DECISIONS 1. That Cabinet Executive note the progress achieved towards delivering the 2008/9 Critical Projects as set out in the Council’s Corporate Plan. 2. That a further report be brought to Cabinet Executive once year end performance information is available so that the outcomes of activity can be assessed. Reason: It is important that Cabinet Executive maintain close attention to the delivery of the Councils improvement priorities so that they challenge the achievement of outcomes.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
CRITICAL ACTIVITIES FOR Currently DELIVERY 2008/09 AS behind DEFINED IN CORPORATE target PLAN Concerns
Updates to be put into document On Target Activity by the 3rd of each month to allow Lead Start Planned Revised complete Comments information to be processed and Date End End Current for 08/09 any issues highlighted and Date Date Situation (use (please discussed with your Director before the monthly Performance Board colour key) √) meeting.
Vision//Critical Activity
A CLEAN, ATTRACTIVE AND SUSTAINABLE ENVIRONMENT:
Ambition 1: The economy is prospering and prosperous Objective A: To retain and deliver job opportunities/employment land in the right locations to match housing growth and needs of residents 2. Carry out a research/employment land study John Leach Mar 2008 Jan 2009 √ Completed went to Cabinet January, 2009.
Ambition 2: It is easy to get about using sustainable, integrated transport networks CRITICAL ACTIVITIES FOR Currently DELIVERY 2008/09 AS behind DEFINED IN CORPORATE target PLAN Concerns
Updates to be put into document On Target Activity by the 3rd of each month to allow Lead Start Planned Revised complete Comments information to be processed and Date End End Current for 08/09 any issues highlighted and Date Date Situation (use (please discussed with your Director before the monthly Performance Board colour key) √) meeting.
Vision//Critical Activity
Objective A: Improved infrastructure to support use of public transport and reduce road congestion 1. Increase Narborough Station car Jon Wells parking facilities Sept 2008 End of Jan √ Project complete
2009 Objective B: Establish sustainable transport policies amongst major employers and service providers 1. Support local businesses, Jon Wells Jan Ongoing Travel Wise Event, including Blaby District Council, to put in place 2008 √ Climate Change Action Plan & approval of BDC Green Travel Plan effective sustainable by Cabinet. Actions being taken in transport (2008/11) accordance with approved Action Plan. Work being progressed through the Members Working Group. Objective C: Improve access to community transport service CRITICAL ACTIVITIES FOR Currently DELIVERY 2008/09 AS behind DEFINED IN CORPORATE target PLAN Concerns
Updates to be put into document On Target Activity by the 3rd of each month to allow Lead Start Planned Revised complete Comments information to be processed and Date End End Current for 08/09 any issues highlighted and Date Date Situation (use (please discussed with your Director before the monthly Performance Board colour key) √) meeting.
Vision//Critical Activity
1. Increase publicity for Jon Wells Nov Ongoing To be developed as part of BDC community transport and car schemes in an 2008 √ Green Travel Plan.
integrated way (2008/11) Objective E: Expand cycleway and footpath networks and encourage increased use 1, Ensure all large new Sept 2011(On Joined up working with planning developments have good quality, sustainable cycle way link and Martin Taylor 2008 going) √ Policy Team. Increased availability of pre-application advice. footpath networks to amenities, employment areas and community facilities (2008/11) 2. Promote use of existing network Jon Wells 2008 Ongoing Linked with LDF Framework & BDC and examine the feasibility of improving these (2008/11) √ Green Travel Plan
Ambition 3: The physical environment across the district makes people proud CRITICAL ACTIVITIES FOR Currently DELIVERY 2008/09 AS behind DEFINED IN CORPORATE target PLAN Concerns
Updates to be put into document On Target Activity by the 3rd of each month to allow Lead Start Planned Revised complete Comments information to be processed and Date End End Current for 08/09 any issues highlighted and Date Date Situation (use (please discussed with your Director before the monthly Performance Board colour key) √) meeting.
Vision//Critical Activity
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.