DECISION To approve the findings of the and its related Improvement Plan as detailed at Appendix 1, 2 and 3 respectively attached to the report of the Acting Head of Housing Services and as summarised at 6.5. Reason for The reason for making the above recommendation is that the approval of the review and subsequent implementation of the Improvement Plan are intended to improve the effectiveness and efficiency of the service and enable the service to engage more effectively with value for money issues.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
Appendix 3: Best Value Review of Repairs and Maintenance: Improvement Plan
Task Output Target Date Milestone Outcome Lead Resources Comments Officer VFM/Investment Management/ Effective Use of Resources Complete HRA Agreed TBA with Draft May Strategic direction for HOH Staff time Business Plan Plan/GOEM GOEM service FFP Uplift SORs on New SOR April 2007 50% at Charges and costs are HWUTL HRA Savings basis of NHF June 2006 compatible – sustainable / IM figures HWU True market May 2008 Robust information for HOH HRA Achieve Market position of Transfer HOM Value HWU VFM known established Batched P4 End March None Historic backlog cleared HWUTL HRA building repairs 2006 backlog P4 Programme outsourced P4’s batched July 2006 Planned services HWUTL HRA on quarterly ongoing VFM Staff Time basis
Identify work to Planned June 2006 Revised ‘P’ Programmed works HWUTL HRA be included in programmes ongoing categories creating greater efficiency Staff Time Planned formulated agreed by maintenance Cabinet programme May 2006 2006/2007
V1 April 2006 1 Appendix 2
Consultancy November Improved gas safety IM HRA Completed Partnership 2005 management November 2005 Agreed with Improved contract TAS for gas specifications and electrical management Improved choice and economies of scale Payment Card TBC by Improved Service HWUTL HRA Modern system for Procurement Procurement materials Manager & supply Chain Partnering November See IM HRA Completed Management Contract for 2005 separate Gas Servicing Improveme nt Action Plan Windows & doors Contract Efficiency savings IM MRA Capital with London Programme Housing Consortium
SCS database Procure & May 2006 Accurate, robust IM MRA Capital managed to implement information HRO Programme inform capital updated Staff Time programme PIMMS module Formulate Three Programmes June 2006 Appropriately aligned IS MRA Capital Year Capital identified Capital Programmes Programme Programme Policy & May 2006 VFM IM HRA Asset procedures for Appropriately focussed MRA Management Asset service Management
V1 April 2006 2 Appendix 2
Communication June 2006 VFM IM HRA & Integrated & Information Effectively focused services PSTL General Fund procedures for sharing HWUTL Disabled protocol Adaptations established Review October 2006 Robust information HOM Staff Time services & Necessary amendments / HA charges improvements identified Cabinet January 2007 Appropriate endorsement of HOM Staff Time Leaseholder approval policy Management obtained Leaseholder April 2007 VFM HOM Staff Time management Improved Service HA policy & procedure in place Amendments August 2006 Appropriate amendments HOM Staff Time identified for service improvement HWUTL Changes October 2006 Appropriate endorsement of HOM Staff Time agreed by amendments Cabinet Review HWU Consultation November Ownership & understanding HOM Staff Time Structure carried out with 2006 – March for need for changes HWUTL relevant 2007 stakeholders
New structure April 2007 VFM HOM HRA implemented Improved service HWUTL
V1 April 2006 3 Appendix 2
Operational Issues Asbestos April 2006 Legislative Compliance IM HRA Completed Register Asbestos Policy and May 2006 Improved, consistent IM Staff Time Management procedures for management HRA management Establish May 2006 Robust information IM Staff Time register of relevant properties Procure testing May 2006 Effective VFM Service IM HRA Legionella services Management Devise testing May 2006 Legislatively compliant IS Staff Time programme service
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.