CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Blaby District Council
Audit Committee, Wednesday 27 June 2007

Internal Audit Progress Report - April to June 2007

Noted Finance 4 papers

Audit Committee noted this item on Wednesday 27 June 2007. Below is the council's own wording, with the papers it was decided on.

Item86

Resolved

DECISION That the Internal Audit report for the first quarter of the financial year 2007/2008 be noted. Reason: To enable the Audit Committee to monitor the work of the Internal Audit Section.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Audit Committee

Purpose of report

1.1To review the work of the Internal Audit section for the first quarter of the financial year 2007/2008.

Recommendation

2.1To note the Internal Audit report for the first quarter of the financial year 2007/2008.

3. Reason for Decision Recommended

3.1To enable the Audit Committee to monitor the work of the Internal Audit Section.

4. Forward Plan

Not applicable.

5. Key Decision

5.1Not applicable.

6. Matter(s) for Consideration

6.1Introduction

6.1.1 This report sets out progress in coverage of the quarterly audit plan and any matters arising for the Audit Committee to address.

6.2Progress against Quarterly Plan

6.16.2.1 Progress against the quarterly audit plan for the first quarter of 2007/08 is shown at Appendix A. Two additional audits (BVPIs and Staff and Member Conduct) were added to the plan and completed during the quarter replacing audits that have had to be deferred by agreement with management.

6.3Summary of Audit Report findings and recommendations

6.3.1 Appendix B lists final reports issued during the quarter with an executive summary and number of recommendations made and accepted. All reports that have been finalised were discussed with management and action plans agreed as necessary. There are no matters arising from the current audit reports that I specifically need to bring to the attention of Members of the Audit & Risk Committee.

6.4Quarterly Audit Plan for period July to September 2007

6.4.1 Appendix C shows reviews scheduled for the next period ending 30th September 2007.

6.5Implementation of recommendations

6.5.1 Although implementation of agreed recommendations is clearly the responsibility of management, Internal Audit can act as a prompt to management, by undertaking implementation reviews from time to time. At Blaby this is done every six months. The latest review (interim only) concluded that 86% of recommendations have been implemented and where practicable implementation dates for the remainder have been rescheduled.

6.6Fraud and Corruption and Theft

6.6.1 Members may recall that at the last Audit Committee meeting In March 2007, I drew their attention to an audit of a suspected irregularity involving invoices submitted by a housing works contractor. Subsequent investigations revealed that the Housing Service’s contract managing agent (Technical Advisory Services) had not given the contractor an approved schedule of rates to work to, had not carried out post work inspections to verify that work was up to a satisfactory standard or to independently confirm that invoiced materials were properly accounted for. Due to Internal Audit’s intervention, an overpayment of £10,461 to this contractor was prevented.

6.6.2 Recovery of overpayments made to another Housing works contractor is currently underway and an attempt is being made to seek reparation from the contract managing agent for any other unrecoverable losses and costs incurred. A further update on the position will be reported to the next Audit Committee.

6.7Conclusion

6.7.1 Internal Audit will continue to maintain and improve its performance and to work towards supporting the Council’s six corporate aims. 7. Other Options Considered

7.1None.

8. Appropriate Consultations

8.1Heads of Service and Service Managers.

9. Financial and Efficiency Implications

9.1None in the context of this report.

10. Exempt Information.

10.1None.

11. Appendices to this report

11.1Appendix A - Internal Audit Plan March – June 2007 11.2 Appendix B - Executive Summary of Final Audit reports and recommendations (March 2007 – June 2007) 11.3 Appendix C – Internal Audit Plan July – September 2007

12. List of Background Papers

12.1None.

The following Officer(s)/Member(s) have been consulted (identified by ): Head of Paid Service  S. 151 Officer Monitoring Officer Portfolio Holder (Cabinet Executive/Council reports only)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q1 2007-08Appendix A 11 KB Download
PDF
Q 1 2007-08Appendix B 22 KB Download
PDF
Q1 2007-08Appendix C 10 KB Download
PDF
Internal Audit Progress Report: April to June 2007Report 27 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 11 attended
JO
Councillor J. O. HudsonChairman, present
BM
Councillor B. M. ParkinsMember, present
JS
Councillor J. SpringthorpeMember, present
KD
Councillor K. D. ColesMember, present
JB
Councillor J. BlackwellVice-Chair, present
JB
Councillor. J. BellMember, present
JH
Mr J.L. HoldenOfficer, in attendance
JW
Mr J. WarlowOfficer, in attendance
MS
Mr M SpencerOfficer, in attendance
MB
Mr M. BerryOfficer, in attendance
JK
Councillor J. KenneyMember, apologies

On this subject at Blaby

Search all
  1. Internal Audit Progress Report - April to June 2007This decision
  2. Internal Audit Partnership ArrangementsApproved
  3. Shared Internal Audit ServiceApproved
  4. Recommendations of the Cabinet Executive - Shared Internal Audit ServiceApproved
  5. Shared Internal Audit ServiceApproved
  6. Internal Audit Progress Report October - December 2010Decided

More from Blaby Audit Committee

All decisions
MeetingDecisionOutcome
30 Jun 2011 Introduction to Audit and the Audit CommitteeIt was agreed that future dates for training for Members of the Audit Committee would be sought. Agreed Open
21 Dec 2010 Annual Audit LetterDECISION That the produced by PriceWaterhouseCooopers be acknowledged and its contents accepted. Reason: It is approp... Decided Open
21 Dec 2010 Use of ResourcesDECISION That the ‘’ assessment and the progress the Council has made be accepted. Reason: This assessment was carrie... Agreed Open
21 Dec 2010 Internal Audit Progress Report October - December 2010DECISION That the Internal Audit report for the third quarter of the 2010/2011 financial year be accepted. Reason: To... Decided Open
21 Dec 2010 Risk Management ReportDECISION That the Risk Management report be accepted. Reason: To enable the Audit Committee to monitor the management... Decided Open