Cabinet Executive, Monday 21 September 2026

Quarter 1 Capital Programme Review 2026-27

Approved Executive 3 papers

AI summaryBlaby District Council's Cabinet Executive has recommended a revised 2026/27 Capital Programme of £8,538,488 to full Council, up from £5,066,684 after carrying forward £3,445,644 of unspent 2025/26 budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCabinet asks Council to accept report and revised programme
Money£8,538,488Total for revised 2026/27 capital programme
What happens nextFull Council to decideCabinet recommendations go to Council
Who it affectsCouncil capital budgets and projectsSpans housing, vehicles, leisure, IT and grants

What was decided

The Cabinet Executive asked full Council to accept the report.

The Cabinet Executive asked full Council to approve the latest 2026/27 Capital Programme, totalling £8,538,488. Report P5

Why

To make sure the Council has adequate resources in place to meet its capital spending commitments.

To reflect additions and other changes since the original programme was approved on 24th February 2026, including the carry forward of £3,445,644 of unspent 2025/26 budget. Report P1, P8

What happens next

Full Council will consider the Cabinet's recommendations at a future meeting.

Officers will continue to monitor spend against the revised programme and report variances to councillors, with projects deferred or removed if they cannot be afforded. Report P36

EV charging at the Council Depot and 12 chargers at Enderby Leisure Centre are due to be completed by 31st March 2027 and end of September 2026 respectively, and five further food waste vehicles are due by September 2026. Report P23, P24, P26

The money

  • £8,538,488 Latest 2026/27 Capital Programme total Report P5
  • £5,066,684 Original 2026/27 Capital Programme approved on 24th February 2026 Report P1
  • £3,445,644 Incomplete schemes carried forward from 2025/26 Report P3, P8
  • £2,627,099 Borrowing requirement within the original programme Report P1
  • £1,179,492 Capital spend by the end of June 2026 Report 4.2
  • £3,468,609 Planned Strategic Regeneration Property spend not yet used (deposits paid for properties at Little Glen and Countesthorpe) Report P20
  • £25,000 New pilot Business Grant Scheme (Business Growth and Decarbonisation plus Shop Front Improvements) Report P3, P12
  • £607k Set aside from the carry forward to buy properties easing demand for temporary accommodation Report P9

Options considered

  • Chosen: Accept the revised Capital Programme at £8,538,488. No other options were put forward by the report author Report 8.1

Implications

  • Risk: Risks of cost overruns and rising inflation are to be managed through ongoing monitoring, with price rises outside normal tolerances to be reported back to Council before works proceed; unaffordable projects may be deferred or removed. Report P36
  • Equalities: No Equalities Impact Assessment was required for this report and no concerns were identified on Human Rights, legal, HR or public health inequality grounds. Report P30, P31
  • Climate: No Net Zero and Climate Impact Assessment was required for this report, although EV infrastructure, food waste vehicles and the Business Grant decarbonisation strand are part of the programme. Report 5.1, P10, P11, P12, P24

Who and where

  • Residents needing temporary accommodation, with £607k earmarked to buy properties in the district Report P9
  • Micro businesses that may apply to the new pilot Business Grant Scheme (£20k Business Growth and Decarbonisation, £5k Shop Front Improvements) Report P12
  • Disabled residents waiting for home adaptations, as the Lightbulb service is under review to speed up DFG completions Report P21
  • Householders receiving the food waste service, as five further collection vehicles are due to be delivered by September 2026 Report P10, P23
  • Users of Enderby Leisure Centre, with planned volleyball flooring and EV charging upgrades Report P13, P26
  • Parish councils and community groups that can bid for Section 106 backed schemes Report P14

Timeline

  • 1st July 2025: IT transition completed Report P27
  • December 2025: Groundworks began on EV infrastructure at the Council Depot Report P24
  • 23rd February 2026: Cabinet Executive approved the 2026/27 Business Grant Scheme Report P12
  • 24th February 2026: Council approved the original 2026/27 Capital Programme Report P1
  • March 2026: Food waste service rolled out across the district Report P10
  • End of June 2026: £1,179,492 spent against the planned Capital Programme Report 4.2
  • End of September 2026: Five remaining food waste vehicles and 12 EV chargers at Enderby Leisure Centre due to be installed Report P23, P26
  • 31st March 2027: EV infrastructure at the Council Depot expected to be completed within budget Report P24
  • 2027: Walk & Ride Blaby final works expected to complete (Blaby's allocation is contingency) Report P28
  • 2027/28: New road sweeper on the Fleet Vehicle Replacement Programme due to be delivered Report P22

Plain English for the jargon

  • DFG: Disabled Facilities Grants, used to fund home adaptations for disabled residents
  • Section 106 (S106): Developer contributions used to fund community infrastructure, released when the Planning Obligations Monitoring Group approves bids
  • NZCIA: Net Zero and Climate Impact Assessment, the council's climate screening tool
  • Lightbulb: A Leicestershire partnership service that delivers disabled home adaptations on behalf of the council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2026/27, totalling £8,538,488, be accepted. Reasons: 1. To ensure that the Council has adequate resources in place to meet its capital expenditure commitments. 2. To reflect additions or other changes to the Capital Programme since it was approved by Council on 24th February 2026, including the carry forward of unspent budget from 2025/26.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Cabinet Executive

Background

The original Capital Programme for 2026/27 was approved by Council on 24th February 2026 and totalled £5,066,684, including a borrowing requirement of £2,627,099. After allowing for unspent budget carried forward from 2025/26 and other movements, the Capital Programme now stands at £8,538,488. The movements between the original value and the latest value are shown in the following table, Appendix A gives a scheme-by-scheme breakdown of the planned expenditure for 2026/27.

£ Original Capital Programme – approved February 2026 5,066,884

New Additions 1. Incomplete schemes brought forward from 2025/26 3,445,644 2. Business Grant Scheme 25,000 3. Huncote Leisure Centre Volleyball Flooring 16,000 4. Section 106 backed schemes 960 5. Crow Mills Access Improvements 500

Reductions 6. Walk & Ride Blaby (16,000) 7. Food Waste Vehicles and Receptacles (500)

Revised Capital Programme 2026/27 8,538,488

The reasons behind the additions and reductions highlighted in the table above are as follows:

New Additions

1. Reflects schemes that were not finalised at 31st March 2026 amounting to £3,445,644 and the budget provision, along with associated resources which were carried over into the new financial year to allow for the projects be completed. This includes:

- £607k towards the purchase of properties to ease the pressure on the demand for temporary accommodation within the district;

- £553k for the purchase of 5 new food waste vehicles that are yet to be delivered. The food waste service was successfully rolled out in March 2026;

- £451k provision for the installation of electric vehicle infrastructure at the Council Depot.

2. Business Grant Scheme – the scheme will offer small grants to micro businesses. The grant will be used for a range of improvements that will enable the businesses to grow. As this is the first time Blaby District Council has established a business grant scheme, the scheme will operate as a pilot for the first year. The £25k is allocated across two primary application routes – Business Growth and Decarbonisation Grant (£20k) and Shop Front Improvements Grant (£5k). This will be funded from existing budgets and does not require new Council Investment. The grants will be administered by the Grants panel, which includes Elected Members and Officers. The 2026/27 Business Grant Scheme was approved by Cabinet Executive on 23rd February 2026.

3. Huncote Leisure Centre Volleyball Flooring - the Councils contribution towards the refurbishment of the main sports hall flooring, to enable the hosting of competition standard Volleyball. Existing budget has been transferred from the Walk & Ride Blaby capital project.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Monitoring Statement to 30th June 2026Appendix A 130 KB Download
PDF
Capital Forecasting Statement to 30th June 2026Appendix B 106 KB Download
PDF
Quarter 1 Capital Programme Review 2026-27Report 135 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 15 attended
BT
Councillor Ben TaylorLeader, present
CC
Councillor Cheryl CashmoreDeputy Leader, present
NC
Councillor Nick ChapmanMember, present
SF
Councillor Susan FindlayMember, present
NG
Councillor Nigel GrundyMember, present
MS
Councillor Mike ShirleyMember, present
NB
Councillor Nick BrownMember, in attendance
NW
Councillor Neil WrightMember, in attendance
JS
Julia SmithOfficer, in attendance
SP
Sarah PennelliOfficer, in attendance
LH
Louisa HortonOfficer, in attendance
MG
Marc GreenwoodOfficer, in attendance

All 15 on the meeting page

On this subject at Blaby

Search all
  1. Quarter 1 Capital Programme Review 2026-27This decision
  2. Quarter 3 Capital Programme Review 2025/26Approved
  3. Quarter 1 Capital Programme Review 2025/26Approved
  4. Quarter 3 Capital Programme Review 2024/25Decided
  5. Quarter 2 Capital Programme Review 2024/25Decided
  6. Quarter 1 Capital Programme Review 2024/25Approved

More from Blaby Cabinet Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Quarter 1 Budget ReviewDECISIONS 1. That the financial performance against the budget for the quarter ending 30th June 2026 be accepted. 2. ... Approved Open
21 Sep 2026 Risk Management StrategyDECISION That the revised be adopted. Reasons: 1. The should be subject to regular review to ensure that it reflects ... Approved Open
21 Sep 2026 Quarter 1 Treasury Management Update 2026-27RECOMMENDATIONS TO COUNCIL 1. That the latest position in respect of treasury activities, and the prudential indicato... Approved Open
29 Jun 2026 Update on Local Government Reorganisation and Establishment of voluntary Joint CommitteesDECISIONS 1. That the current position regarding Local Government Reorganisation in Leicester, Leicestershire and Rut... Noted Open
29 Jun 2026 Annual Governance Statement 2025/26DECISIONS 1. That the Annual Governance statement in respect of 2025/26 financial year, be approved. 2. That the upda... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies