DECISION (1) To negotiate with the current contractor (William Freer Ltd) to extend the contract for a period of six months (1 April – 31 October 2006) during which time to carry out a tendering exercise to procure a contractor for the following three years, under a partnering arrangement for the Gas Appliance Servicing contracts. (2) To negotiate with the existing maintenance Contractor (Pratt and Chesterton Ltd) to extend the Electrical Maintenance contract for a period of six months (1 April 2006-31 October 2006) during which time to carry out the same tendering exercise as detailed above. Reason for Decision : To ensure a Housing Gas Appliance Servicing Contract is in place as at 1 st April to enable the authority to meet its landlord obligations . To facilitate the procurement of an improved three year contract at the end of these interim contract arrangements
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
1.1This report informs Cabinet Executive of the current status of the Housing Gas Appliance Servicing and Electrical Maintenance contracts and makes recommendations for future procurement of the contracts.
Recommendation
2. 1 To negotiate with the current contractor (William Freer Ltd) to extend the contract for a period of six months (1 April – 31 October 2006) during which time to carry out a tendering exercise to procure a contractor for the following three years, under a partnering arrangement for the Gas Appliance Servicing contracts.
2.2To negotiate with the existing maintenance Contractor (Pratt and Chesterton Ltd) to extend the Electrical Maintenance contract for a period of six months (1 April 2006-31 October 2006) during which time to carry out the same tendering exercise as detailed above.
3. Reasons for Decision Recommended
3.1• To ensure a Housing Gas Appliance Servicing Contract is in place as at 1st April to enable the authority to meet its landlord obligations • To facilitate the procurement of an improved three year contract at the end of these interim contract arrangements 4. Forward Plan
4.1This report has not been included in the last Forward Plan. It is a key decision. The matter has become apparent since the publication of the Forward Plan and because the authority will be at risk if there is no Gas Servicing Contract in place on 1 April 2006 it is impracticable to defer the decision on this report until after the operative date of the next Forward Plan on which it could appear. Accordingly the General Exception Procedure contained in Part 4 Section 2 Paragraph 18 of the Constitution has been invoked to enable its consideration. The Scrutiny Commissioners have been informed and public notice has been given by posting it at the Council Offices.
5. Key Decision
5.1Yes
6. Matter(s) for Consideration
6.1The authority has a duty of care as a Registered Social Landlord to carry out the servicing of all gas appliances in the properties within its ownership every 12 months. The authority will be at risk in terms of gas safety management in council homes and also will be failing in its legislative duty as a Social Landlord if it does not ensure that it has a Gas Servicing contract in place.
6.2The current contract for the carrying out of the necessary servicing expires on 31 March 2006. The authority will be in a risk situation if it does not have a suitable contract in place to carry out the necessary works on 1 April 2006. This is especially the case as the contract covers breakdown and repair.
6.3Since November 2005 the authority’s consultants, Technical Advisory Services (TAS) have been working with the authority to review and make recommendations for improvement in all aspects of gas servicing, installation and maintenance. Phase 1 of TAS’s contract encompassed all aspects of the auditing, record keeping, quality and safety management in relation to gas management, and this has now been completed. Work has recently begun on Phase 2. Phase 2 of the contract includes the review of specifications and contracts. TAS have made recommendations that will improve the service to the authority’s tenants including recommendations to alter the contract conditions of the gas servicing agreement.
6.4This will require the adoption of a new specification and also requires the authority to conform to its legislative responsibilities regarding tendering procedures. The new contract will require an OJEU notice to be placed and then tendered accordingly. This exercise will take time and the authority must ensure interim measures are in place to avoid a risk situation. It is for this reason that the recommendation is made to negotiate with the current contractor (William Freer Ltd) to provide the necessary interim cover.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.