Cabinet Executive, Monday 1 December 2008

Blaby Town Centre Masterplan

Approved Executive 2 papers

Cabinet Executive approved this item on Monday 1 December 2008. Below is the council's own wording, with the papers it was decided on.

Item301

Resolved

DECISIONS 1. That Cabinet Executive supports in principle the Blaby Town Centre Masterplan Report (October 2008) and in particular the four transformational projects recommended within the Masterplan Report. 2. That a new post of Part-Time Town Centre Manager for Blaby (18.5 hours a week), at S.P . 29 for a fixed term period of 2 years, (for which funding has been provided as part of the 2008/2009 budget process) be approved; 3. That the establishment of a Town Centre Implementation Group as a Partnership body with terms of reference to advise on and deliver the Masterplan projects be approved. 4. That priority should be given to improvements to the public realm, as outlined in Options 1 and 2 within the report of the Corporate Head of Policy & Partnerships. 5. That the preparation of a Blaby Town Centre Supplementary Planning Document based on the Masterplan be approved, subject to additional funding being secured to cover the costs. 6. That the Membership of the Steering Group be amended to replace the Portfolio Holder for Natural & Built Environment with the Portfolio Holder for Growth Development & Assets. Reasons: 1. A statement of support for the principles and proposals of the Masterplan will make it clear to the public, businesses, developers and other parties that the Council is committed to the regeneration of Blaby Town Centre. The projects recommended in the Masterplan would make a significant impact on the Town Centre and enable the Vision to be realised. 2. A Town Centre Manager would be a valuable resource to co-ordinate the work of the many individuals, businesses and other bodies which have an interest in the Town Centre. 3. An Implementation Group would seek to co-ordinate the work of the various parties involved by means of an Implementation Plan. 4. Improvements to the public realm could be undertaken in the short-term and may act as a stimulus to private sector investment. The options shown indicate the level of funding which may be required from this Council to deliver the recommendations. 5. Supplementary Planning Document status will place the Council in a stronger position when seeking to negotiate contributions for Town Centre Improvements from developers. 6. It is appropriate that the relevant Portfolio Holder is represented on the Steeering Group.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Cabinet Executive

Blaby Town Centre Masterplan 68 Masterplan Implementation Plan

APPENDIX 1

8. Priority Projects

8.1The Projects and Masterplan Section includes 25 projects, of varying scale and contribution to the Vision, some of which may not be able to be delivered within the next 15 years. This section summarises 12 Priority Projects, on which it is recommended that the Steering Group principally focus on. These should be seen as the minimum extent of projects that should be progressed to deliver comprehensive regeneration of the Town Centre. If these 12 projects are successfully delivered then it is believed that the Vision will be realised.

8.2The rationale for prioritising the projects has been explained in The Projects and Masterplan Section of this report. The 12 projects are all identified as either Transformational or High Priority Projects.

8.3The Transformational Projects are important as they will deliver real physical change that will enable perceptions of the Town Centre to be altered and provide new uses and destinations. All four Transformational Projects have been identified as Priority Projects.

8.4‘Early Wins’ are also important because they deliver change in a timescale that allow residents and users of the Town Centre to see that the Masterplan is being progressed and for confidence and momentum gained during the Consultation process to continue. Early Wins are projects that it is considered could be delivered within 2 years of inception. 6 Early Win projects have been identified. A further 2 are projects that have longer term elements but also elements within them which can be delivered as Early Wins. For more detail refer to the Masterplan Projects Matrix (figure 5.1)

8.5The 12 Priority Projects comprise:

Project Priority Timescale

D2.British Legion/ Sycamore Street/ Transformational Long The George

D3. John’s Court Transformational Long

D4. Bouskell Park Transformational Long

E1. Town Centre Core Transformational Early Win

D1. Sycamore Corner High Early Win Blaby Town Centre Masterplan 69 Masterplan Implementation Plan

E2. Blaby Gateways High Early Win

E4. The Pinfold High Early Win

E5. Jitties Enhancement High Early Win

A1. Car Parking Strategy High Early Win / Long

A4. Movement Pattern High Early Win / Medium / Long

N1. Blaby Day High Medium

N3. Town Centre Champion High Early Win

8.6For further detail on these Projects the relevant sections of this report should be consulted (Projects and Masterplan; Transport Strategy; Transformation Projects). The Masterplan Project Matrix also provides a useful summary.

8.7The ‘Making It Happen’ and ‘Next Steps’ sections provide detailed advice on viability and deliverability on all projects. In order to focus the mind, the table below summarises the initial actions required by the Steering Group for each of the 12 Priority Projects.

Project Key Initial Actions

A.1. Car Parking Strategy Consultation with Highways Authority.

Consultation with Town Centre Businesses

Prepare Car Parking Strategy document.

A.4. Movement Pattern Commission Traffic Modelling.

Consultation with Highways Authority.

D.1. Sycamore Corner Discussions with Blaby Art & Print.

Detailed Design and Specification.

D.2. British Legion/Sycamore Initial discussions with landowners.

Street/The George Prepare Development Brief. Blaby Town Centre Masterplan 70 Masterplan Implementation Plan

D.3. John’s Court Initial discussions with landowners.

Prepare Development Brief.

D.4. Bouskell Park Confirm land ownership and legal issues.

Ascertain potential funding sources

Discuss with LCC Museums, Arts and Records Service

Prepare Brief for Design Competition.

E.1. Town Centre Core Consultation with Highways Authority

Detailed Design and Specification

E.2. Blaby Gateways Consultation with Highways Authority.

Detailed Design and Specification.

E.4. The Pinfold Confirm land ownership.

Detailed Design and Specification.

E.5. Jitties Enhancement Confirm land ownership.

Detailed Design and Specification.

Highways Authority need to be consulted.

N1. Blaby Day Create organising committee.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A1: Blaby Town Centre MasterplanReport 92 KB DownloadRead as text
PDF
Blaby Town Centre MasterplanReport 71 KB Download

At this meeting

Whole meeting

Who was there

5 of 27 attended
EF
Councillor E. F. WhiteLeader, apologies
JO
Councillor J. O. HudsonDeputy Leader, present
DC
Councillor David ClementsMember, present
JA
Councillor J. A. DickinsonMember, present
GJ
Councillor Guy JacksonMember, present
GS
Councillor Gary SandersMember, apologies
EA
Councillor E. A. Webster-WilliamsMember, present
SW
Mrs Sandra WhilesOfficer, in attendance
JH
Mr J.L. HoldenOfficer, in attendance
JT
Jane TomanOfficer, in attendance
JL
Mr J. LeachOfficer, in attendance
VH
Mrs. V. HeathcoteOfficer, in attendance

All 27 on the meeting page

On this subject at Blaby

Search all
  1. Blaby Town Centre MasterplanThis decision
  2. Blaby Town Centre ImprovementsApproved
  3. Car Parking Petition - Blaby Town CentreDecided

More from Blaby Cabinet Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Quarter 1 Budget ReviewDECISIONS 1. That the financial performance against the budget for the quarter ending 30th June 2026 be accepted. 2. ... Approved Open
21 Sep 2026 Risk Management StrategyDECISION That the revised be adopted. Reasons: 1. The should be subject to regular review to ensure that it reflects ... Approved Open
21 Sep 2026 Quarter 1 Treasury Management Update 2026-27RECOMMENDATIONS TO COUNCIL 1. That the latest position in respect of treasury activities, and the prudential indicato... Approved Open
21 Sep 2026 Quarter 1 Capital Programme Review 2026-27RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2026/27, totallin... Approved Open
29 Jun 2026 Update on Local Government Reorganisation and Establishment of voluntary Joint CommitteesDECISIONS 1. That the current position regarding Local Government Reorganisation in Leicester, Leicestershire and Rut... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies