AI summaryBlaby District Council's Cabinet Executive has recommended a revised 2026/27 Capital Programme of £8,538,488 to full Council, up from £5,066,684 after carrying forward £3,445,644 of unspent 2025/26 budget.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCabinet asks Council to accept report and revised programme
Money£8,538,488Total for revised 2026/27 capital programme
What happens nextFull Council to decideCabinet recommendations go to Council
Who it affectsCouncil capital budgets and projectsSpans housing, vehicles, leisure, IT and grants
What was decided
The Cabinet Executive asked full Council to accept the report.
The Cabinet Executive asked full Council to approve the latest 2026/27 Capital Programme, totalling £8,538,488. Report P5
Why
To make sure the Council has adequate resources in place to meet its capital spending commitments.
To reflect additions and other changes since the original programme was approved on 24th February 2026, including the carry forward of £3,445,644 of unspent 2025/26 budget. Report P1, P8
What happens next
Full Council will consider the Cabinet's recommendations at a future meeting.
Officers will continue to monitor spend against the revised programme and report variances to councillors, with projects deferred or removed if they cannot be afforded. Report P36
EV charging at the Council Depot and 12 chargers at Enderby Leisure Centre are due to be completed by 31st March 2027 and end of September 2026 respectively, and five further food waste vehicles are due by September 2026. Report P23, P24, P26
The money
£8,538,488 Latest 2026/27 Capital Programme total Report P5
£5,066,684 Original 2026/27 Capital Programme approved on 24th February 2026 Report P1
£3,445,644 Incomplete schemes carried forward from 2025/26 Report P3, P8
£2,627,099 Borrowing requirement within the original programme Report P1
£1,179,492 Capital spend by the end of June 2026 Report 4.2
£3,468,609 Planned Strategic Regeneration Property spend not yet used (deposits paid for properties at Little Glen and Countesthorpe) Report P20
£25,000 New pilot Business Grant Scheme (Business Growth and Decarbonisation plus Shop Front Improvements) Report P3, P12
£607k Set aside from the carry forward to buy properties easing demand for temporary accommodation Report P9
Options considered
Chosen: Accept the revised Capital Programme at £8,538,488. No other options were put forward by the report author Report 8.1
Implications
Risk: Risks of cost overruns and rising inflation are to be managed through ongoing monitoring, with price rises outside normal tolerances to be reported back to Council before works proceed; unaffordable projects may be deferred or removed. Report P36
Equalities: No Equalities Impact Assessment was required for this report and no concerns were identified on Human Rights, legal, HR or public health inequality grounds. Report P30, P31
Climate: No Net Zero and Climate Impact Assessment was required for this report, although EV infrastructure, food waste vehicles and the Business Grant decarbonisation strand are part of the programme. Report 5.1, P10, P11, P12, P24
Who and where
Residents needing temporary accommodation, with £607k earmarked to buy properties in the district Report P9
Micro businesses that may apply to the new pilot Business Grant Scheme (£20k Business Growth and Decarbonisation, £5k Shop Front Improvements) Report P12
Disabled residents waiting for home adaptations, as the Lightbulb service is under review to speed up DFG completions Report P21
Householders receiving the food waste service, as five further collection vehicles are due to be delivered by September 2026 Report P10, P23
Users of Enderby Leisure Centre, with planned volleyball flooring and EV charging upgrades Report P13, P26
Parish councils and community groups that can bid for Section 106 backed schemes Report P14
Timeline
1st July 2025: IT transition completed Report P27
December 2025: Groundworks began on EV infrastructure at the Council Depot Report P24
23rd February 2026: Cabinet Executive approved the 2026/27 Business Grant Scheme Report P12
24th February 2026: Council approved the original 2026/27 Capital Programme Report P1
March 2026: Food waste service rolled out across the district Report P10
End of June 2026: £1,179,492 spent against the planned Capital Programme Report 4.2
End of September 2026: Five remaining food waste vehicles and 12 EV chargers at Enderby Leisure Centre due to be installed Report P23, P26
31st March 2027: EV infrastructure at the Council Depot expected to be completed within budget Report P24
2027: Walk & Ride Blaby final works expected to complete (Blaby's allocation is contingency) Report P28
2027/28: New road sweeper on the Fleet Vehicle Replacement Programme due to be delivered Report P22
Plain English for the jargon
DFG: Disabled Facilities Grants, used to fund home adaptations for disabled residents
Section 106 (S106): Developer contributions used to fund community infrastructure, released when the Planning Obligations Monitoring Group approves bids
NZCIA: Net Zero and Climate Impact Assessment, the council's climate screening tool
Lightbulb: A Leicestershire partnership service that delivers disabled home adaptations on behalf of the council
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2026/27, totalling £8,538,488, be accepted. Reasons: 1. To ensure that the Council has adequate resources in place to meet its capital expenditure commitments. 2. To reflect additions or other changes to the Capital Programme since it was approved by Council on 24th February 2026, including the carry forward of unspent budget from 2025/26.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
The original Capital Programme for 2026/27 was approved by Council on 24th February 2026 and totalled £5,066,684, including a borrowing requirement of £2,627,099. After allowing for unspent budget carried forward from 2025/26 and other movements, the Capital Programme now stands at £8,538,488. The movements between the original value and the latest value are shown in the following table, Appendix A gives a scheme-by-scheme breakdown of the planned expenditure for 2026/27.
£ Original Capital Programme – approved February 2026 5,066,884
New Additions 1. Incomplete schemes brought forward from 2025/26 3,445,644 2. Business Grant Scheme 25,000 3. Huncote Leisure Centre Volleyball Flooring 16,000 4. Section 106 backed schemes 960 5. Crow Mills Access Improvements 500
Reductions 6. Walk & Ride Blaby (16,000) 7. Food Waste Vehicles and Receptacles (500)
Revised Capital Programme 2026/27 8,538,488
The reasons behind the additions and reductions highlighted in the table above are as follows:
New Additions
1. Reflects schemes that were not finalised at 31st March 2026 amounting to £3,445,644 and the budget provision, along with associated resources which were carried over into the new financial year to allow for the projects be completed. This includes:
- £607k towards the purchase of properties to ease the pressure on the demand for temporary accommodation within the district;
- £553k for the purchase of 5 new food waste vehicles that are yet to be delivered. The food waste service was successfully rolled out in March 2026;
- £451k provision for the installation of electric vehicle infrastructure at the Council Depot.
2. Business Grant Scheme – the scheme will offer small grants to micro businesses. The grant will be used for a range of improvements that will enable the businesses to grow. As this is the first time Blaby District Council has established a business grant scheme, the scheme will operate as a pilot for the first year. The £25k is allocated across two primary application routes – Business Growth and Decarbonisation Grant (£20k) and Shop Front Improvements Grant (£5k). This will be funded from existing budgets and does not require new Council Investment. The grants will be administered by the Grants panel, which includes Elected Members and Officers. The 2026/27 Business Grant Scheme was approved by Cabinet Executive on 23rd February 2026.
3. Huncote Leisure Centre Volleyball Flooring - the Councils contribution towards the refurbishment of the main sports hall flooring, to enable the hosting of competition standard Volleyball. Existing budget has been transferred from the Walk & Ride Blaby capital project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Annual Governance Statement 2025/26DECISIONS 1. That the Annual Governance statement in respect of 2025/26 financial year, be approved. 2. That the upda...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.