposed stadia upgrades; and - identify practical opportunities where it might add value to the developments, and to explore how its future investments, resources and assets might be configured to align with the construction of the new stadia and secure optimum social outcomes and community benefits. The scope of this work was limited to the investment in Casement Park and Windsor Park given the proximity of the Council’s leisure assets to these stadia. Following a competitive tendering process Deloitte were appointed to progress this work. 1.6 It should be noted that this work is being undertaken in parallel to the work which is being progressed by the sport’s governing bodies (IFA and GAA) on the development of their business case proposals and the work on the development and design of the stadia themselves. Sport NI, as part of the of the consultation for the Deloitte report, highlighted that the funding for the redevelopments of the stadia is committed under this CSR round and there is a very finite ‘window of opportunity’ in which the Council can input into the design process – in terms of, for example, the integration into the surrounding area and provision of services etc. DCAL highlighted their support for the wider regeneration of ... view the full minutes text for item 16a
Word for word from the decision Belfast published for this meeting. Source: minutes.belfastcity.gov.uk

Follow this further

Built from Belfast's papers

What the report saysPro

Report to Pre April-2015 Strategic Policy and Resources Committee

Report to: Strategic Policy & Resources Committee Subject: Investment Programme: Stadia Upgrades – Windsor and Casement Parks Date: 22 June 2012 Reporting Officer: Gerry Millar, Director of Property & Projects Andrew Hassard, Director of Parks & Leisure Contact Officer: Cathy Reynolds (Ext 3497) Sinead Grimes (Ext. 6203)

1.0Background and relevant information

1.1Members will be aware that last year the NI Executive committed significant investment towards local sports facilities including - £61.4m to the IFA (of which £25.2m will go towards the redevelopment of Windsor Park), £61.4m to the GAA for the redevelopment of Casement Park and £15million to the IRFU towards the upgrade of Ravenhill. The respective sporting governing bodies are also expected to provide additional substantial funding of their own towards facilities upgrades. The governing bodies are now in the process of developing full business cases for their respective projects. 1.2 The Council owns a number of leisure assets in the immediate vicinity and surrounding areas of both Windsor Park and Casement Park. These include - - Windsor Park – Olympia Leisure Centre/Community Centre, Boucher Road Playing Fields, head landlord for majority of Boucher Road Estate - Casement Park – Andersonstown Leisure Centre, North Link Playing Fields 1.3 Council related projects aligned to the stadia upgrades are highlighted as emerging projects in the Council’s Investment Programme 2012-2015. In addition, a comprehensive review of the Council’s leisure estate is also a key project under the Investment Programme. 1.4 The Council therefore regarded it as important that these stadia developments and investments were not viewed in isolation but rather that the full regeneration impacts, added value of and synergies between the developments was examined. This will have the potential to help build critical mass, lever further infrastructure investment, engender greater public interest and potentially generate greater economic, social and physical regeneration outcomes for the city. 1.5 It was therefore agreed last year that the Council would commission consultants to - - examine the potential added value and regeneration impact of the proposed stadia upgrades; and - identify practical opportunities where it might add value to the developments, and to explore how its future investments, resources and assets might be configured to align with the construction of the new stadia and secure optimum social outcomes and community benefits. The scope of this work was limited to the investment in Casement Park and Windsor Park given the proximity of the Council’s leisure assets to these stadia. Following a competitive tendering process Deloitte were appointed to progress this work. 1.6 It should be noted that this work is being undertaken in parallel to the work which is being progressed by the sport’s governing bodies (IFA and GAA) on the development of their business case proposals and the work on the development and design of the stadia themselves. Sport NI, as part of the of the consultation for the Deloitte report, highlighted that the funding for the redevelopments of the stadia is committed under this CSR round and there is a very finite ‘window of opportunity’ in which the Council can input into the design process – in terms of, for example, the integration into the surrounding area and provision of services etc. DCAL highlighted their support for the wider regeneration of the stadia areas but it was made clear that the stadia projects have fixed budgets and fixed timescales under which the money has to be spent.

2.0Key issues

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Stadia Upgrades Olympia LC Windsor Stadium MapAppendix 1 273 KB Download
PDF
Stadia Upgrades: Windsor and Casement ParksMinutes 152 KB DownloadRead as text

More from Belfast Pre April-2015 Strategic Policy and Resources Committee

All decisions
MeetingDecisionOutcome
23 Jan 2015 Flood Alleviation in BelfastIt was agreed that this work would be undertaken by the Council in conjunction with the three main drainage agencies;... Agreed Open
19 Sep 2014 Request to Participate in Cinemagic InitiativeResolved – That the Committee agrees to approve expenditure of £6,500 for the aforementioned event under Section 37 o... Agreed Open
22 Aug 2014 Working GroupsIt was agreed also to review the number and role of the existing working groups to take account of the dual governanc... Agreed Open
22 Aug 2014 NI Street League FundingResolved - That the Committee agrees that expenditure of £4,400 in respect of the aforementioned event be approved un... Agreed Open
19 Jun 2014 Request for Funding – Common Purpose BelfastResolved – That expenditure in the sum of £6,000 be approved for the aforementioned Programme under Section 37 of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies