RECOMMENDATION TO COUNCIL (1) That, subject to (3) below, the proposed financial arrangements and capital investment strategy for the ten year term of the Enderby Leisure Centre and Golf Course Contract identified as Option 3 in the report of the Strategic Director & Deputy Chief Executive and Interim Head of Community Development be approved, (2) that the Cabinet Executive notes that a report elsewhere on this agenda makes recommendations that, as part of the arrangements, the Council will be using the Prudential Borrowing facility as part of the budget and policy framework to provide both the initial tranche of capital funding, estimated at £965,000, and subject to the future availability of capital resources, the capital funding required in years 8, 9 and 10 of the ten year contract period, and (3) that, subject to satisfactory legal assurances on vires, the Council enter into a contract with Sports and Leisure Management on the basis of the recommendation set out in the report of the Strategic Director & Deputy Chief Executive and Interim Head of Community Development. Reason for Decision : In order to facilitate the required level of investment in the Enderby Leisure Centre and to achieve a satisfactory financial arrangement in terms of the proposed contract a number of capital financing structures have been examined. Option 3, which requires the Council to fund the capital investment using PWLB funding, provides the Council with the maximum financial benefit in the early years of the contract and allows for greater control over the capital investment.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
# The financing costs shown include a proportion of the fees that SLM will have to pay for other investments into the site that are not part of the major capital programme that is under consideration. These items include new fitness equipment and new IT equipment. CAPITAL INVESTMENT OPTIONS FOR INVESTMENT AT ENDERBY LEISURE CENTRE APPENDIX B
Option One
SLM fund the initial Investment and BDC fund the investment required in years 8,9 and 10 (BDC borrow full £321,000 as 3 year annuity in year 8).
Year 1 2 3 4 5 6 7 8 9 10 Total
SLM capital Investment 965,000 BDC Capital Investment 107,000 107,000 107,000
Amount of Financing fund required by SLM 193590 193590 193590 193590 193590 193590 193590 193590 193590 193590 Balance available to fund borrowing 0 0 0 0 0 0 0 0 0 0
Cost to Council of borrowing 0 0 0 0 0 0 0 -115,000 -115,000 -115,000 Income from SLM (Surplus Finance money) 0 0 0 0 0 0 0 0 0 0 Management Fee from SLM 26,000 26,000 26,000 26,000 26,000 60,000 60,000 60,000 60,000 60,000 430,000 Total received by BDC 26,000 26,000 26,000 26,000 26,000 60,000 60,000 -55,000 -55,000 -55,000 85,000
Advantages SLM carry the risk of borrowing and any control costs for the project work The additional costs are deferred for 7 years
Disadvantages BDC have less control over expenditure BDC are less likely to consider putting the future investment in early if that was deemed necessary. The higher borrowing costs for SLM affect the bottom line over the full term of the contract. BDC receive no additional income to compensate for accepting liability for the year 8,9 and 10 investment CAPITAL INVESTMENT OPTIONS FOR INVESTMENT AT ENDERBY LEISURE CENTRE APPENDIX C Option Two
BDC fund the initial Investment and SLM fund the investment required in years 8,9 and 10
Year 1 2 3 4 5 6 7 8 9 10 Total
SLM capital Investment 107,000 107,000 107,000 BDC Capital Investment 965,000
Amount of Financing fund required by SLM 66282 66282 66282 66282 66282 66282 66282 66282 66282 66282 662820 Balance available to fund borrowing 127243 127243 127243 127243 127243 127243 127243 127243 127243 127243 1272430
Cost to Council of borrowing -120,000 -120,000 -120,000 -120,000 -120,000 -120,000 -120,000 -120,000 -120,000 -120,000 -1200000 Income from SLM (Surplus Finance money) 127,243 127,243 127,243 127,243 127,243 127,243 127,243 127,243 127,243 127,243 1272430 Management Fee 26,000 26,000 26,000 26,000 26,000 60,000 60,000 60,000 60,000 60,000 430000 Total received by BDC 33,243 33,243 33,243 33,243 33,243 67,243 67,243 67,243 67,243 67,243 502430
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.